Rainforest Reserves Australia Inc v Minister for the Environment and Water

Link copied
Case Copied 74 min read

FEDERAL COURT OF AUSTRALIA

Rainforest Reserves Australia Inc v Minister for the Environment and Water [2025] FCA 532

Review of: Decision dated 17 June 2024 (EPBC 2021/9066)
File number(s): VID 837 of 2024
Judgment of: SHARIFF J
Date of judgment: 22 May 2025
Catchwords: ENVIRONMENTAL LAW – where a delegate of the Minister for the Environment and Water granted an approval under ss 130(1) and 133(1) of the Environment Protection and Biodiversity Conservation Act 1999 (Cth) (EPBC Act) to construct, operate and decommission wind turbine generators for a project known as the Gawara Baya Wind Farm (Wind Farm) – where Wind Farm to be located adjacent to but outside the UNESCO-listed Wet Tropics World Heritage Area in North Queensland that is home to various species of protected or endangered species of birds and bats
ADMINISTRATIVE LAW – whether s 140 of the EPBC Act creates a jurisdictional fact essential to the exercise of power under ss 130(1) and 133(1) – whether non-compliance with s 140 invalidates a decision made under ss 130(1) and 133(1) of the EPBC Act – whether approval decision involved an improper exercise of power on the basis that it was uncertain within the meaning of ss 5(1)(e) and 5(2)(h) of the Administrative Decisions (Judicial Review) Act 1977 (Cth) – Held: grounds of review not established
PUBLIC INTERNATIONAL LAW – whether the approval decision is inconsistent with Australia’s bilateral treaty obligations with Japan, China and the Republic of Korea (Specified Bilateral Treaties) – where Specified Bilateral Treaties relevantly provide that each nation-state party shall prohibit the “taking” of protected migratory birds and their eggs – whether an innocent, negligent or reckless act which results in the death of migratory birds involves “taking” those birds in a manner inconsistent with the obligations in the Specified Bilateral Treaties – whether the approval of the Wind Farm involves a “taking” of migratory birds protected by Specified Bilateral Treaties – interpretation of multi-lingual bilateral treaties – meaning of the word “taking” – relevance of dictionary definitions in the interpretation of multi-lingual bilateral treaties – where text, context and purpose relevant to the interpretation of the Specified Bilateral Treaties – Held: – decision to approve the Wind Farm is not inconsistent with Specified Bilateral Treaties – application dismissed
Legislation:

Administrative Decisions (Judicial Review) Act 1977 (Cth) ss 5(1)(e), 5(1)(h), 13(1)

Environment Protection and Biodiversity Conservation Act 1999 (Cth) ss 3, 12, 13A, 15A, 15B, 15C, 16, 17B, 18, 18A, 20, 20A, 67, 67A 68, 75, 76, 77, 82, 87, 96A, 98, 99, 100, 130, 133, 134, 136, 137A, 138, 139, 140, 140A, 156A, 156B, 156D, 209, 316, 321, 428, 523

Judiciary Act 1903 (Cth) s 39B

Migratory Bird Treaty Act 1918, 16 USC § 703

Agreement between the Government of Australia and the Government of the Republic of Korea on the Protection of Migratory Birds, 6 December 2006, Australia–South Korea, 2483 UNTS 459 arts 2, 4, 5, 6 (entered into force 13 July 2007) (ROKAMBA)

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Rainforest Reserves Australia Inc v Minister for the Environ... and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2025] FCA 532
Decision Date

CaseChat Overview and Summary

Rainforest Reserves Australia Inc, an environmental charity, sought judicial review of a decision by the Minister for the Environment and Water to approve the construction, operation, and decommissioning of wind turbine generators for the Gawara Baya Wind Farm, located near the UNESCO-listed Wet Tropics World Heritage Area in North Queensland. The charity contended that the approval would harm endangered and protected species of birds and bats, and that it contravened Australia’s international obligations under specified bilateral treaties with Japan, China, and the Republic of Korea, which prohibit the "taking" of protected migratory birds and their eggs. The key issues for the court to decide were whether the approval was inconsistent with Australia’s international obligations, whether the approved actions exceeded those proposed, and whether certain conditions attached to the approval rendered the decision uncertain.

The court examined these issues in detail. Regarding the international obligations, the court held that the approval did not contravene Australia’s treaty obligations because the treaties did not explicitly prohibit the incidental death of birds caused by wind turbines. The court also concluded that the approval did not exceed the actions proposed to the Minister, and that the conditions attached to the approval were not uncertain as they were clear and necessary for mitigating potential harm to protected species. The court found that the decision was properly exercised within the statutory framework of the EPBC Act, and that the concerns raised by the applicant did not establish any grounds for judicial review.

The court dismissed the application, finding that the grounds for review were not established. It directed the parties to file submissions on the question of costs, with specific deadlines for filing and serving those submissions. The court further noted that the costs would be determined on the papers unless a party requested a hearing.

Orders

Orders of the court

1. The amended originating application be dismissed.

2. On or by 5 pm on 29 May 2025, the respondents file and serve submissions on the question of costs (to the extent that the respective respondents seek their costs of the proceedings) with any such submissions not to exceed 5 pages.

3. On or by 5 pm on 5 June 2025, the applicant file and serve submissions in reply on the question of costs with such submissions not to exceed 5 pages.

4. On or by 5 pm on 12 June 2025, the respondents file and serve submissions in reply to any submissions filed by the applicant under order 3 with such submissions not to exceed 5 pages.

5. The question of costs be determined on the papers unless one or more of the parties indicate to the court by 12 pm on 16 June 2025 that they wish to be heard on the question of costs.

Note: Entry of orders is dealt with in Rule 39.32 of the Federal Court Rules 2011.

Background

Background to the litigation

Evidence

Evidence Before The Court

Decision

Reasons for decision

On 17 June 2024, a delegate of the Minister made a decision to grant approval to the Proponent (the Approval Decision) to construct, operate and decommission the Wind Farm pursuant to ss 130(1) and 133(1) of the Environment Protection and Biodiversity Conservation Act 1999 (Cth) (EPBC Act) but subject to certain conditions specified in Annexure A of the decision (the Conditions). The applicant is a not-for-profit environmental charity. It holds concerns that the operation of the WTGs at the proposed Wind Farm will kill, injure or disturb endangered or protected species of birds and bats. It says, amongst other things, that the approval of the Wind Farm amounts to the “taking” of migratory bird species in a manner that is inconsistent with Australia’s obligations under specified international treaties which are protected by the EPBC Act. By a further amended original application, the applicant seeks relief pursuant to s 5 of the Administrative Decisions (Judicial Review) Act 1977 (Cth) (ADJR Act) and s 39B of the Judiciary Act 1903 (Cth). By the time of the hearing before me, the applicant narrowed its case such that it raised the following issues for determination:(a)whether the Approval Decision is inconsistent with Australia's international obligations for the purposes of s 140 of the EPBC Act and, therefore, invalid because s 140 gives rise to a jurisdictional fact that must be established as a matter of objective fact or because that provision is otherwise jurisdictional such that non-compliance with it gives rise to invalidity: Ground 1 (the Migratory Species Ground);(b)whether the “action” that was approved went beyond the action that was referred to the Minister by the Proponent: Ground 3 (the Baseline Measures Ground); and(c)whether certain Conditions make the Approval Decision uncertain (the Uncertainty Grounds), specifically: (i)whether the "impact trigger threshold" definitions and conditions contained in the Approval Decision are uncertain: Ground 5 (the Impact Trigger Threshold Issue); and(ii)whether certain other conditions contained in the Approval Decision that provide for further Ministerial approval to be obtained are uncertain in that they give rise to a “secondary consent” process: Grounds 6 and 7 (the Further Ministerial Approval Issues). For the reasons set out below, the further amended originating application should be dismissed and I will hear the parties on the question of cost. For convenience, I have structured my reasons as follows: (a)Part 2 sets out the salient aspects of the applicable statutory scheme;(b)Part 3 summarises the relevant facts;(c)Part 4 addresses the Migratory Species Ground; (d)Part 5 addresses the Baseline Measures Ground; (e)Part 6 address the Uncertainty Grounds; and (f)Part 7 sets out my conclusion.2. THE SALIENT ASPECTS OF THE STATUTORY SCHEME The objects of the EPBC Act are identified in s 3(1) and relevantly include the protection of the environment, especially matters of national environmental significance (MNES) (s 3(1)(a)), the promotion of ecologically sustainable development (s 3(1)(b)), the promotion of a co-operative approach to the protection and management of the environment involving governments, the community, land-holders and indigenous peoples (s 3(1)(d)) and assisting in the co-operative implementation of Australia’s international environmental responsibilities (s 3(1)(e)).

Ratio Decidendi

Legal Principle Established

As these authorities demonstrate, the question of whether the result of the relevant exercise of power is uncertain is to be determined by a process of statutory construction. It is therefore necessary to consider each of the applicant’s arguments on the Uncertainty Grounds by reference to these principles.6.2.1Consideration of Impact Trigger Threshold Issue In assessing whether the “impact trigger thresholds” involve an exercise of power that results in uncertainty, it is necessary not only to consider the relevant power in question but also to properly construe the Conditions relating to these thresholds. Section 134(1) empowers the Minister to attach a condition to the approval of action if the Minister is satisfied that the condition is “necessary or convenient” for, amongst other things, “repairing or mitigating damage to a matter protected by a provision of Part 3 for which the approval has effect…”. The Conditions relating to the “impact trigger thresholds” were such conditions, which the Minister’s delegate was satisfied should be imposed. For example, in relation to the Red Goshawk, the Delegate’s Reasons disclose (at [215]) that the delegate considered the measures proposed in the draft BBMP were appropriate by way of risk management and that conditions should be imposed to that effect:215. I considered that the proponent’s proposed adaptive management approach in the draft BBMP would adequately manage the impacts of WTG collision, and should the significant impact threshold be reached, appropriate measures to compensate would be implemented. To ensure such, I agreed to impose specific conditions relating to the requirements of the final BBMP, as well as conditions to limit turbine impacts. The delegate was further satisfied that such conditions were necessary and convenient for the reasons set out at [222]–[223]:222.I agreed that these conditions were necessary, and appropriately reflected and applied the precautionary principle given the threat or serious damage to the species by way of reduction of the population, and the lack of scientific certainty as to the presence and extent of the species in the project area and the use of the habitat by the species.223. The department also recommended, and I accepted, including conditions that require the proponent to cease the rotation of the WTG blades if 1 or more red goshawk individuals are estimated to be killed by collision with the WTGs in a given year. I noted that the trigger for the red goshawk had been clarified to be just 1 individual due to the small population number, vulnerability of the species and feedback from DESI. The conditions also required the proponent to promptly report any exceedance to the department and undertake an ‘Impact Trigger Avoidance Review’… In relation to the other species, the Delegate’s Reasons disclose a similar process of reasoning. For example, in relation to the Bare-rumped Sheathtail, the delegate reasoned that:248.For similar reasons that I gave at paragraphs [223]–[226] above relating to the red goshawk, I considered conditions relating to managing impacts from WTG collision, including the preparation of a BBMP which I considered would adequately address such impacts and offsets, were necessary for the protection of the bare-rumped sheathtail bat. I also considered that the impact trigger thresholds which strengthened the additional measures were appropriate.249. In relation to the bare-rumped sheathtail bat the department specifically recommended, and I accepted, a condition as follows:a) To avoid impacts to Bare-rumped Sheathtail breeding, the Approval Holder must not clear bare-rumped sheathtail bat habitat in any period commencing on 1 December and ending on 31 January in the same financial year.250. The department considered and I agreed that this condition is necessary and convenient to protect bare-rumped sheathtail bats during breeding season when the species is most vulnerable to disturbance.