Roluke Pty Ltd v Lamaro Consultants Pty Ltd

Link copied
Case Copied 57 min read

New South Wales


Court of Appeal


CITATION: Roluke Pty Ltd & Anor v Lamaro Consultants Pty Ltd & Anor [2008] NSWCA 323
HEARING DATE(S): 23 September 2008
 
JUDGMENT DATE: 

27 November 2008
JUDGMENT OF: Basten JA at 1; Campbell JA at 2; Sackville AJA at 3
DECISION: 1. Appeal allowed in part.
2. The parties file agreed short minutes of order within 14 days giving effect to the judgment herein and dealing with the costs of the appeal and of the trial.
3. In the absence of agreement, the appellants serve and file short minutes of order within 14 days (including orders relating to the costs of the appeal and the costs of the trial), together with a brief outline of submissions supporting the proposed orders.
4. If the appellants serve and file draft short minutes of order in accordance with Order 3, the respondents, within a further seven days, file and serve short minutes of order (including orders relating to the costs of the appeal and the costs of the trial), together with a brief outline of submissions supporting the proposed orders.
5. If the respondents wish to proceed with the summons for leave to appeal against the costs orders made by the primary Judge, the outline of submissions referred to in Order 4 should notify the Court of that intention.
CATCHWORDS: DAMAGES – negligent design of waterproof concrete slab by an engineer – measure of damages for breach of contract – whether terms of contract required a waterproof slab that would last for the life of the building or one that included a membrane requiring periodic repairs – whether primary Judge’s findings of fact on life expectancy of membrane and repairs to slabs were correct – whether owners of building entitled to damages for diminution in value of building where repairs had been satisfactorily completed
LEGISLATION CITED: Evidence Act 1995 (NSW)
CATEGORY: Principal judgment
CASES CITED: Auburn Municipal Council v ARC Engineering Pty Ltd [1973] 1 NSWLR 513
Bellgrove v Eldridge [1954] HCA 36; 90 CLR 613
Beregold Pty Ltd v Mitsopoulos (Supreme Court of New South Wales, 10 November 1992, unreported)
Bevan Investments Ltd v Blackhall and Struthers (No 2) [1978] 2 NZLR 97
Brown Falconer Group Pty Ltd v South Parklands Hockey & Tennis Centre Inc [2005] SASC 75
Costa v The Public Trustee of NSW [2008] NSWCA 223
Fox v Percy [2003] HCA 22; 214 CLR 118
Haines v Bendall [1991] HCA 15; 172 CLR 60
Skinner v Frappell [2008] NSWCA 296
State Rail Authority of New South Wales v Brown [2006] NSWCA 220
TEXTS CITED: A. Hudson and M. Lawrence, The Law of Building and Engineering Contracts : and of the Duties and Liabilities of Architects, Engineers and Surveyors, 7th ed, (1946) Sweet and Maxwell at 343
PARTIES: Roluke Pty Ltd (First Appellant)
Scotts Motors Artamon Pty Limited (Second Appellant)
Lamaro Consultants Pty Ltd (First Respondent)
Anthony Vincent Lamaro (Second Respondent)
FILE NUMBER(S): CA 40492/2007
COUNSEL:

Mr J Glissan QC (Appellants)

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Roluke Pty Ltd v Lamaro Consultants Pty Ltd and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2008] NSWCA 323
Decision Date

CaseChat Overview and Summary

Roluke Pty Ltd (the owner) appealed to the Court of Appeal of New South Wales against a decision of the primary judge concerning damages awarded against Lamaro Consultants Pty Ltd (the engineer) for negligent design of a waterproof concrete slab. The dispute centred on the measure of damages for breach of contract, specifically whether the contract required a slab that would remain waterproof for the life of the building or one that incorporated a membrane necessitating periodic repairs. The owner also challenged the primary judge's findings of fact regarding the expected lifespan of the membrane and the necessary repairs to the slabs, and whether the owner was entitled to damages for the diminution in the building's value despite the satisfactory completion of repairs.

The Court of Appeal was required to determine the correct measure of damages for the engineer's breach of contract. This involved interpreting the contractual obligations regarding the waterproof slab, specifically its expected durability and maintenance requirements. Furthermore, the court had to assess the correctness of the primary judge's factual findings concerning the life expectancy of the membrane and the extent of repairs required. A key legal issue was whether the owner could claim damages for the diminution in the building's value even after the defective elements had been repaired to a satisfactory standard.

The Court of Appeal allowed the appeal in part. While the precise reasoning is not detailed in the provided text, the outcome indicates that the court disagreed with the primary judge on some aspects of the damages assessment. The court directed the parties to file agreed short minutes of order within 14 days to give effect to its judgment, including provisions for the costs of the appeal and the trial. If agreement could not be reached, the appellants were to serve and file their proposed orders and submissions, with the respondents having a further opportunity to respond. The court also noted the possibility of the respondents seeking leave to appeal the primary judge's costs orders.

Orders

Orders of the court

1. Appeal allowed in part. 2. The parties file agreed short minutes of order within 14 days giving effect to the judgment herein and dealing with the costs of the appeal and of the trial. 3. In the absence of agreement, the appellants serve and file short minutes of order within 14 days (including orders relating to the costs of the appeal and the costs of the trial), together with a brief outline of submissions supporting the proposed orders. 4. If the appellants serve and file draft short minutes of order in accordance with Order 3, the respondents, within a further seven days, file and serve short minutes of order (including orders relating to the costs of the appeal and the costs of the trial), together with a brief outline of submissions supporting the proposed orders. 5. If the respondents wish to proceed with the summons for leave to appeal against the costs orders made by the primary Judge, the outline of submissions referred to in Order 4 should notify the Court of that intention.

Background

Background to the litigation

Full text does not contain this section.

Evidence

Evidence Before The Court

Full text does not contain this section.

Decision

Reasons for decision

Full text does not contain this section.

Ratio Decidendi

Legal Principle Established

Full text does not contain this section.