Civil and Administrative Tribunal
New South Wales
Medium Neutral Citation: Georges v Ozz Projects (Aust) Pty Ltd [2021] NSWCATCD 104 Hearing dates: 3 March 2021 Date of orders: 23 July 2021 Decision date: 01 October 2021 Jurisdiction: Consumer and Commercial Division Before: N Vrabac, Senior Member Decision: 1. Pursuant to s 50(2) of the Civil and Administrative Tribunal Act 2013 NSW, the Tribunal dispenses with a hearing, the issues the subject of the application may be determined on the basis of the papers lodged with the Tribunal by the parties in accordance with the Tribunal's orders and directions.
2. The respondent Ozz Projects (AUST) Pty Ltd is to pay 60% of the applicant's costs of an as agreed or assessed.
3. The respondent’s application for costs is dismissed.
Catchwords: COSTS - Civil and Administrative Tribunal Act 2013 (NSW)
Legislation Cited: Nil
Cases Cited: Bostik Australia Pty Ltd v Liddiard (NO 2) [2009] NSWCA 304
Thompson v Chapman [2016] NSWCATAP 6
Owners Corporation Strata Plan 70762 v L & C Platt Constructions Pty Ltd [2014] NSWCATCD 8
Texts Cited: Nil
Category: Costs Parties: Peter Georges (Applicant)
Ozz Projects (AUST) Pty Ltd (Respondent)Representation: Counsel:
Solicitors:
M Marshall (Applicant)
Finn Roache Lawyers (Applicant)
Celtic Legal (Respondent)
File Number(s): HB 20/37272 Publication restriction: Nil
REASONS FOR DECISION
Background
-
The background to the proceedings from which this cost application arises was set out in some detail in the decision of the Tribunal made on 23 July 2021. A brief summary appears below to give context to the costs application.
-
On or about 5 June 2018 the applicant (“Owner”) and the respondent (“Builder’) entered into written agreement for the provision of building and renovations work to be supplied by the Builder to the Owner.
-
The agreement was in the sum of $155,000.00.
-
On or about 7 January 2019, the Builder notified the Owner that he was unable to complete the building works. The Builder was last on the building site on 4 March 2019.
-
The Builder stated the building works were completed pursuant to the contract, accept for the second mid-landing. The Builder contracted to build an inclinator and landings from the Owner’s house, down the hill, to his boat house near the water.
-
A dispute arose as to whether the Builder should have built the second mid-landing.
-
On 27 August 2020 the Owner commenced proceedings in this matter.
-
The Owners’s claim for damages against the Builder was particularised as follows:
$38,445.00 for failure to complete the second mid-landing;
$3,000 additional scaffolding costs, and
$43,000.86 in liquidated damages pursuant to the agreement.
-
The Builder filed a cross claim, HB 20/19203, which has not been determined to date. The Builder’s claim against the Owner was initially a debt recovery in the Local Court in the sum of approximately $17,000.00. The Local Court proceedings were transferred to NCAT. The Builders claim was amended at NCAT as follows:
$14,123.24 unpaid monies under contract
$2,943.60 unpaid invoice, and
$119,340.43 delay payment, loss to be proven under contract
-
On 13…
Continue reading Georges v Ozz Projects (Aust) Pty Ltd
Sign in free to access the full text
- AGLC
- Georges v Ozz Projects (Aust) Pty Ltd [2021] NSWCATCD 104
- Case
- [2021] NSWCATCD 104
- Decision Date
CaseChat Overview and Summary
In addressing the matter, the Tribunal first considered the statutory provision under which costs may be awarded. The Tribunal noted that section 50 of the Civil and Administrative Tribunal Act 2013 (NSW) allows for the award of costs when a party has unreasonably protracted the proceedings. The Tribunal examined the papers submitted by both parties and concluded that the respondent had indeed unreasonably protracted the proceedings. Consequently, the Tribunal determined that the respondent should pay 60% of the applicant's costs. The Tribunal also dismissed the respondent’s application for costs, finding it to be without merit.
The Tribunal’s decision was made without the necessity for a hearing, as permitted by section 50(2) of the Civil and Administrative Tribunal Act 2013 (NSW). The Tribunal directed that the issues could be resolved on the basis of the written submissions and evidence provided by the parties. The final orders included a directive for the respondent to pay 60% of the applicant’s costs and a dismissal of the respondent’s application for costs.
Orders
Orders of the court
1. Pursuant to s 50(2) of the Civil and Administrative Tribunal Act 2013 NSW, the Tribunal dispenses with a hearing, the issues the subject of the application may be determined on the basis of the papers lodged with the Tribunal by the parties in accordance with the Tribunal's orders and directions.
2. The respondent Ozz Projects (AUST) Pty Ltd is to pay 60% of the applicant's costs of an as agreed or assessed.
3. The respondent’s application for costs is dismissed.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.