FEDERAL COURT OF AUSTRALIA
Rimfire Energy Pty Ltd v BSF Co Pty Ltd [2024] FCA 602
File number(s): VID 201 of 2023 Judgment of: O’CALLAGHAN J Date of judgment: 7 June 2024 Catchwords: CONTRACTS – determination of separate questions pursuant to r 30.01 of the Federal Court Rules 2011 (Cth) – where answers to separate questions turned on proper construction of “Power Purchase Agreements” (PPAs) – whether the court needed to determine the validity of the respondents’ “extension of time” claims under the PPAs to determine whether 50% of invoiced amounts of liquidated damages is payable – whether applicant had proven that 50% of invoiced amounts of liquidated damages is payable Legislation: Competition and Consumer Act 2010 (Cth) sch 2
Federal Court Rules 2011 (Cth) r 30.01(1)
Building and Construction Industry Security of Payment Act 2002 (Vic)
Building and Construction Industry Security of Payment Act 1999 (NSW)
Cases cited: Electricity Generation Corporation v Woodside Energy Ltd (2014) 251 CLR 640
Mount Bruce Mining Pty Ltd v Wright Prospecting Pty Ltd (2015) 256 CLR 104
Division: General Division Registry: Victoria National Practice Area: Commercial and Corporations Sub-area: Commercial Contracts, Banking, Finance and Insurance Number of paragraphs: 76 Date of hearing: 4 April 2024 Counsel for the Applicant: KA O’Gorman SC with K Butler Solicitor for the Applicant: Mills Oakley Lawyers Counsel for the Respondents: A Di Pasquale Solicitor for the Respondents: DLA Piper ORDERS
VID 201 of 2023 BETWEEN: RIMFIRE ENERGY PTY LTD
Applicant
AND: BSF CO PTY LTD AS TRUSTEE FOR THE TRUST CONSTITUTED BY THE TRUST DEED DATED 30 AUGUST 2019
First Respondent
HCPS CO PTY LTD AS TRSUTEE FOR THE TRUST CONSTITUTED BY THE TRUST DEED DATED 30 AUGUST 2019
Second Respondent
ORDER MADE BY:
O’CALLAGHAN J
DATE OF ORDER:
7 JUNE 2024
THE COURT ORDERS THAT:
1.The separate questions ordered to be heard and determined separately by order made on 14 March 2024 (Orders) be answered as follows:
(a)Question 1: On the proper construction of the Batchelor PPA (as defined in paragraph 3 of the Applicant’s Concise Statement dated 4 April 2023 (the Concise Statement)) and the Hudson Creek PPA (as defined in paragraph 13 of the Concise Statement), does the Court need to determine the validity of each or any of the extension of time claims set out in Annexure A to the Orders in order to determine whether 50% of the invoiced amount of liquidated damages, in the invoices issued by the Applicant to the relevant Respondent set out in Annexure B to the Orders, is payable under cl 12.4(a) of the Batchelor PPA and cl 11.4(a) of the Hudson Creek PPA? Answer: No.
(b)Question 2: If the answer is no, has the Applicant proven that 50% of the invoiced amount of liquidated damages is payable (pending determination of the final trial) under cl 12.4(a) of the Batchelor PPA and cl 11.4(a) of the Hudson Creek PPA? Answer:
Keep reading for free
Create a free CaseChat account to read Rimfire Energy Pty Ltd v BSF Co Pty Ltd and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2024] FCA 602
- Decision Date
CaseChat Overview and Summary
The court needed to decide if the validity of the respondents’ extension of time claims was necessary to determine whether 50% of the invoiced liquidated damages was payable under the PPAs. The court considered the terms of the PPAs, specifically clauses 12.4(a) of the Batchelor PPA and 11.4(a) of the Hudson Creek PPA, which provided for payment of 50% of the disputed amount if the paying party did not give a notice of dispute within the specified timeframe. The court found that the validity of the extension of time claims was not a prerequisite to determining whether 50% of the liquidated damages was payable. The court held that the applicant had proven its entitlement to the interim payment of 50% of the invoiced liquidated damages.
The court answered the separate questions accordingly, determining that the validity of the respondents’ extension of time claims was not necessary to determine whether 50% of the invoiced liquidated damages was payable. The court found that the applicant had proven its entitlement to the interim payment of 50% of the invoiced liquidated damages. The proceeding was listed for further hearing on a date to be fixed, with the parties to liaise with the court to convene a case management hearing. The court ordered that the separate questions be answered as follows: (a) the validity of the respondents’ extension of time claims was not a prerequisite to determining whether 50% of the liquidated damages was payable; and (b) the applicant had proven its entitlement to the interim payment of 50% of the invoiced liquidated damages.
Orders
Orders of the court
1. The separate questions ordered to be heard and determined separately by order made on 14 March 2024 (Orders) be answered as follows:
(a) Question 1: On the proper construction of the Batchelor PPA (as defined in paragraph 3 of the Applicant’s Concise Statement dated 4 April 2023 (the Concise Statement)) and the Hudson Creek PPA (as defined in paragraph 13 of the Concise Statement), does the Court need to determine the validity of each or any of the extension of time claims set out in Annexure A to the Orders in order to determine whether 50% of the invoiced amount of liquidated damages, in the invoices issued by the Applicant to the relevant Respondent set out in Annexure B to the Orders, is payable under cl 12.4(a) of the Batchelor PPA and cl 11.4(a) of the Hudson Creek PPA? Answer: No.
(b) Question 2: If the answer is no, has the Applicant proven that 50% of the invoiced amount of liquidated damages is payable (pending determination of the final trial) under cl 12.4(a) of the Batchelor PPA and cl 11.4(a) of the Hudson Creek PPA? Answer: Yes.
2. The proceeding be listed for further hearing on a date to be fixed.
Note: Entry of orders is dealt with in Rule 39.32 of the Federal Court Rules 2011.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Ratio Decidendi
Legal Principle Established
Schedule 5 is in the following terms:Liquidated damages for failure to achieve the Target Commercial Operation DateThe amount payable by the Owner under clause 6.1 is equal to $5,750, multiplied by the number of days by which the Commercial Operation Date is delayed beyond the Target Commercial Operation Date, up to the earliest to occur of:(a) the Commercial Operation Date;(b)the date on which the aggregate amount paid or payable by the Owner under clause 6.1 equals or exceeds $1,035,000; and(c) the date of termination of this document.(The amounts in the equivalent schedule of the Batchelor PPA are $2000 and $365,000 respectively.) It was accepted by both parties that schedule 5 incorrectly refers to clause 6.1, and should be read as referring to the liquidated damages provision in clause 6.2. (This error is replicated in the Batchelor PPA.) The effect of clause (b) in schedule 5 is that the maximum liquidated damages payable under clause 6.2 is capped at six months after the Target Commercial Operation Date. The invoices issued by the applicant to the respondents on 21 November 2022 are for the six-month maximum liquidated damages amounts payable under each PPA. Clause 11.2, under the heading “Invoices”, provides:(a)The Owner (Invoicing Party) must prepare and submit to the Buyer (Paying Party), within fifteen Business Days after the end of each Billing Period, an invoice setting out each Charge due from the Buyer to the Owner and details how such Charges are calculated (Invoice).(b)In respect of any other amount payable by one party (Invoicing Party) to the other party (Paying Party) under this document, the Invoicing Party must deliver to the Paying Party as soon as practicable an invoice (Invoice) for the amount payable under this document. (The equivalent clause in the Batchelor PPA is clause 12.2.) Clause 11.4, under the heading “Payment and disputes”, relevantly provides that:(a)On or before 30 days after the end of each Billing Period, the Paying Party must either:(i) pay to the Invoicing Party the amount of the Invoice; or(ii) if the Paying Party bona fide disputes any part of the Invoice:(1)give to the Invoicing Party a notice stating the part disputed and the reason for the dispute; and(2)pay to the Invoicing Party the undisputed amount of the Invoice plus 50% of the disputed amount.(b)Promptly after a notice pursuant to clause 11.4(a)(ii)(1) is received by the Invoicing Party, the parties will negotiate with a view to resolving the dispute. If parties fail to agree by the date which is five Business Days after the date the notice is received by the Invoicing Party, either party may give a Dispute Notice pursuant to clause 27.(c)Subject to clause 11.4(d), if the Paying Party does not give a notice of dispute in accordance with clause 11.4(a)(ii)(1), the Paying Party is deemed to have accepted the Invoicing Party’s calculations of the amounts included in the relevant Invoice … (The equivalent clause in the Batchelor PPA is clause 12.4.)