PT Krakatau Steel v Felix Resources Limited (No 2)

Link copied
Case Copied 11 min read

SUPREME COURT OF SOUTH AUSTRALIA

(Civil)

PT KRAKATAU STEEL v FELIX RESOURCES LIMITED & ORS (NO 2)

[2010] SASC 217

Judgment of The Honourable Justice White

23 July 2010

PROCEDURE - COSTS - DEPARTING FROM THE GENERAL RULE - ORDER FOR COSTS ON INDEMNITY BASIS

PROCEDURE - COSTS - GENERAL RULE - COSTS FOLLOW THE EVENT - COSTS OF WHOLE ACTION - GENERALLY

Application by defendants for costs to be awarded on an indemnity basis - whether plaintiff should have properly known that their case was unsustainable - whether case pursued by the plaintiff was "hopeless" - by consent application determined on the basis of the parties' written submissions - application dismissed.

PT Krakatau Steel v Felix Resources & Ors [2010] SASC 170 at [135], discussed.
Fountain Selected Meats (Sales) Pty Ltd v International Produce Merchants Pty Ltd (1988) 81 ALR 397 at 401; Colgate-Palmolive Ltd v Cussons Pty Ltd (1993) 46 FCR 225 at 232-3; Kenneally v Pouras [2007] SASC 303 at [13]; Sands v Channel Seven Adelaide Pty Ltd & Anor (No 2) [2009] SASC 365 at [6], considered.

PT KRAKATAU STEEL v FELIX RESOURCES LIMITED & ORS (NO 2)
[2010] SASC 217

Civil

  1. WHITE J:             On 9 June 2010, I delivered judgment dismissing the claim of the plaintiff (PTKS) in this action[1] and ordered that PTKS pay the defendants’ costs of action on a party/party basis.  However, I granted liberty to the defendants to apply to have the costs paid on a different basis.

  2. Subsequently the defendants made an application for an order that they have the whole or part of their costs on an indemnity basis.  The parties agreed that I should determine that application on the basis of their respective written submissions.

    Background

  3. In the substantive proceedings, PTKS sought to recover from the defendants the sum of US$2.5m being the amount of its contribution to a failed joint venture project (the SASE Project).  It made that claim on numerous bases, including breach of contract, breach of fiduciary duty, misleading or deceptive conduct, and oppression.  The full detail of the various claims is set out in the reasons delivered on 9 June 2010 (the principal reasons) and it is not necessary to repeat them.

  4. At the heart of PTKS’s claim was the assertion that a provision (cl 11.2.5) in the Shareholders Agreement (the SHA) regulating the relationship of the first defendant (Felix), the second defendant (Ausmelt) and itself required Felix and the third defendant (SASE) to grant it access to mineral deposits from which it could extract iron ore or coal to the value of US$2.5m (together with the costs of extraction and transportation) so that it could recoup the amount of its investment in the SASE Project.  It alleged that Felix and SASE had failed to comply with that obligation.

  5. PTKS also pursued the oppression claim on other bases, alleging that Felix had misused its majority voting power in SASE to its…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read PT Krakatau Steel v Felix Resources Limited (No 2) and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2010] SASC 217
Decision Date

CaseChat Overview and Summary

PT Krakatau Steel, the plaintiff, brought an action against Felix Resources Limited and others, the defendants, seeking to recover the sum of US$2.5 million, representing their contribution to a failed joint venture project. The plaintiff’s claims were founded on multiple grounds, including breach of contract, breach of fiduciary duty, misleading or deceptive conduct, and oppression. The plaintiff asserted that a provision in the Shareholders Agreement obligated the defendants to grant it access to mineral deposits from which it could extract iron ore or coal to recoup its investment. The plaintiff also alleged that the defendants misused their majority voting power and engaged in asset stripping. The court dismissed all claims, finding that the plaintiff’s fundamental assumption about the profitability of extracting iron ore or coal was unsupported by evidence. The defendants subsequently applied for costs on an indemnity basis, arguing that the plaintiff should have known that their case was unsustainable.

The primary legal issue before the court was whether the plaintiff should have known that their case was unsustainable and whether it was "hopeless" such that costs should be awarded on an indemnity basis. The court considered the plaintiff's failure to adduce evidence supporting the fundamental assumption underpinning their claims, despite being given ample opportunity to do so. The court also examined the plaintiff's decision not to cross-examine the defendants' expert witness or obtain a counter-expert report, despite having been provided with the defendants' expert report well in advance of the trial. The court found that the plaintiff's case was not "hopeless" but rather that the plaintiff had made a strategic decision to proceed with the case based on what they considered to be a meritorious claim. The court concluded that the plaintiff's decision to proceed with the case was not unreasonable and that there was no basis for awarding costs on an indemnity basis.

In determining the application for costs, the court held that the plaintiff's case, while ultimately unsuccessful, was not "hopeless" to the extent that it warranted an indemnity costs order. The court observed that the plaintiff had engaged in the litigation process in good faith and had pursued claims that, while ultimately unsuccessful, were not entirely without merit. The court found that the plaintiff's decision to proceed with the case, despite the defendants' expert evidence, was a reasonable one and did not warrant a departure from the general rule that costs follow the event. The application for indemnity costs was accordingly dismissed. The court emphasized that the decision was based on the particular circumstances of this case, and it did not establish a broad precedent for departing from the general rule regarding costs in similar cases. The court made no order as to costs, leaving the parties to bear their own costs of the application.

Orders

Orders of the court

Background

Background to the litigation

Subsequently the defendants made an application for an order that they have the whole or part of their costs on an indemnity basis. The parties agreed that I should determine that application on the basis of their respective written submissions.Background In the substantive proceedings, PTKS sought to recover from the defendants the sum of US$2.5m being the amount of its contribution to a failed joint venture project (the SASE Project). It made that claim on numerous bases, including breach of contract, breach of fiduciary duty, misleading or deceptive conduct, and oppression. The full detail of the various claims is set out in the reasons delivered on 9 June 2010 (the principal reasons) and it is not necessary to repeat them. At the heart of PTKS’s claim was the assertion that a provision (cl 11.2.5) in the Shareholders Agreement (the SHA) regulating the relationship of the first defendant (Felix), the second defendant (Ausmelt) and itself required Felix and the third defendant (SASE) to grant it access to mineral deposits from which it could extract iron ore or coal to the value of US$2.5m (together with the costs of extraction and transportation) so that it could recoup the amount of its investment in the SASE Project. It alleged that Felix and SASE had failed to comply with that obligation. PTKS also pursued the oppression claim on other bases, alleging that Felix had misused its majority voting power in SASE to its (PTKS’) detriment; that Felix and Ausmelt had breached other contractual obligations which they owed to it; and that Felix and Ausmelt had divested assets of SASE to themselves to its detriment by engaging in a form of asset stripping. I rejected all of PTKS’ claims. In addition, I considered that there was a fundamental defect in PTKS’ claim insofar as it rested in cl 11.2.5 of the SHA. PTKS pursued its claims on the basis that if it had been granted access to coal deposits which were the subject of exploration licences held by Felix, or to the iron ore deposits which were subject to the exploration licences held by SASE, it would, as a matter of fact, have been able to extract iron ore or coal of sufficient value so as to be able to recoup its contribution of US$2.5m as well as the extraction and transportation costs involved. PTKS did not adduce any evidence at all to support this fundamental assumption which was implicit in its claims. However the defendants adduced evidence indicating that, even if PTKS had been granted access, it could not have extracted iron ore or coal profitably, and that any attempt by it to do so would have caused still further losses. PTKS did not dispute that evidence and did not require the expert (Mr Horn) retained by the defendants to give evidence on this topic to attend for cross‑examination. The defendants delivered Mr Horn’s report to PTKS on 15 October 2009. PTKS was then given the opportunity to consider whether it wished to obtain an answering expert’s report, before the proceedings were set down for trial. By an email dated 29 October 2009, the solicitors for PTKS (Norton Rose) informed the defendants’ solicitors that PTKS “[would] not be filing any expert evidence in reply to that of Mr Horn”.

Evidence

Evidence Before The Court

Decision

Reasons for decision

Ratio Decidendi

Legal Principle Established