Medium Neutral Citation: Premium Building Management Pty Ltd v The Owners - Strata Plan No 69204 [2019] NSWDC 312 Hearing dates: 18 – 20, 24 June 2019 Date of orders: 10 July 2019 Decision date: 10 July 2019 Jurisdiction: Civil Before: Abadee DCJ Decision: See paragraph 232
Catchwords: CONTRACT – building management agreement – whether and when agreement existed – terms of the agreement – incomplete or uncertain terms – statutory illegality – validity of contract under s67 of Strata Schemes Management Act 2015 (NSW)
ESTOPPEL – conventional estoppel – reply to defence of statutory illegality – whether defendant estopped from denying it entered into a binding agreement.
DAMAGES – claim for loss of profit – whether overhead expenses required to be taken into account proportionately to the business.
EVIDENCE – whether Jones v Dunkel inference available against defendant for failure to call evidence from attendees at meeting of content of discussions – reliability of Minute as business record of the defendant.
PRACTICE AND PROCEDURE – pleading requirements – whether assertion of incompleteness or uncertainty in contract needs to be pleaded – whether a party, in reply to unpleaded contention of incompleteness, may raise alterative case on date when agreement entered into.Legislation Cited: Civil Procedure Act 2005 (NSW)
Corporations Act 2001 (Cth)
Evidence Act 1995 (NSW)
Strata Schemes Management Act 2015 (NSW)
Uniform Civil Procedure RulesCases Cited: ASIC v Hellicar & Ors (2012) 247 CLR 345
ASIC v Rich (2005) 191 FLR 385
Bondlake Pty Ltd v The Owners – Strata Plan No. 60285 (2005) 62 NSWLR 158
Commercial Union Assurance Co of Australia v Ferrcom Pty Ltd (1991) 22 NSWLR 389
Empirnall Holdings Pty Ltd v Machon Paull Partners Pty Ltd (1988) 14 NSWLR 523
Equuscorp Pty Ltd v Haxton (2012) 246 CLR 498
Gynch v Polish Club (2015) 255 CLR 414
Johnston v Brightstars Holding Company Pty Ltd [2014] NSWCA 150
Meriton Apartments Pty Ltd v Owners Strata Plan No. 72381 (2015) 105 ACSR 1
Moratic Pty Ltd v Gordon [2007] NSWSC 5
Mushroom Composters Pty Ltd v IS & DE Robertson Pty Ltd [2015] NSWCA 1
Nelson v Nelson (1995) 184 CLR 538
North Sydney Leagues’ Club v Sydney Protection Agency Pty Ltd (2012) 83 NSWLR 710
Pua Hor Ong v Wu You Yang Pty Ltd (2008) SASC 365
Purkess v Crittenden (1965) 114 CLR 164
Ryledar Pty Ltd v Euphoric Pty Ltd (2007) 69 NSWLR 603
Stolfa v Owners Strata Plan 4366 [2009] NSWSC 589
Upper Hunter County District Council Australian Chilling & Freezing Co (1968) 118 CLR 429
Waldorf Apartment Hotel, the Entrance Pty Ltd v Owners Corp Sp 71623 [2010] NSWCA 226
Waltons Stores (Interstate) Ltd v Maher (1988) 164 CLR 387
Water Board v Moustakas (1988) 180 CLR 491
Whitlock v Brew (1968) 118 CLR 445
York Air Conditioning and Refrigeration (A/Sia) Pty Ltd v Commonwealth (1949) 80 CLR 11Texts Cited: Cheshire & Fifoot Law of Contract, 11th Australian ed
Heydon on Contract:…
Keep reading for free
Create a free CaseChat account to read Premium Building Management Pty Ltd v The Owners - Strata Pl... and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2019] NSWDC 312
- Decision Date
CaseChat Overview and Summary
The court held that the parties had entered into a binding agreement, which was not illegal under the Strata Schemes Management Act 2015 (NSW). The agreement was found to be complete and certain, with the term "for such period as the parties agree" being sufficient to bind the parties. The court found that the defendant was estopped from denying the existence of a binding agreement, as it had led the company to believe that an agreement was in place. The court also found that the claim for loss of profit was subject to a proportionate deduction of overhead expenses. Finally, the court found that a Jones v Dunkel inference could be drawn against the defendant for failing to call evidence from attendees at a meeting regarding the content of discussions. The defendant's pleading that the contract was incomplete or uncertain was considered to be sufficient to put the plaintiff on notice of the defendant's case, even though the plaintiff had not pleaded the incompleteness or uncertainty of the contract.
Orders
Orders of the court
See paragraph 232
Background
Background to the litigation
Evidence
Evidence Before The Court
Decision
Reasons for decision
Ratio Decidendi