PLANNING AND ENVIRONMENT COURT OF QUEENSLAND
CITATION:
QCoal Pty Ltd & Anor v Isaac Regional Council [2021] QPEC 60
PARTIES:
QCOAL PTY LTD ACN 010 911 234 AND
QCOAL GROUP
(Appellants)
v
ISAAC REGIONAL COUNCIL
(Respondent)
FILE NO:
1480/2020
DIVISION:
Planning & Environment
PROCEEDING:
Appeal
ORIGINATING COURT:
Planning and Environment Court, Brisbane
DELIVERED ON:
1 November 2021
DELIVERED AT:
Brisbane
HEARING DATE:
19–22 October 2021
JUDGE:
Everson DCJ
ORDER:
Appeal dismissed
CATCHWORDS:
PLANNING AND ENVIRONMENT – APPEAL – appeal against refusal of a development application for a Works Camp in the Rural zone
PLANNING AND ENVIRONMENT – ASSESSMENT – compliance with regional plan and planning scheme – whether there is a need for the proposed development – whether there are relevant matters which justify the proposed development
LEGISLATION:
Planning and Environment Court Act 2016 (Qld) ss 43, 45 and 46
Planning Act 2016 (Qld) ss 45 and 60
CASES:
Abeleda & Anor v Brisbane City Council & Anor [2020] QCA 257
Wilhelm v Logan City Council & Ors [2020] QCA 273
Zappala Family Co Pty Ltd v Brisbane City Council [2014] QCA 147
Isgro v Gold Coast City Council & Anor [2003] QPELR 414
COUNSEL: C L Hughes QC and E J Morzone QC for the appellants
M J Batty and S J Hedge for the respondent
SOLICITORS: Emanate Legal for the appellants
King & Company for the respondent
Introduction
This is an appeal against the refusal by the respondent of a development application for a development permit for a material change of use for a Works Camp (“the proposed development”) in respect of land situated at 529 Wollombi Road, Suttor (“the site”).
The development application seeks to make permanent and expand a temporary Works Camp at the site which commenced operation on 31 January 2018. The temporary Works Camp was approved for a maximum of four years from the commencement of the use or the completion of the construction phase of the Byerwen Coal Mine Project (“the mine”), whichever occurred first.[1] The proposed development seeks to make the temporary Works Camp at the mine permanent and expand it to accommodate up to 600 persons and 650 rooms.[2]
[1]Exhibit 9, para 4.
[2]Ibid para 3.
The proposed development and the mine
The proposed development is intended to house workers at the mine which is located approximately 30 kilometres west of the town of Glenden. Glenden is within the local government area administered by the respondent.[3]
[3]Ibid para 17.
As at July 2021 the mine comprised a total of eight mining leases,[4] and once fully operational it is anticipated to produce up to 10 million tonnes of hard coking coal per year.[5] The mine was approved as a Coordinated Project by the Coordinator-General in July 2014 and is expected to have a life of more than 50 years.[6] The Coordinator‑General’s evaluation report dated July 2014 had regard to an environmental impact statement (“the EIS”).[7] At full production, the workforce throughout the operational phase of the mine is anticipated to be…
Keep reading for free
Create a free CaseChat account to read QCoal Pty Ltd v Isaac Regional Council and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2021] QPEC 60
- Decision Date
CaseChat Overview and Summary
The court concluded that the proposed development was inconsistent with the relevant provisions of the Regional Plan and the Nebo Planning Scheme. The appellants had not demonstrated that their existing and prospective workforce could not be housed nearby in and around Glenden, as contemplated by the relevant assessment benchmarks. The consequences of approving the proposed development would be detrimental to the ongoing utilisation of the significant social and administrative infrastructure which is already located in Glenden. The court found that the appellants had not discharged the onus of establishing that the appeal should be allowed. The failure of the proposed development to offer a significant choice to prospective workers to accommodate them with their families a short bus ride from the mine was likely to have a negative impact on certain workers.
The appeal was therefore dismissed. The court found that the proposed development was inconsistent with the relevant provisions of the Regional Plan and the Nebo Planning Scheme, and that the appellants had not demonstrated that their existing and prospective workforce could not be housed nearby in and around Glenden, as contemplated by the relevant assessment benchmarks. The court found that the consequences of approving the proposed development would be detrimental to the ongoing utilisation of the significant social and administrative infrastructure which is already located in Glenden.
Orders
Orders of the court
Appeal dismissed
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.