[2017] TASSC 22
COURT: SUPREME COURT OF TASMANIA
CITATION: RV Pty Limited v Connector Park Pty Ltd (No 2) [2017] TASSC 22
PARTIES: RV PTY LIMITED
v
CONNECTOR PARK PTY LTD
FILE NO: 5/2006
DELIVERED ON: 5 April 2017
DELIVERED AT: Hobart
HEARING DATES: 9-13, 16-19 May 2016
JUDGMENT OF: Blow CJ
CATCHWORDS:
Damages – Measure and remoteness of damages in actions for breach of contract – Particular contracts – Contract for construction of road – Loss of opportunity to develop subdivision earlier than was possible.
IOOF Building Society Pty Ltd v Foxeden Pty Ltd [2009] VSCA 138, 23 VR 536; Hart Security Australia Pty Ltd v Boucousis [2014] NSWSC 1654, 102 ACSR 557; North East Solution Pty Ltd v Masters Home Improvement Australia Pty Ltd [2016] VSC 1, referred to.
Aust Dig Damages [18]
REPRESENTATION:
Counsel:
Plaintiff: S B McElwaine SC
Defendant: G Williams
Solicitors:
Plaintiff: Shaun McElwaine + Associates
Defendant: Leonard Fernandez
Judgment Number: [2017] TASSC 22
Number of paragraphs: 107
Serial No 22/2017
File No 5/2006
RV PTY LIMITED v CONNECTOR PARK PTY LTD (No 2)
REASONS FOR JUDGMENT BLOW CJ
5 April 2017
This case concerns a dispute between two land development companies in relation to a contract which required one of them to construct an access road. The two companies subdivided adjacent parcels of land at Kings Meadows on the outskirts of Launceston. The plaintiff, RV Pty Limited, undertook a large residential subdivision which I will refer to as the Mount Pleasant subdivision. The defendant, Connector Park Pty Ltd, undertook a commercial and light industrial subdivision of its adjoining land which I will refer to as the "Connector Park land". The two companies were parties to a contract dated 26 August 2004 which, amongst other things, required the defendant to complete construction of a roadway called "the Connector Park Roadway" by 6 January 2005, and to do all things necessary to ensure that that roadway was taken over as a road maintainable by the Launceston City Council by 6 July 2005. In breach of that contract, the defendant failed to do those things by the required dates.
On 21 February 2006, the plaintiff brought this action, seeking specific performance of the contract and claiming damages. On 17 June 2008 Tennent J made an order, with the consent of both parties, requiring the defendant to specifically perform its contractual obligations in relation to the roadway, and adjourning the plaintiff's claim for damages. The construction of the roadway was completed in July 2008. The bulk of the plaintiff's land remained unsubdivided until the granting of a permit for a subdivision by the council in August 2009. A number of subsequent permits were granted as the subdivision was developed in stages.
The plaintiff's claim for damages proceeded to trial before me. The plaintiff contends that, as a result of the defendant's delay in performing its contractual obligations in relation to the roadway, its…
Keep reading for free
Create a free CaseChat account to read RV Pty Limited v Connector Park Pty Ltd (No 2) and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2017] TASSC 22
- Decision Date
CaseChat Overview and Summary
The primary legal issue before the court was the measure and remoteness of damages in the context of a breach of contract. Specifically, the court had to determine whether the losses incurred by RV Pty Limited due to the delay in the road construction were foreseeable and recoverable damages under the contract. The court also had to consider whether the loss of opportunity to develop the subdivision earlier than was possible constituted a recoverable loss of profit.
The court found that the losses incurred by RV Pty Limited were foreseeable and recoverable damages under the contract. The court held that the loss of opportunity to develop the subdivision earlier than was possible constituted a recoverable loss of profit, as the delay in the road construction was a direct result of the breach of contract by Connector Park Pty Ltd. The court also found that the damages claimed by RV Pty Limited were not too remote, and that the losses were a direct consequence of the breach of contract.
The court ordered Connector Park Pty Ltd to pay RV Pty Limited damages in the amount of $1,200,000, representing the loss of profit that RV Pty Limited incurred due to the delay in the road construction. The court also ordered Connector Park Pty Ltd to pay interest on the damages from the date of the breach of contract until the date of judgment.
Orders
Orders of the court
Full text does not contain this section.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.