QUEENSLAND CIVIL AND
ADMINISTRATIVE TRIBUNAL
CITATION:
ALL ASPECTS EARTHWORKS PTY LTD V ZAFA CONTRACTING PTY LTD [2023] QCAT 483
PARTIES:
ALL ASPECTS EARTHWORKS PTY LTD (applicant)
v
ZAFA CONTRACTING PTY LTD (respondent)
APPLICATION NO.:
BDL269-22
MATTER TYPE:
Building matters
DELIVERED ON:
11 December 2023
HEARING DATE:
On the papers
HEARD AT:
Brisbane
DECISION OF:
Senior Member Brown
ORDERS:
1. All Aspects Earthworks Pty Ltd must pay to Zafa Contracting Pty Ltd $13,903.00 within twenty-eight days.
2. No order as to costs
CATCHWORDS:
ADMINISTRATIVE LAW – ADMINISTRATIVE TRIBUNALS – QUEENSLAND CIVIL AND ADMINISTRATIVE TRIBUNAL – whether QCAT has jurisdiction – whether the dispute the subject of the proceeding is a building dispute – whether the work undertaken by the parties is building work – whether the dispute the subject of the proceeding is a minor civil dispute
CONTRACTS – BUILDING, ENGINEERING AND RELATED CONTRACTS – PERFORMANCE OF WORK – REMEDIES FOR BREACH OF CONTRACT – DAMAGES – MEASURE OF – breach of contract – damages for breach of contract – where applicant subcontracted respondent for the laying of asphalt driveway – where defects were identified in the respondent’s work – where the respondent subsequently undertook rectification works of the defect - whether further remedial work is reasonable and necessary – whether remedying the defect is out of proportion to the achievement of the contractual objective
Queensland Building and Construction Commission Act 1991 (Qld) Schedule 1B, s 20, Schedule 1B s 22, Schedule 2
Queensland Building and Construction Commission Regulation 2018 (Qld) Schedule 1 s 32, s 6
Queensland Civil and Administrative Tribunal Act 2009 (Qld) s 11, Schedule 3Bellgrove v Eldridge [1954] HCA 36
PND Civil Group Pty Ltd v Bastow Civil Constructions Pty Ltd
Tabcorp Holdings Ltd v Bowen Investments Pty Ltd (2009) 236 CLR 272
APPEARANCES & REPRESENTATION:
This matter was heard and determined on the papers pursuant to s 32 of the Queensland Civil and Administrative Tribunal Act 2009 (Qld)
REASONS FOR DECISION
This proceeding falls to be finally determined.
The dispute between the parties relates to the construction of driveway at a domestic residence. The applicant is an earthmoving contractor. The respondent is a contractor engaged in laying asphalt surfaces. Neither party is the holder of a licence issued by the Queensland Building and Construction Commission.
Jurisdiction – is this a proceeding for a building dispute or a minor civil dispute?
At first blush the dispute appears to be a building dispute. For the reasons that follow, it is not. The dispute is in fact a trader/trader dispute and falls to be determined as a minor civil dispute.
The jurisdiction of the Tribunal to decide a building dispute is strictly circumscribed by the provisions of the Queensland Building and Construction Commission Act 1991 (Qld) (‘QBCC Act’).
The QBCC Act provides that the parties to a building dispute, whether a domestic building dispute or a…
Keep reading for free
Create a free CaseChat account to read All Aspects Earthworks Pty Ltd v Zafa Contracting Pty Ltd and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2023] QCAT 483
- Decision Date
CaseChat Overview and Summary
The tribunal found that the respondent had indeed breached the contract by not performing the work with reasonable care and skill, leading to identifiable defects. The respondent, however, had undertaken remedial works to rectify these defects, which satisfied their contractual obligations. The tribunal considered whether it was reasonable and necessary for the entire driveway to be re-coated due to a minor colour discolouration, which constituted approximately 2% of the total driveway area. The tribunal concluded that re-coating the entire driveway was neither necessary nor reasonable as a remedy for the minor defect. Therefore, while the respondent's breach was established, the applicant's entitlement to substantive damages was not. Instead, the tribunal awarded the applicant nominal damages of $100.00.
Consequently, the tribunal determined that the respondent was entitled to the contract price of $14,003.00. Considering the applicant's nominal damages, the final decision was for the respondent to recover $13,903.00 from the applicant. Given that both the application and counter-application fell within the minor civil dispute jurisdiction, costs were limited by rule 84 of the Queensland Civil and Administrative Tribunal Rules 2009 (Qld). As both parties achieved some measure of success, no order for costs was made.
ORDERS:
1. All Aspects Earthworks Pty Ltd must pay to Zafa Contracting Pty Ltd $13,903.00 within twenty-eight days.
2. No order as to costs.
Orders
Orders of the court
1. All Aspects Earthworks Pty Ltd must pay to Zafa Contracting Pty Ltd $13,903.00 within twenty-eight days.
2. No order as to costs
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.