Court of Appeal
Supreme Court
New South Wales
Medium Neutral Citation: PND Civil Group Pty Ltd v Bastow Civil Constructions Pty Ltd [2017] NSWCA 159 Hearing dates: 16/06/2017 Date of orders: 27 June 2017 Decision date: 27 June 2017 Before: McColl JA [1]; Gleeson JA [2]; McDougall J [3] Decision: (1) Notice of appeal dismissed with costs.
(2) On the cross-appeal:
(a) Set aside the costs orders made by the primary judge;
(b) In place of those orders, order the appellant to pay the respondent’s costs of the proceedings below; and
(c) Make no order as to the costs of the cross-appeal.Catchwords: CIVIL PROCEDURE – appeals – where new issues raised for the first time on appeal – CONTRACTS – damages – whether respondent entitled to recover cost of the management time spent by its employees in dealing with the appellant’s defective work – CIVIL PROCEDURE – appeals – costs – whether primary judge’s discretion miscarried Legislation Cited: Civil Procedure Act 2005 (NSW)
Uniform Civil Procedure Rules 2005 (NSW)Cases Cited: Bellgrove v Eldridge (1954) 90 CLR 613
Electricity Generation Corporation v Woodside Energy Ltd (2014) 251 CLR 640
House v The King (1936) 55 CLR 499
Orlit Pty Ltd v JF&P Consulting Engineers Pty Ltd [1993] QCA 277
Orlit Pty Ltd v JF&P Consulting Engineering Pty Ltd (1995) 11 BCL 260
Tabcorp Holding Ltd v Bowen Investments Pty Ltd (2009) 236 CLR 272
Waters v PC Henderson (Aust) Pty Ltd (1994) 254 ALR 328Category: Principal judgment Parties: PND Civil Group Pty Ltd (Appellant)
Bastow Civil Constructions Pty Ltd (Respondent)Representation: Counsel:
Solicitors:
DP O’Connor / F Bustos-McNeil (Appellant)
G McNally SC / D Stewart (Respondent)
Adams & Partners Lawyers (Appellant)
Matthews Dooley & Gibson (Respondent)
File Number(s): 2016/389583 Decision under appeal
- Court or tribunal:
- District Court of New South Wales
- Jurisdiction:
- Civil
- Date of Decision:
- 05/12/2016
- Before:
- Curtis DCJ
- File Number(s):
- 2013/88095
Judgment
-
McCOLL JA: I agree with McDougall J.
-
GLEESON JA: I agree with McDougall J.
-
McDOUGALL J: The respondent (Bastow) engaged the appellant (PND) as a subcontractor to perform work on a project at Terrigal. Bastow claimed that PND’s work was defective. It sued to recover the cost of rectification. The primary judge concluded that the work was defective, and awarded Bastow some (but not all) of the claimed cost of rectification.
-
PND appeals from the whole of the decision of the primary judge. Bastow cross-appeals from his Honour’s disallowance of a portion of its claim, and from a particular costs order made by his Honour.
The subcontract
-
Bastow contracted with Energy Australia (the parties and the primary judge referred to this entity as “Ausgrid”, and I shall do likewise) to undertake work that involved constructing trenches in public roads, installing cable ducts in those trenches, and backfilling and sealing the trenches. Bastow subcontracted some of that work to PND. The subcontract, on the findings of the primary judge (not now challenged) was oral, but was made by reference to a “Pre-Works…
Keep reading for free
Create a free CaseChat account to read PND Civil Group Pty Ltd v Bastow Civil Constructions Pty Ltd and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2017] NSWCA 159
- Decision Date
CaseChat Overview and Summary
The Court of Appeal was required to determine whether the respondent was entitled to recover the cost of management time spent by its employees in addressing the appellant's defective work. Additionally, the court considered whether the primary judge's discretion regarding costs had miscarried.
The Court of Appeal dismissed the appeal, finding no error in the primary judge's substantive decision. Regarding the costs of the proceedings below, the court set aside the primary judge's original costs orders and substituted an order that the appellant pay the respondent's costs. No order was made as to the costs of the cross-appeal.
Orders
Orders of the court
(1) Notice of appeal dismissed with costs.
(2) On the cross-appeal:
(a) Set aside the costs orders made by the primary judge;
(b) In place of those orders, order the appellant to pay the respondent’s costs of the proceedings below; and
(c) Make no order as to the costs of the cross-appeal.
Background
Background to the litigation
Evidence
Evidence Before The Court
Decision
Reasons for decision
Ratio Decidendi