O'Donnell Griffin Pty Ltd v Davis

Link copied
Case Copied 20 min read

O'DONNELL GRIFFIN PTY LTD -v- DAVIS & ORS [2007] WASC 215



SUPREME COURT OF WESTERN AUSTRALIACitation No:[2007] WASC 215
07/09/2007
Case No:CIV:1818/200716 AUGUST 2007
Coram:TEMPLEMAN J16/08/07
14Judgment Part:1 of 1
Result: Application dismissed
A
PDF Version
Parties:O'DONNELL GRIFFIN PTY LTD (ACN 003 905 093)
ROGER DAVIS
SIEMENS LTD (ACN 004 347 888)
THIESS SERVICES PTY LTD (ACN 010 221 486) T/AS STCJV SERVICES FOR TELECOMMUNICATIONS JOINT VENTURE (ABN 61 507 423 189)

Catchwords:

Practice and procedure
Application for interlocutory injunction to prevent adjudication under the Construction Contracts Act 2004 (WA)
No cause of action disclosed
Failure to comply with O 59 r 9
Damages an adequate remedy
Balance of convenience favours defendant
Indemnity costs

Legislation:

Construction Contracts Act 2004 (WA), s 3, s 6, s 25, s 27, s 28, s 31, s 45, s 46
Rules of the Supreme Court 1971 (WA), O 6, O 59

Case References:

Australian Broadcasting Corporation v Lenah Game Meats Pty Ltd (2001) 208 CLR 199
Bremer Vulkan Schiffbau und Maschinenfabrik v South India Shipping Corporation Ltd [1981] AC 909
Castlemaine Tooheys Ltd v South Australia (1986) 161 CLR 148
Chief Executive Officer of Customs v AMI Toyota Ltd (2000) 102 FCR 578
Coordinated Construction Co Pty Ltd v Climatech (Canberra) Pty Ltd [2005] NSWCA 229
Coordinated Construction Co Pty Ltd v J M Hargreaves (NSW) Pty Ltd [2005] NSWCA 228
FAI General Insurance Co Ltd v Burns (1996) 9 ANZ Ins Cas 61-384
Fountain Selected Meats (Sales) Pty Ltd v International Produce Merchants Pty Ltd (1988) 81 ALR 397
Lionsgate Australia Pty Ltd v Macquarie Private Portfolio Management Ltd [2007] NSWSC 318
Newport Association Football Club Ltd v Football Association of Wales Ltd [1995] 2 All ER 87
Project Blue Sky Inc v Australian Broadcasting Authority (1998) 194 CLR 355


JURISDICTION : SUPREME COURT OF WESTERN AUSTRALIA
    IN CHAMBERS
CITATION : O'DONNELL GRIFFIN PTY LTD -v- DAVIS & ORS [2007] WASC 215 CORAM : TEMPLEMAN J HEARD : 16 AUGUST 2007 DELIVERED : 16 AUGUST 2007 PUBLISHED : 7 SEPTEMBER 2007 FILE NO/S : CIV 1818 of 2007 BETWEEN : O'DONNELL GRIFFIN PTY LTD (ACN 003 905 093)
    Plaintiff

    AND

    ROGER DAVIS
    First Defendant

    SIEMENS LTD (ACN 004 347 888)
    THIESS SERVICES PTY LTD (ACN 010 221 486) T/AS STCJV SERVICES FOR TELECOMMUNICATIONS JOINT VENTURE (ABN 61 507 423 189)
    Second Defendant

Catchwords:

Practice and procedure - Application for interlocutory injunction to prevent adjudication under the Construction Contracts Act 2004 (WA) - No cause of action disclosed - Failure to comply with O 59 r 9 - Damages an adequate remedy - Balance of convenience favours defendant - Indemnity costs


(Page 2)



Legislation:

Construction Contracts Act 2004 (WA), s 3, s 6, s 25, s 27, s 28, s 31, s 45, s 46


Rules of the Supreme Court 1971 (WA), O 6, O 59

Result:

Application dismissed

Category: A


Representation:

Counsel:


    Plaintiff : Mr P…
CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read O'Donnell Griffin Pty Ltd v Davis and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2007] WASC 215
Decision Date

CaseChat Overview and Summary

The case of O'Donnell Griffin Pty Ltd v Davis involved an application by O'Donnell Griffin, the applicant, for an interlocutory injunction to prevent the defendant, Davis, from initiating adjudication proceedings under the Construction Contracts Act 2004 (WA). The dispute arose from a construction contract between the parties, and the applicant sought to restrain the defendant from pursuing adjudication on the grounds that it would be an abuse of process.

The primary legal issues before the court were whether the applicant had disclosed a cause of action, whether the applicant had complied with the relevant procedural rules, and the balance of convenience between the parties. The court had to determine if the applicant's failure to comply with procedural rules and the adequacy of damages as a remedy would influence the outcome of the injunction application.

The court found that the applicant had not disclosed a cause of action and had failed to comply with Order 59 of the Supreme Court of Western Australia's rules. The court also noted that damages would be an adequate remedy for the applicant if the adjudication proceeded. Furthermore, the balance of convenience favoured the defendant, as the applicant's delay in seeking the injunction would prejudice the defendant. Consequently, the court dismissed the application for an interlocutory injunction. In addition, the court ordered the applicant to pay the defendant's costs on an indemnity basis.

Orders

Orders of the court

Application dismissed

Background

Background to the litigation

Full text does not contain this section.

Evidence

Evidence Before The Court

Full text does not contain this section.

Decision

Reasons for decision

Full text does not contain this section.

Ratio Decidendi

Legal Principle Established

Full text does not contain this section.