SUPREME COURT OF SOUTH AUSTRALIA
(Civil)
PT KRAKATAU STEEL v FELIX RESOURCES & ORS
[2010] SASC 170
Judgment of The Honourable Justice White
9 June 2010
CONTRACTS - GENERAL CONTRACTUAL PRINCIPLES - CONSTRUCTION AND INTERPRETATION OF CONTRACTS - OTHER MATTERS
CONTRACTS - GENERAL CONTRACTUAL PRINCIPLES - CONSTRUCTION AND INTERPRETATION OF CONTRACTS - IMPLIED TERMS - GENERALLY
ESTOPPEL - ESTOPPEL IN PAIS - EQUITABLE ESTOPPEL - PROMISSORY ESTOPPEL
TRADE AND COMMERCE - TRADE PRACTICES ACT 1974 (CTH) AND RELATED LEGISLATION - CONSUMER PROTECTION - MISLEADING OR DECEPTIVE CONDUCT OR FALSE REPRESENTATIONS - MISLEADING OR DECEPTIVE CONDUCT GENERALLY
CORPORATIONS - MEMBERSHIP, RIGHTS AND REMEDIES - MEMBERS' REMEDIES AND INTERNAL DISPUTES - OPPRESSIVE OR UNFAIR CONDUCT - WHAT CONSTITUTES - GENERALLY
Plaintiff and the first and second defendants are shareholders in the third defendant - an attempt by the third defendant to establish the viability of pig iron production using a particular technology was unsuccessful and was abandoned - plaintiff seeks to recover the amount of its investment in the project - the relationship of the parties was governed by two agreements: the "State Agreement" and the "Shareholders Agreement" - the plaintiff claimed that cl 11.2.5 of the Shareholders Agreement required the defendants to grant it access to mineral deposits from which it could recover iron ore or coal of equivalent value to the amount of its investment, thereby rendering its investment cash neutral.
Whether the defendants breached cl 11.2.5 - whether the first defendant breached express terms of the Shareholders Agreement by divesting its interest in a subsidiary and by relinquishing exploration licences - whether the first defendant breached an implied term of the Shareholders Agreement to do what was reasonably necessary to allow the plaintiff to have the benefit of cl 11.2.5 - whether the first defendant breached an implied term of the Shareholders Agreement requiring it, upon request, to transfer title to coal deposits to the third defendant - whether the second defendant breached the Shareholders Agreement by its disposal of the technology used in the project.
Whether the first and second defendants are estopped from denying a construction of cl 11.2.5 which would give the plaintiff the right to obtain iron ore or coal to the value of its contribution to the project, or the same rights which were conferred under a previous agreement - whether an estoppel arose on the basis of representations made by representatives of the first and second defendants or upon a conventional basis.
Whether, in the event that cl 11.2.5 of the Shareholder's Agreement did not entitle the plaintiff to obtain iron ore or coal to recoup the amount of its contribution in addition to the extraction and transportation costs, the clause should be rectified to give it that effect.
Whether representations made by the first and second defendants amounted to misleading or deceptive conduct contrary to s 52 of the Trade Practices Act 1974 (Cth).
Whether the parties owed fiduciary duties to each other - whether the defendants breached those obligations.
Whether the…
Keep reading for free
Create a free CaseChat account to read Pt Krakatau Steel v Felix Resources and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2010] SASC 170
- Decision Date
CaseChat Overview and Summary
The primary legal issues the court needed to address were whether the defendants breached specific clauses of the Shareholders Agreement, including Clause 11.2.5, which the plaintiff argued required the defendants to facilitate a cash-neutral investment. The court also had to determine if the first defendant breached other express terms of the Shareholders Agreement and whether there were any implied terms that the defendants failed to honour. Additionally, the court needed to assess whether the second defendant's actions in disposing of project technology constituted a breach of the Shareholders Agreement.
The court's reasoning focused on the objective interpretation of the agreements, applying the principle that the parties' subjective intentions are not determinative. Instead, the court considered what a reasonable person would have understood the contractual terms to mean, taking into account the surrounding circumstances and the purpose of the transaction. The court rejected the plaintiff's reliance on subjective evidence of prior negotiations, emphasizing that only objective evidence relevant to the agreements' interpretation was admissible. The court found that despite the plaintiff's claims, the defendants did not breach the Shareholders Agreement, and the plaintiff's investment did not become cash neutral as alleged.
The court's final orders dismissed the plaintiff's claims against the defendants, finding no breaches of the Shareholders Agreement and rejecting the plaintiff's claims for rectification, estoppel, and misleading or deceptive conduct. The defendants were found not liable for the plaintiff's investment losses.
Orders
Orders of the court
Background
Background to the litigation
Evidence
Evidence Before The Court
Decision
Reasons for decision
Ratio Decidendi
Legal Principle Established
The Asian Financial Crisis, which occurred during 1997 affected the ability of Maritosa and PTKS to meet their respective obligations under the SASE JVA. In April 1997 the parties executed amending agreements extending the time within which Maritosa could make its contribution and within which PTKS could make its further contribution. However, Maritosa still did not comply with its obligations and, on 26 November 1997, all parties agreed that Maritosa should cease to be a participant in the SASE Joint Venture. It took no further part thereafter.Incorporation of the Joint Venture Shortly after entering into the SASE JVA on 14 November 1996, the Australian participants realised that an unincorporated joint venture had some shortcomings, particularly in the raising of finance. Further, the parties contemplated making an application to the Australian Government for a Research and Development Start Grant, and such grants could be made only to Australian resident companies. They sought advice on whether the SASE Joint Venture should be incorporated. In anticipation of that advice, SASE (originally known as Ausmelt-MML Pty Ltd) was incorporated on 16 September 1997.[12] In December 1997, Ernst & Young recommended that the SASE Joint Venture be incorporated and Gresham Partners recommended that the parties hold their respective interests in the SASE Project and in the demonstration plant through SASE.[13][12] Exhibit P2 at [26].[13] Exhibit P1 at p 994. On 10 December 1997, AusIndustry (a department of the Australian Government) approved a grant (the R & D Start Grant) to Felix, Ausmelt, the Minister and PTKS as joint venturers, and for the purpose of the SASE Joint Venture. The amount of the R & D Start Grant was 50 per cent of the eligible project expenditure for the SASE Project or $6,532,329, whichever was the lesser. This meant that the joint venture had to fund at least $6,532,329 from its own resources if it was to receive the maximum grant. The R & D Start Grant was subject to certain conditions. The negotiation of those conditions and the entry by SASE into an agreement with AusIndustry was delayed for a number of reasons, including the negotiation of the incorporation of the terms of the SASE JVA into the SHA and into the State Agreement. The agreement relating to the R & D Start Grant was not executed until 16 December 1999 and payment of instalments of the R & D Grant commenced shortly afterwards. The decision to incorporate the SASE Joint Venture and to use SASE as the vehicle was made at a meeting of the Management Committee of the SASE Joint Venture on 12 January 1998. This meeting was attended by Mr Arthur as a representative of Felix, by three representatives of Ausmelt (including Mr McCammon, its Managing Director, and Mr Fogarty), three representatives from PTKS including Mr Bujang, then the Director of Technology within PTKS, and Mr Satrio, and by three representatives from the Department of Primary Industry and Resources (PIRSA) in South Australia representing the Minister. This was an important meeting as Mr Bujang was given assurances relied upon by PTKS in these proceedings to the effect that the entitlements and benefits of PTKS under the existing SASE JVA would be preserved and protected within the proposed incorporated structure. It will be necessary to return to the representations made at the meeting on 12 January 1998 and to their effect.