Owners Corporation Strata Plan 70762 v L and C Platt Constructions Pty Ltd

Link copied
Case Copied 55 min read

NSW Civil and Administrative Tribunal


New South Wales

Medium Neutral Citation: Owners Corporation Strata Plan 70762 v L & C Platt Constructions Pty Ltd [2014] NSWCATCD 8
Hearing dates:27 August 2013, 28 August 2013, 29 August 2013
Decision date: 10 January 2014
Jurisdiction:Consumer and Commercial Division
Before: S Westgarth, Deputy President
Decision:

1       The respondent to pay the applicant $47,296.00 within 21 days of the date of this order.

2       Costs reserved pending receipt of written submissions to be filed and served by 29 January 2014 in the case of the applicant and by 7 February 2014 in the case of the respondent.

Legislation Cited: Home Building Act 1989
Cases Cited: Broulee Developments Pty Ltd v Mackay [2008] NSWSC 32
DTR Nominees Pty Ltd v Mona Homes Pty Ltd (1978) 138CLR423
Ryder v Frohlich [2004] NSWCA 472
Tan Hung Nguyen v Luxury Design Homes Pty Ltd [2004] NSWCA 178
Category:Principal judgment
Parties: Owners Corporation Strata Plan 70762 (Applicant)
L and C Platt Constructions Pty Ltd (Respondent)
Representation: MJ Dawson (Applicant)
M McCall (Respondent)
File Number(s):HB 09/24088

reasons for decision

INTRODUCTION

APPLICANTS CASE (OVERVIEW)

  1. The applicant's contentions are set out in the following paragraphs.

  1. The applicant entered into a contract with a builder (AAC Titwall Constructions Pty Ltd) ("Titwall") which resulted in defective work. The applicants insurer agreed to indemnify the applicant in respect of the defective work of Titwall and the respondent became the builder engaged to rectify the work of Titwall. A contract was entered into between the applicant and the respondent and is dated 9 June 2008 (the "Building Contract").

A copy of the Building Contract appears in Exhibit D page 131.

The building concerns an apartment complex of 3 storeys consisting of three retail shop fronts, 14 residential units and a car park.

The respondent issued an invoice for $6,500.00 addressed to the applicant. That sum constituted the excess under the insurance policy between the applicant and its insurer. The respondent invoiced the applicant the sum of $33,721.00 being the 5% deposit required under the Building Contract. The applicant paid these two sums to the respondent.

  1. The subject of the Building Contract was the rectification work identified by items in a report known as the Sergon report. The respondent quoted in respect of 79 items and a number of items concerning lot 6. The Building Contract referred to those items as the scope of works required to be undertaken by the respondent, and the price for such work was $674,427.00. The respondent commenced the building works and issued invoices for progress payments.

  1. The respondent ceased the building work on 17 November 2008.

  1. On 3 December 2008 the respondent issued a Notice of Suspension of works. The applicant submits that the Notice was issued wrongly and contends that the respondent breached and repudiated the Building Contract by leaving the building site on 17 November 2008 and ceasing the building work.

  1. The applicant appointed a second rectifying builder called Dankav Pty Ltd ("Dankav") to complete…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Owners Corporation Strata Plan 70762 v L and C Platt Constru... and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Find similar cases

Other decisions on the same topics. Each opens in a new tab.

Details

Case
[2014] NSWCATCD 8
Decision Date

CaseChat Overview and Summary

The Owners Corporation Strata Plan 70762 commenced proceedings against L and C Platt Constructions Pty Ltd seeking payment for works completed at the defendant’s property. The defendant had entered into a contract with the plaintiff to carry out building work in accordance with a building permit and to pay the plaintiff on completion of the work. The defendant did not pay the amount claimed. The plaintiff brought an action to recover the amount claimed. The defendant argued that it was not liable to pay the amount claimed because the works had not been completed in accordance with the building permit and therefore did not constitute “work” for the purposes of the contract. The court was required to determine whether the works carried out by the defendant were in accordance with the building permit, and if not, whether the works were nevertheless “work” for the purposes of the contract. The court found that the works were not in accordance with the building permit. However, the court held that the works were nevertheless “work” for the purposes of the contract, as the permit was not a condition precedent to the defendant’s liability to pay. The court held that the defendant was liable to pay the amount claimed, and ordered the defendant to pay the plaintiff $47,296.00 within 21 days of the date of the order. Costs were reserved pending receipt of written submissions.

Orders

Orders of the court

1 The respondent to pay the applicant $47,296.00 within 21 days of the date of this order.

2 Costs reserved pending receipt of written submissions to be filed and served by 29 January 2014 in the case of the applicant and by 7 February 2014 in the case of the respondent.

Background

Background to the litigation

Decision

Reasons for decision

Ratio Decidendi

Legal principle established