All Aspects Earthworks Pty Ltd v Zafa Contracting Pty Ltd

Link copied
Case Copied 21 min read

QUEENSLAND CIVIL AND
ADMINISTRATIVE TRIBUNAL


CITATION:

ALL ASPECTS EARTHWORKS PTY LTD V ZAFA CONTRACTING PTY LTD [2023] QCAT 483

PARTIES:

ALL ASPECTS EARTHWORKS PTY LTD 

(applicant)

v

ZAFA CONTRACTING PTY LTD

(respondent)

APPLICATION NO.:

BDL269-22

MATTER TYPE:

Building matters

DELIVERED ON:

11 December 2023

HEARING DATE:

On the papers

HEARD AT:

Brisbane

DECISION OF:

Senior Member Brown

ORDERS:

1.       All Aspects Earthworks Pty Ltd must pay to Zafa Contracting Pty Ltd $13,903.00 within twenty-eight days.

2.       No order as to costs

CATCHWORDS:

ADMINISTRATIVE LAW – ADMINISTRATIVE TRIBUNALS – QUEENSLAND CIVIL AND ADMINISTRATIVE TRIBUNAL – whether QCAT has jurisdiction – whether the dispute the subject of the proceeding is a building dispute – whether the work undertaken by the parties is building work – whether the dispute the subject of the proceeding is a minor civil dispute

CONTRACTS – BUILDING, ENGINEERING AND RELATED CONTRACTS – PERFORMANCE OF WORK – REMEDIES FOR BREACH OF CONTRACT – DAMAGES – MEASURE OF – breach of contract – damages for breach of contract – where applicant subcontracted respondent for the laying of asphalt driveway – where defects were identified in the respondent’s work – where the respondent subsequently undertook rectification works of the defect - whether further remedial work is reasonable and necessary – whether remedying the defect is out of proportion to the achievement of the contractual objective

Queensland Building and Construction Commission Act 1991 (Qld) Schedule 1B, s 20, Schedule 1B s 22, Schedule 2
Queensland Building and Construction Commission Regulation 2018 (Qld) Schedule 1 s 32, s 6
Queensland Civil and Administrative Tribunal Act 2009 (Qld) s 11, Schedule 3

Bellgrove v Eldridge [1954] HCA 36

PND Civil Group Pty Ltd v Bastow Civil Constructions Pty Ltd

[2017] NSWCA 159

 Scott Carver Corporation Pty Ltd v SAS Trustee Corporation (Formerly State Authorities Superannuation Board) [2005] NSWCA 462

Tabcorp Holdings Ltd v Bowen Investments Pty Ltd (2009) 236 CLR 272

APPEARANCES & REPRESENTATION:

This matter was heard and determined on the papers pursuant to s 32 of the Queensland Civil and Administrative Tribunal Act 2009 (Qld)

REASONS FOR DECISION

  1. This proceeding falls to be finally determined.

  2. The dispute between the parties relates to the construction of driveway at a domestic residence. The applicant is an earthmoving contractor. The respondent is a contractor engaged in laying asphalt surfaces. Neither party is the holder of a licence issued by the Queensland Building and Construction Commission.

    Jurisdiction – is this a proceeding for a building dispute or a minor civil dispute?

  3. At first blush the dispute appears to be a building dispute. For the reasons that follow, it is not. The dispute is in fact a trader/trader dispute and falls to be determined as a minor civil dispute.

  4. The jurisdiction of the Tribunal to decide a building dispute is strictly circumscribed by the provisions of the Queensland Building and Construction Commission Act 1991 (Qld) (‘QBCC Act’).  

  5. The QBCC Act provides that the parties to a building dispute, whether a domestic building dispute or a…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read All Aspects Earthworks Pty Ltd v Zafa Contracting Pty Ltd and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2023] QCAT 483
Decision Date

CaseChat Overview and Summary

All Aspects Earthworks Pty Ltd (the applicant) commenced proceedings against Zafa Contracting Pty Ltd (the respondent) in the Queensland Civil and Administrative Tribunal (QCAT). The applicant sought damages for breach of contract following the completion of works by the respondent for the laying of an asphalt driveway. The respondent had subsequently undertaken rectification works to address defects identified by the applicant. The primary issue for the tribunal was whether the respondent had breached the contract by failing to undertake the works in a proper manner and, if so, what the appropriate remedy was.

The tribunal found that the respondent had indeed breached the contract by not performing the work with reasonable care and skill, leading to identifiable defects. The respondent, however, had undertaken remedial works to rectify these defects, which satisfied their contractual obligations. The tribunal considered whether it was reasonable and necessary for the entire driveway to be re-coated due to a minor colour discolouration, which constituted approximately 2% of the total driveway area. The tribunal concluded that re-coating the entire driveway was neither necessary nor reasonable as a remedy for the minor defect. Therefore, while the respondent's breach was established, the applicant's entitlement to substantive damages was not. Instead, the tribunal awarded the applicant nominal damages of $100.00.

Consequently, the tribunal determined that the respondent was entitled to the contract price of $14,003.00. Considering the applicant's nominal damages, the final decision was for the respondent to recover $13,903.00 from the applicant. Given that both the application and counter-application fell within the minor civil dispute jurisdiction, costs were limited by rule 84 of the Queensland Civil and Administrative Tribunal Rules 2009 (Qld). As both parties achieved some measure of success, no order for costs was made.

ORDERS:
1. All Aspects Earthworks Pty Ltd must pay to Zafa Contracting Pty Ltd $13,903.00 within twenty-eight days.
2. No order as to costs.

Orders

Orders of the court

1. All Aspects Earthworks Pty Ltd must pay to Zafa Contracting Pty Ltd $13,903.00 within twenty-eight days.

2. No order as to costs

Background

Background to the litigation

Full text does not contain this section.

Evidence

Evidence Before The Court

Full text does not contain this section.

Decision

Reasons for decision

For the foregoing reasons I am satisfied that the respondent has performed its obligations under the contract and is entitled to the payment of the contract price of $14,003.00.Conclusion I am satisfied that the respondent breached the contract in failing to undertake the works in an appropriate and skilful way and with reasonable care and skill. I am satisfied that the respondent undertook remedial works to rectify the defect. I am not satisfied that it is necessary nor reasonable for the entire driveway to be re-coated with asphalt to address a minor colour discolouration involving an area of approximately 2% of the total driveway area. The applicant has established that the respondent breached the contract. The applicant has not established an entitlement to substantive damages. The applicant is entitled to an award of nominal damages. I assess nominal damages in the amount of $100.00. The respondent is entitled to recover from the applicant $14,003.00. Taking into consideration the applicant’s entitlement to nominal damages, there will be a final decision for the respondent in the amount of $13,903.00. As both the application and the counter application are within the minor civil disputes jurisdiction, costs recoverable by each of the parties is limited by rule 84 of the Queensland Civil and Administrative Tribunal Rules 2009 (Qld). Each party has been successful to some degree. I therefore make no order as to costs.

Ratio Decidendi

Legal Principle Established

Full text does not contain this section.