QCoal Pty Ltd & Anor v Isaac Regional Council (No 2) [2023] QPEC 18
PARTIES:
QCOAL PTY LTD ACN 010 911 234 AND
QCOAL GROUP
(Appellants)
vISAAC REGIONAL COUNCIL
(Respondent)FILE NO/S:
1480/2020
DIVISION:
Planning and Environment
PROCEEDING:
Appeal
ORIGINATING COURT:
Planning and Environment Court, Brisbane
DELIVERED ON:
19 May 2023
DELIVERED AT:
Brisbane
HEARING DATE:
4 May 2023
JUDGE:
Everson DCJ
ORDER:
APPEAL DISMISSED
CATCHWORDS:
PLANNING AND ENVIRONMENT – APPEAL – appeal against refusal of a development application for a Works Camp in the Rural Zone
PLANNING AND ENVIRONMENT – ASSESSMENT – compliance with regional plan and planning scheme – whether there is a need for the proposed development – whether in the way the mine is operated it is reasonable to expect the appellants to accommodate their non-residential workers in or adjacent to Gelenden
LEGISLATION:
Planning Act 2016 (Qld)
Planning and Environment Court Act 2016 (Qld)
CASES:
Abeleda & Anor v Brisbane City Council & Anor [2020] QCA 257
Brisbane City Council v YQ Property Pty Ltd [2020] QCA 253
QCoal Pty Ltd & Anor v Isaac Regional Council [2022] QCA 237
QCoal Pty Ltd & Anor v Isaac Regional Council [2021] QPEC 60
SLS Property Group Pty Ltd v Townsville City Council [2011] 2 Qd R 166
Wilhelm v Logan City Council & Ors [2020] QCA 273
Zappala Family Co Pty Ltd v Brisbane City Council [2014] QCA 147
COUNSEL:
G A Thompson KC, E J Morzone KC and K W Wylie
for the appellants
M J Batty and J Bowness for the respondent
SOLICITORS:
Emanate Legal for the appellants
King & Company for the respondent
Introduction
This is a re-hearing after a successful appeal to the Court of Appeal. It is limited in scope as the appeal succeeded on only one ground.
The appeal is against the refusal by the respondent of a development application for a development permit for a material change of use for a Works Camp (“the proposed development”) in respect of the land situated at 529 Wollombi Road, Suttor (“the site”). The development application seeks to make permanent and to expand a temporary Works Camp at the site such that it can accommodate up to 600 persons and 650 rooms.[1]
[1]QCoal Pty Ltd & Anor v Isaac Regional Council [2021] QPEC 60 at [1] – [2].
The proposed development is intended to house workers at the Byerwen Coal Mine (“the mine”) which is anticipated to produce up to 10 million tonnes of hard coking coal per year and expected to have a life of more than 50 years.[2] At full production, the workforce of the mine is anticipated to be between 850 and 900 employees.[3] The proposed development is intended to incorporate ancillary services including a wet mess and a gymnasium.[4]
[2]Ibid, [3] – [4].
[3]Ibid, [4].
[4]Ibid, [6].
The site is located in the Regional Landscape and Rural Production Area under the Mackay Isaac and Whitsunday Regional Plan (“the Regional Plan”). It…
Keep reading for free
Create a free CaseChat account to read QCoal Pty Ltd v Isaac Regional Council (No 2) and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2023] QPEC 18
- Decision Date
CaseChat Overview and Summary
The court considered whether it was reasonable to expect QCoal Pty Ltd to accommodate its non-residential workers in or adjacent to Glenden, given the mine's operational rostering arrangement. The court was not persuaded that the relatively short bus trip to and from a works camp or other accommodation facility in or adjacent to Glenden created an unreasonable fatigue management burden or otherwise. The court concluded that the mine could be conveniently serviced and non-residential workers could be practically located in accommodation within or adjacent to Glenden, in line with the identified assessment benchmarks. The court found that all facilities available to workers in the proposed development could be provided by QCoal Pty Ltd in or adjacent to Glenden, in conformity with the relevant assessment benchmarks.
The court dismissed the appeal, finding that it was still reasonable, particularly considering the relevant assessment benchmarks and the implications for Glenden, to expect QCoal Pty Ltd to accommodate its non-residential workers in or adjacent to Glenden. The development application should be refused, even taking into account the way the mine was and would be operated.
The court dismissed the appeal and the development application was refused.
Orders
Orders of the court
APPEAL DISMISSED
Background
Background to the litigation
Evidence
Evidence Before The Court
Decision
Reasons for decision
Ratio Decidendi