CITATION: Jem Developments v Hansen Yuncken [2006] NSWSC 1308 HEARING DATE(S): 30 November 2006
JUDGMENT DATE :
4 December 2006JURISDICTION: Equity JUDGMENT OF: Austin J DECISION: Period for compliance with statutory demand extended, otherwise originating process dismissed with costs. CATCHWORDS: CORPORATIONS - winding up in insolvency - presumption of insolvency through failure to comply with a statutory demand - offsetting claim - meaning of "offsetting" - effect of contractual provision excluding counter claims - CONTRACTS - settlement of building dispute - parties agree that "a payment obligation is to rank in priority" before any entitlements of payer to receive monies in connection with building project - proper construction LEGISLATION CITED: Corporations Act 2001 (Cth) ss 459C, 459E, 459F, 459G, 459H CASES CITED: Asia Pacific Glass Pty Ltd v Sindea Trading Co [2003] NSWSC 334
Carter v Roberts [1903] 2 Ch 312
Eyota Pty Ltd v Hanave Pty Ltd (1994) 12 ACSR 785
Gilbert-Ash (Northern) Ltd v Modern Engineering (Bristol) Ltd [1974] AC 689
Graywinter Properties Pty Ltd v Gas & Fuel Corporation Superannuation Fund (1996) 70 FCR 452
Macleay Nominees Pty Ltd v Bell Property East Pty Ltd [2001] NSWSC 743
POS Media v B Family [2003] NSWSC 147
Re Polaroid Australia Pty Ltd (Supreme Court of New South Wales, Santow J, unreported, 15 December 1997)
Robowash Pty Ltd v Robowash Finance Pty Ltd (2000) 158 FLR 338PARTIES: Jem Developments Pty Ltd (P1)
Pacifico Holdings Pty Ltd (P2)
Hansen Yuncken Pty Ltd (D)FILE NUMBER(S): SC 2349/06 COUNSEL: D S Weinberger (P1,P2)
P Fury (D)SOLICITORS: Salim Lawyers (P1,P2)
Crisp (D)
IN THE SUPREME COURT
OF NEW SOUTH WALES
EQUITY DIVISION
CORPORATIONS LIST
AUSTIN J
MONDAY 4 DECEMBER 2006
2349/06 JEM DEVELOPMENTS PTY LTD & ANOR V HANSEN YUNCKEN PTY LTD
JUDGMENT
1 HIS HONOUR: This is an application by the plaintiffs (to whom I shall refer, together, as "Jempac") under s 459G of the Corporations Act 2001 (Cth) to set aside a statutory demand served on them by the defendant ("HY"). The plaintiffs say they have offsetting claims which exceed the amount demanded. In the alternate, they submit that the demand should be set aside on "other grounds" within the meaning of s 459J, on the basis that the defendant failed to follow a contractual dispute resolution procedure and that the demand is an abuse of process.
The building contract
2 Jempac are property developers and the proprietors of a site in Wollongong. On 27 January 2004 they entered into a building contract with HY in the sum of $25.08 million, for HY as a builder to construct a building on the site, to be known as "The Landmark", comprising a block of residential apartments, a ground floor commercial area, and several levels of basement/car park.
3 The building contract appointed Jempac Developments Pty Ltd as "Superintendent", and contained the following relevant provisions:
· HY was obliged to comply with the Superintendent's "directions" (defined to include payment certificates and decisions) (clause 23);
· if HY was…
Keep reading for free
Create a free CaseChat account to read Jem Developments Pty Ltd v Hansen Yuncken Pty Ltd and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2006] NSWSC 1308
- Decision Date
CaseChat Overview and Summary
The court found that Hansen Yuncken's claim was not an "offsetting" claim as it did not directly relate to the statutory demand but rather arose from a separate building contract. Additionally, the court held that the contractual provision excluding counterclaims did not prevent Hansen Yuncken from asserting the priority of certain payment obligations over other entitlements. The court concluded that the priority clause meant that Jem Developments' payment obligations were to be met before Hansen Yuncken could claim any entitlements in connection with the building project. This interpretation was consistent with the intention of the parties as expressed in the contract.
As a result, the court dismissed Jem Developments' winding-up application, finding that Hansen Yuncken was not insolvent. The court's decision emphasised the importance of properly construing contractual provisions and the distinction between offsetting claims and other types of claims in the context of statutory demands.
Orders
Orders of the court
Full text does not contain this section.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.