O'Brien v Queensland Building Services Authority

Link copied
Case Copied 24 min read
CITATION: O’Brien v Queensland Building Services Authority [2013] QCAT 542
PARTIES: Gerard O’Brien and Susan O’Brien
(Applicants)
v
Queensland Building Services Authority
(Respondent)
APPLICATION NUMBER: GAR365-12
MATTER TYPE: General administrative review matters
HEARING DATE: 12 June 2013
HEARD AT:  Brisbane
DECISION OF: Michael Howe, Member
DELIVERED ON: 11 October 2013
DELIVERED AT: Brisbane
ORDERS MADE:

1     The decision of the Authority made 26 September 2012 is set aside.

2     The Applicants’ claim under the statutory insurance scheme be accepted in respect of items 1, 2, 3, 4, 5 and 7 of the complaint lodged 9 November 2011.

CATCHWORDS:

REVIEW - Review of decision of the Authority – decision to refuse a claim under the statutory insurance scheme out of time -  -  exercise of discretion – explanation for delay – prejudice to the Authority – loss of opportunity to issue direction to rectify – actual as opposed to theoretical loss of opportunity – estoppel of the Authority  – election by the Authority – construction of documents – costs

Queensland Building Services Authority Act 1991 ss 9A(1), 26A, 72
Statutory Instruments Act 1992 ss 7, 9
Acts Interpretation Act 1954 ss 7, 14A(1), 24AA

Holmes v QBSA [2010] QCAT 197
R v Australian Broadcasting Tribunal; Ex parte 2hd Pty Ltd [1979] HCA 62
Swan Hill Shire v Bradbury (1937) 56 CLR 746
Rezaee and Anor v QBSA [2012] QCATA 147
Gallo v Dawson [1990] HCA 30
Mansoor and Rezaee v QBSA [2011] QCAT 53
Vandenhoven v QBSA [2011] QCAT 673
Murphy v QBSA [1996] QBT 207
Jones v Dunkel [1959[ HCA 8
Re Minister of Immigration v Kurtovic [1990] FCA 22
Robertson v Minister of Pensions (1949) 1 KB 227

APPEARANCES and REPRESENTATION (if any):

APPLICANT:  Mr S Hogg of Counsel, instructed by John Drakos, Solicitors

RESPONDENT:  Mr S Formby of Counsel, instructed by Holding Redlich, Solicitors

REASONS FOR DECISION

Background

  1. In March 2008 Mr and Mrs O'Brien contracted with Preferred Builders Pty Ltd to build them a home at Manly.

  2. A certificate of insurance issued pursuant to the statutory home warranty scheme.  Practical completion occurred on 18 October 2009. 

  3. Generally, the owners and Mr Steenland, the builder director behind Preferred Builders Pty Ltd, had a good relationship and when Mr and Mrs O'Brien pointed out various defects after completion they were remedied fairly quickly.  Mr Steenland returned three or four times to do remedial work.  The second time they had to wait some 10 weeks before someone came out, but the work was done.

  4. In December 2010 Mr and Mrs O'Brien noticed tiles lifting and water damage to one of the decks.  Then in January 2011 water leaks became evident in the garage and in the house.  Before that, in 2009, some minor cracks had been noticed in the ceiling in the study area and some cracking on rendered pillars on the pool deck.

  5. In December 2010 and January 2011 there was very heavy rain in Southeast Queensland.  The house developed water leaks.  Mr Steenland was contacted and he came…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read O'Brien v Queensland Building Services Authority and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Find similar cases

Other decisions on the same topics. Each opens in a new tab.

Details

Case
[2013] QCAT 542
Decision Date

CaseChat Overview and Summary

Gerard O'Brien and Susan O'Brien sought review of a decision by the Queensland Building Services Authority (QBSA) to refuse their claim under the statutory insurance scheme. The O'Briens' claim was made out of time, but they argued that the QBSA should exercise its discretion to accept the claim. The QBSA refused the claim, asserting that the O'Briens had failed to lodge the complaint within the time limits set out in the statutory insurance policy and that the delay had prejudiced the QBSA by denying it the opportunity to issue a direction to rectify to the builder. The O'Briens argued that they had a reasonable excuse for the delay and that the delay had not prejudiced the QBSA. The O'Briens also argued that the QBSA had made a representation to them that the claim had been accepted and that the QBSA had made an election to accept the claim. The QCAT set aside the QBSA's decision and ordered that the O'Briens' claim be accepted in respect of six of the seven items of complaint. The QCAT found that the O'Briens had provided a reasonable explanation for the delay in lodging their claim. The QCAT found that the delay had not prejudiced the QBSA. The QCAT also found that the QBSA had not made a representation to the O'Briens that the claim had been accepted and that the QBSA had not made an election to accept the claim. The QCAT ordered that both parties bear their own costs.

Background

Background to the litigation

Decision

Reasons for decision

Ratio Decidendi

Legal principle established