QUEENSLAND CIVIL AND
ADMINISTRATIVE TRIBUNAL
CITATION:
Rainbow v Turkovic & anor [2021] QCAT 441
PARTIES:
BLAIR RAINBOW
(applicant)
v
ED TURKOVIC
MICHELLE GROGAN(respondents)
APPLICATION NO/S:
BDL271-19
MATTER TYPE:
Building matters
DELIVERED ON:
20 December 2021
HEARING DATE:
1 February 2021
2 February 2021
FURTHER SUBMISSIONS:
26 February 2021; 12 March 2021; 26 March 2021; 9 April 2021; 16 April 2021
HEARD AT:
Brisbane
DECISION OF:
Member Traves
ORDERS:
1. On the application for a domestic building dispute filed by Blair Rainbow, Ed Turkovic and Michelle Grogan pay to Blair Rainbow the sum of $65, 019.11.
2. On the cross-application filed by Ed Turkovic and Michelle Grogan:
(i) Blair Rainbow pay to Ed Turkovic and Michelle Grogan the sum of $30, 346.27, by way of damages for negligence; and
(ii) Blair Rainbow pay to Ed Turkovic and Michelle Grogan the sum of $6, 501.55, by way of restitution for money paid under a mistake of fact.
3. In the premises of order 1 and 2 hereof, the net sum payable by Ed Turkovic and Michelle Grogan to Blair Rainbow is the sum of $28, 171.29. This sum must be paid, by:
4:00pm on 28 January 2022.
4. The parties must file and serve any submissions seeking costs by 4:00pm on 11 February 2022.
5. The parties must file and serve any submissions as to costs in reply by 4:00pm on 25 February 2022.
6. Unless otherwise ordered, any application for costs will be determined by the Tribunal on the papers on the basis of the parties’ written submissions and without an oral hearing, not before 4:00pm on 25 February 2022.
CATCHWORDS:
CONTRACTS – BUILDING, ENGINEERING AND RELATED CONTRACTS – REMUNERATION – RECOVERY ON QUANTUM MERUIT – IN GENERAL – where Owners engaged builder to complete renovations to their home on a cost plus basis – where no contract signed – where non-compliance with s 13(2) of Schedule 1B of the Queensland Building and Construction Commission Act 1991 (Qld) whether contract of no effect – whether builder entitled to recover on quantum meruit – whether evidence of fair and reasonable value of work – whether evidence of market price of labour and materials necessary
BUILDING DISPUTE - NEGLIGENCE – whether builder owed a duty of care to Owners - whether builder breached duty of care – whether Owners suffered material damage caused by builder’s breach of duty – where damages to be assessed – where purpose of damages to restore Owners to position they would have been in had wrongful acts not occurred – whether evidence of damages claimed
RESTITUTION – whether Owners entitled to recover money wrongly paid to builder on basis of mistake
Electronic Transactions (Queensland) Act 2001 (Qld), s 14
Queensland Building and Construction Commission Act 1991 (Qld), s 77, Sch 1B, s 13(5)
Australia and New Zealand Banking Group Ltd v Westpac Banking Corporation (1988) 164 CLR 662
Bryan v Maloney (1995) 182 CLR 609
Mann v Paterson Constructions Pty Ltd (2019) 267 CLR 560
Pavey &…
Continue reading Rainbow v Turkovic
Sign in free to access the full text
- AGLC
- Rainbow v Turkovic [2021] QCAT 441
- Case
- [2021] QCAT 441
- Decision Date
CaseChat Overview and Summary
The central legal issues in this case were whether Mr Rainbow was liable for damages for the negligent works performed and whether the plaintiffs were entitled to a restitutionary claim for the overpayments made. The plaintiffs argued that Mr Rainbow's works were defective and that they had overpaid him for work that was never performed. Mr Rainbow, on the other hand, contended that he had completed the work to a satisfactory standard and that the overpayments were justified. The tribunal had to determine the validity of these claims and assess the appropriate amount of damages and restitution.
The tribunal found that Mr Rainbow was not liable for damages for the defective works as the plaintiffs had not provided sufficient evidence to support their claims. However, the tribunal allowed the restitution claim in the amount of $6, 501.55, finding that some of the payments made by the plaintiffs were for work that was not completed or was of an unsatisfactory standard. The tribunal also determined that the plaintiffs were entitled to $36, 847.82 by way of counter-claim for the rectification of defective work. As a result, the tribunal ordered that Mr Rainbow was entitled to $28, 171.29 for the reasonable value of the work completed by him but not paid for. The tribunal did not order any costs to be paid by either party, as both had been partially successful in their claims.
This case highlights the importance of clear contractual agreements and proper documentation in construction projects. The tribunal's decision underscores the need for builders to ensure that their work meets the required standards and for property owners to carefully review invoices and seek rectification of any defective work. Additionally, the case serves as a reminder of the potential consequences of failing to adequately document the scope of works and the terms of any agreements in place.
Orders
Orders of the court
Full text does not contain this section.
Background
Background to the litigation
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.