FEDERAL COURT OF AUSTRALIA
Rimfire Energy Pty Ltd v BSF Co Pty Ltd (No 2) [2025] FCA 384
File number(s): VID 201 of 2023 Judgment of: O’CALLAGHAN J Date of judgment: 22 April 2025 Catchwords: CONTRACTS – whether, under Power Purchase Agreements (PPAs) for the construction of two facilities in the Northern Territory and the supply of electricity from those facilities, the Owners gave to the Buyer valid notices of extension of time to the Target Commercial Operation Date of the facilities – whether the Buyer was entitled to liquidated damages – held that the notices of extension of time were invalid and the Buyer is entitled to payment of liquidated damages and interest calculated under the PPAs
CONSUMER LAW – alternative claim under s 21 of the Australian Consumer Law, being Schedule 2 of the Competition and Consumer Act 2010 (Cth) – where no utility in dealing with claim
Legislation: Competition and Consumer Act 2010 (Cth), Sch 2, Australian Consumer Law s 21
Power and Water Corporation Act 1987 (NT) s 4
Cases cited: Australian Development Corporation Pty Ltd v White Constructions (ACT) Pty Ltd (1996) 12 BCL 317
Jennings Construction Ltd v QH & M Birt Pty Ltd (1986) 8 NSWLR 18
Lucas Earthmovers Pty Limited v Anglogold Ashanti Australia Limited [2019] FCA 1049
Division: General Division Registry: Victoria National Practice Area: Commercial and Corporations Sub-area: Commercial Contracts, Banking, Finance and Insurance Number of paragraphs: 91 Date of hearing: 31 March 2025 and 1 April 2025 Counsel for the Applicant: K A O’Gorman SC with K Butler Solicitor for the Applicant: Mills Oakley Lawyers Counsel for the Respondent: A Di Pasquale Solicitor for the Respondent: DLA Piper ORDERS
VID 201 of 2023 BETWEEN: RIMFIRE ENERGY PTY LTD
Applicant
AND: BSF CO PTY LTD AS TRUSTEE FOR THE TRUST CONSTITUTED BY THE TRUST DEED DATED 30 AUGUST 2019
First Respondent
HCPS CO PTY LTD AS TRUSTEE FOR THE TRUST CONSTITUTED BY THE TRUST DEED DATED 30 AUGUST 2019
Second Respondent
ORDER MADE BY:
O’CALLAGHAN J
DATE OF ORDER:
22 APRIL 2025
THE COURT ORDERS THAT:
1.The parties file a minute of draft orders to give effect to these reasons.
2.If the parties cannot agree on the question of costs:
(a)the applicant file written submissions not exceeding three pages within 7 days of the date of these orders; and
(b)the respondents file written submissions not exceeding three pages 7 days thereafter.
Note: Entry of orders is dealt with in Rule 39.32 of the Federal Court Rules 2011 (Cth).
REASONS FOR JUDGMENT
O’CALLAGHAN J
INTRODUCTION
The dispositive question the subject of this proceeding turns on the proper construction of two Power Purchase Agreements (PPAs), namely the “Power Purchase Agreement – Batchelor Solar Farm” dated 27 February 2020 (the Batchelor PPA) and the “Power Purchase Agreement – Hudson Creek Power Station” dated 18 February 2020 (the Hudson Creek PPA).
The applicant, Rimfire Energy…
Keep reading for free
Create a free CaseChat account to read Rimfire Energy Pty Ltd v BSF Co Pty Ltd (No 2) and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2025] FCA 384
- Decision Date
CaseChat Overview and Summary
The key legal issues were whether the notices of extension of time provided by the respondents were valid and if the applicant was entitled to the liquidated damages and interest as specified in the PPAs. The court examined the terms of the PPAs and the extension of time notices. It found that the notices did not comply with the requirements of the PPAs and thus were invalid. As a result, the respondents could not rely on them to extend the Target Commercial Operation Dates. The court also considered an alternative unconscionability claim under the Australian Consumer Law, which it found had no utility.
The court ruled that the notices of extension of time were invalid and that the applicant was entitled to the liquidated damages and interest as per the PPAs. The court's interpretation of the PPAs and the extension of time notices was that the respondents had not met the criteria for extending the Target Commercial Operation Dates. Consequently, the applicant was entitled to the full amount of liquidated damages and interest claimed, as per the terms of the PPAs.
The orders of the court were that the parties file a minute of draft orders to give effect to the reasons for the judgment. If the parties could not agree on the costs, the applicant would file written submissions within seven days, followed by the respondents' submissions seven days later. This was to be dealt with under Rule 39.32 of the Federal Court Rules 2011 (Cth).
Orders
Orders of the court
1. The parties file a minute of draft orders to give effect to these reasons.
2. If the parties cannot agree on the question of costs:
(a) the applicant file written submissions not exceeding three pages within 7 days of the date of these orders; and
(b) the respondents file written submissions not exceeding three pages 7 days thereafter.
Note: Entry of orders is dealt with in Rule 39.32 of the Federal Court Rules 2011 (Cth).
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
The first respondent, BSF Co Pty Ltd, is the Owner under the Batchelor PPA and is licensed to generate electricity. Pursuant to the Batchelor PPA, the first respondent agreed to develop and construct a 10MW solar farm near Batchelor, approximately 100 km south of Darwin, and the applicant agreed to purchase all electricity there generated. The Batchelor PPA set the “Target Commercial Operation Date” for the solar farm as 30 June 2021, “[s]ubject to an extension of time”. The second respondent, HCPS Co Pty Ltd, is the Owner under the Hudson Creek PPA and is also licensed to generate electricity. Pursuant to the Hudson Creek PPA, the second respondent agreed to develop and construct a 12MW gas fired power station close to the Hudson Creek Terminal Station in Darwin, and the applicant agreed to purchase all electricity generated by that power station. The Hudson Creek PPA set the Target Commercial Operation Date as 1 July 2021, again “[s]ubject to an extension of time”. As at the date of this judgment, neither the Batchelor solar farm nor the Hudson Creek power station has commenced operating. On 21 November 2022, the applicant issued to each of the respondents an invoice for liquidated damages on the basis that the respondents had failed to achieve the “Commercial Operation Date” by the Target Commercial Operation Date under each PPA. The invoice in respect of the Batchelor solar farm was for $365,000. The invoice in respect of the Hudson Creek power station was for $1,035,000. Following my judgment in Rimfire Energy Pty Ltd v BSF Co Pty Ltd [2024] FCA 602 (Rimfire No 1), the respondents paid 50% of those invoices on the interim basis that I ruled was contemplated by the PPAs. More recently, the applicant submitted that it is entitled to retain that amount and that the respondents are liable to pay the other 50%, plus interest calculated under the PPAs. It also faintly pressed an alternative unconscionability claim under the Australian Consumer Law (ACL), being Schedule 2 of the Competition and Consumer Act 2010 (Cth). The respondents disputed the invoices and submitted that the applicant must repay the sums already paid to it, on the basis that the respondents are not liable to pay any sum under the invoices because the respondents had validly extended the Target Commercial Operation Date pursuant to three extension of time notices (EOTs or EOT claims) issued pursuant to cl 5 of the PPAs. The applicant contended that the EOTs were invalid, that the respondents are not entitled to the claimed extension of time to the Target Commercial Operation Date and that the respondents are thus liable to pay the maximum amount of liquidated damages provided for in the PPAs (being the sums claimed in the invoices). As I have already said, the resolution of the dispute involves the proper construction of the relevant terms of the PPAs and the EOTs purportedly issued under them. For the reasons set out below, the applicant’s construction of cl 5 of the PPAs and the EOTs is correct, and it is entitled to the amount of liquidated damages it seeks, together with interest at the rate contemplated by the PPAs.