Reported Decision:
[2010] ALMD 1452
234 FLR 391
27 ACLC 1474
New South Wales
Supreme Court
CITATION: Project v TQM [2009] NSWSC 699 HEARING DATE(S): 22/07/09
JUDGMENT DATE :
21 September 2009JURISDICTION: Equity Division JUDGMENT OF: Macready AsJ at 1 DECISION: Paragraphs 31 and 32 CATCHWORDS: Corporations Law. Application to set aside statutory demand under s 459G of Corporations Act. Whether a genuine dispute can exist or an off-setting claim can be found notwithstanding a judgment for progress payments under the Building & Construction Industry Security of Payment Act 1999. Held it can. PARTIES: Project Venture Development No 11 Pty Limited v TQM Design & Construct Pty Limited FILE NUMBER(S): SC 6027/08 COUNSEL: Mr S Colledge for plaintiff
Miss V Culkoff for defendantSOLICITORS: Colin Biggers & Paisley for plaintiff
Julie Orsini for defendant
IN THE SUPREME COURT
OF NEW SOUTH WALES
EQUITY DIVISION
Associate Justice Macready
Monday 21 September 2009
6027/2008 Project Venture Development No 11 Pty Limited v TQM Design & Construct Pty Limited
JUDGMENT
1 His Honour: This is an application to set aside a statutory demand served on the plaintiff by the defendant. The statutory demand is dated 4 November 2008 and seeks an amount of $43,258.95. In the schedule to the demand the description of the debt showed that it arose from a judgment entered in the Local Court Downing Centre on 18 August 2008.
2 The parties were involved in a construction contract and the defendant was the builder for the plaintiff developer.
3 The judgment to which the demand relates was one which was obtained in the District Court following an adjudication determination under the Building and Construction Industry Security of Payment Act 1999 (the Act). The adjudication was issued on 1 August 2008 for an amount of $43,114.95. The adjudication was in respect of progress claims and not a final payment.
4 The application is made on the basis that the plaintiff has an offsetting claim substantially exceeding the amount of the judgment. The offsetting claim is based upon a claim for liquidated damages as a result of delayed completion and a claim for rectification costs for works on the property.
5 The liquidated damages claim is a substantial claim that was included in the adjudication application by the plaintiff for an amount of $380,279. The amount liquidated damages for $2,333.50 per day for 163 days.
6 The defendant’s answer to the claim was to make an extension of time claim through the superintendent appointed under the construction contract. Extensions of time claims are allowed in the contract for delays resulting from issues such as variations or bad weather. The superintendent’s allowed date for practical completion was 12 December 2007.
7 The defendant relied on a report saying it was entitled to further extensions of time extending the date for practical completion to 10 April 2008. In fact completion was obtained on 23 May 2008 and the adjudicator accepted the defendant’s application and extended the time to…
Continue reading Project v TQM
Sign in free to access the full text
- AGLC
- Project v TQM [2009] NSWSC 699
- Case
- [2009] NSWSC 699
- Decision Date
CaseChat Overview and Summary
The legal issues before the court were whether a genuine dispute could exist or an off-setting claim could be found despite the judgment for progress payments, and if such a dispute or claim was sufficient to warrant the setting aside of the statutory demand under section 459G. The court considered the definitions of "genuine dispute" and "offsetting claim" under the relevant acts and examined the evidence provided by both parties. The court found that the existence of the judgment did not automatically preclude the possibility of a genuine dispute or an off-setting claim, and that the dispute related to the amount of the debt and not the existence of the debt itself.
The court held that a genuine dispute could indeed exist even after a judgment for progress payments had been issued. The judgment did not preclude Project from asserting a genuine dispute about the amount of the debt. The court found that Project had demonstrated a genuine dispute concerning the amount of the debt owed to TQM. Consequently, the court set aside the statutory demand. The court's decision underscored the importance of examining the specifics of each case to determine the existence of a genuine dispute or an off-setting claim.
Orders
Orders of the court
Full text does not contain this section.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.