Palm Cove Nominees Pty Ltd v Cairns Regional Council

Link copied
Case Copied 15 min read

SUPREME COURT OF QUEENSLAND

CITATION:

Palm Cove Nominees Pty Ltd v Cairns Regional Council & Anor [2023] QSC 289

PARTIES:

PALM COVE NOMINEES PTY LTD ACN 005 775 495

(Applicant )

v

CAIRNS REGIONAL COUNCIL

(First Respondent)

and
WESLEY COATES

(Second Respondent)

FILE NO/S:

437 of 2023

DIVISION:

Trial

PROCEEDING:

Application

ORIGINATING COURT:

Supreme Court of Queensland at Cairns

DELIVERED ON:

15 December 2023

DELIVERED AT:

Cairns

HEARING DATE:

10 November 2023

JUDGE:

Henry J

ORDERS:

1.   It is declared the second respondent’s purported market value determination provided as a result of joint instructions from the applicant and the first respondent pursuant to cl 7.3 of their infrastructure agreement dated 18 January 2022 was not a determination of “the market value of the land contribution” within the meaning of cl 7.3 because it assessed the market value as at a date, namely 2 September 2022, prior to the date the land was contributed, namely 19 October 2022.

2.   Liberty to apply on the giving of two clear business days notice in writing.

3.   I will hear the parties as to costs, if costs are not agreed in the meantime, at 9.15am 7 February 2024.

CATCHWORDS:

CONTRACTS – GENERAL CONTRACTUAL PRINCIPLES – FORMATION OF CONTRACTUAL RELATIONS – where land and works contributions were required by an infrastructure agreement entered into between a developer and  Cairns Regional Council– where the infrastructure agreement provided for a process of valuation of the land contribution which would be binding on the parties – where there is disagreement over an independent valuation of the market value of the land – whether the valuation’s timing or methodology mean it was not a valuation as required by the infrastructure agreement

Ainsworth v Criminal Justice Commission (1992) 175 CLR 564, cited
Downer Engineering Power Pty Ltd v P&H Minepro Australasia Pty Ltd [2007] NSWCA 318, cited
Holt v Cox (1997) 23 ACSR 590, cited
Legal & General Life of Australia Ltd v A Hudson Pty Ltd (1985) 1 NSWLR 314, cited
McArthur v Mercantile Mutual Life Insurance Company Ltd [2002] 2 Qd R 197, cited
Nathanson v Minister for Home Affairs (2022) 96 ALJR 737, cited
Pointe Gourde Quarrying & Transport Co Ltd v Sub-Intendent of Crown Lands [1947] AC 565, cited
Shoalhaven City Council v Firedam Civil Engineering Pty Ltd (2011) 244 CLR 305, cited

COUNSEL:

M Jonsson KC for the applicant

J Horton KC for the respondents

SOLICITORS:

Holding Redlich for the applicant

Corrs Chambers Westgarth for the respondents

  1. A developer and Cairns Regional Council are at odds over the independent valuation of the market value of land.  That land will accommodate a transport link next to the developer’s residential property development.  The land was contributed by the developer to Council to secure approval for reconfiguration of much of the developer’s land at Cedar Road, Palm Cove into 36 residential lots.  The infrastructure agreement which regulated that process provided for a process of valuation of the land contribution which would…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Palm Cove Nominees Pty Ltd v Cairns Regional Council and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2023] QSC 289
Decision Date

CaseChat Overview and Summary

In the case of Palm Cove Nominees Pty Ltd v Cairns Regional Council, the primary dispute revolved around the valuation of land and works contributions stipulated by an infrastructure agreement between the developer, Palm Cove Nominees, and the Cairns Regional Council. The developer contested the validity of the council's valuation of the land, arguing it did not comply with the terms of the agreement. The court was tasked with determining whether the valuation's timing or methodology rendered it invalid under the terms of the infrastructure agreement.

The central legal issue was whether the valuation provided by the council adhered to the requirements set forth in the infrastructure agreement. Specifically, the court had to examine if the valuation was conducted at the correct time and if the methodology used was appropriate. The developer contended that the valuation was conducted before the land was actually contributed, which they argued was against the terms of the agreement. The court needed to assess whether these discrepancies invalidated the valuation as per the contract.

The court found that the valuation was indeed flawed as it assessed the market value of the land before the contribution date, which was contrary to the agreement's stipulations. The court held that this timing discrepancy rendered the valuation invalid. The court also noted that the Pointe Gourde principles, typically applied in cases of compulsory acquisition, were not directly applicable here due to the voluntary nature of the land contribution. The court thus concluded that the valuation did not meet the contractual requirements and declared that the council's valuation was not a valid determination of the market value of the land contribution. The court opted for a declaration as the appropriate remedy, leaving the contractual terms to govern any further actions. Additionally, the court granted liberty to apply for further orders if needed and scheduled a hearing for costs.

Orders

Orders of the court

1. It is declared the second respondent’s purported market value determination provided as a result of joint instructions from the applicant and the first respondent pursuant to cl 7.3 of their infrastructure agreement dated 18 January 2022 was not a determination of “the market value of the land contribution” within the meaning of cl 7.3 because it assessed the market value as at a date, namely 2 September 2022, prior to the date the land was contributed, namely 19 October 2022.

2. Liberty to apply on the giving of two clear business days notice in writing.

3. I will hear the parties as to costs, if costs are not agreed in the meantime, at 9.15am 7 February 2024.

Background

Background to the litigation

Evidence

Evidence Before The Court

Decision

Reasons for decision

The above reasons amply explain why the developer’s second complaint must fail. They also make it unnecessary to explain, or express a concluded view on, the merits of the rival submissions of counsel for each side as to how the so-called Pointe Gourde principles,[7] applicable in cases of compulsory acquisition under a scheme, could by parity of reasoning be applied in support of their arguments about the valuation methodology applied here. This was not a compulsory acquisition. The land was contributed in an exercise of free commercial choice. In that context the Pointe Gourde principles could do no more than potentially inform the valuer’s choice of methodology, a choice which the parties’ agreement left to the valuer’s expertise.[7]Pointe Gourde Quarrying & Transport Co Ltd v Sub-Intendent of Crown Lands [1947] AC 565.Conclusion and orders In circumstances where I have been persuaded to make a declaration as a result of the success of the developer’s first argument but not its second, it is appropriate that declaration be couched in such a way as to specifically reflect that outcome. That is preferable to merely leaving it to the perusal of these reasons, to ascertain why I will be declaring that the second respondent’s determination was not a determination of the market value of the land contribution within the meaning of cl 7. Submissions were also directed to potential orders additional to a declaration. In my conclusion, additional orders would involve a higher level of intervention by the Court in the parties’ contractual relations than appears necessary. A declaration should be sufficient to quell the controversy between the parties and the terms of the agreement can be left to do their work. To cater for the unlikely event further curial guidance is required, my orders will make provision for liberty to apply. The parties having endured mixed success in this application, it will be necessary to hear them as to costs if costs are not agreed. I order:1. It is declared the second respondent’s purported market value determination provided as a result of joint instructions from the applicant and the first respondent pursuant to cl 7.3 of their infrastructure agreement dated 18 January 2022 was not a determination of “the market value of the land contribution” within the meaning of cl 7.3 because it assessed the market value as at a date, namely 2 September 2022, prior to the date the land was contributed, namely 19 October 2022.2. Liberty to apply on the giving of two clear business days notice in writing. 3. I will hear the parties as to costs, if costs are not agreed in the meantime, at 9.15am 7 February 2024.

Ratio Decidendi

Legal Principle Established