| CITATION: | Vandenhoven v Queensland Building Services Authority [2011] QCAT 673 |
| PARTIES: | Mrs Diane Patricia Vandenhoven |
| v | |
| Queensland Building Services Authority |
| APPLICATION NUMBER: | GAR369-10 |
| MATTER TYPE: | General administrative review matters |
| HEARING DATE: | 12 September 2011 |
| HEARD AT: | Rockhampton |
| DECISION OF: | Gerald Byrne, Member |
| DELIVERED ON: | 22 December 2011 |
| DELIVERED AT: | Rockhampton |
ORDERS MADE: | 1. Application allowed. 2. Direction that the application to claim against the insurance fund be allowed. 3. Direction that the scope of the works listed in the decision be completed. |
| CATCHWORDS: | BUILDING DISPUTE – BSA Statutory Insurance Scheme – considerable delay in complaint to the BSA – waiver by BSA of time limits under insurance scheme – prejudice – appropriate scope to the works – judicial notice Queensland Building Services Authority Act 1991, s 26A |
APPEARANCES and REPRESENTATION (if any):
| APPLICANT: | Mrs Diane Patricia Vandenhoven represented by Steven Deaves of Counsel instructed by Kerry Connolly Howard Lawyers |
| RESPONDENT: | Queensland Building Services Authority represented by Scott Seefeld, Senior Lawyer |
REASONS FOR DECISION
Background
Diane Vandenhoven entered into a residential building works contract with Trueline Aluminium Pty Ltd ACN 10137783 (the builder) for an extension to her house at 9 Pacific Drive Yeppoon in Queensland.
In April 2004 the works were substantially completed and the Certificate of practical completion was issued on 11 October 2004. The Applicant gave evidence that the final payment was also made on 11 October 2004.
Prior to completion of the works, in December 2003 Diane Vandenhoven noticed water penetration from the roof of the internal room of the extension. This was the start of a long list of defects and rectification attempts.
The Applicant gave evidence about much of the process and I found her to be a very open and honest witness.
I set out below the chronology in brief as detailed in the Applicant’s affidavit and Application, including defects and rectification attempts.
Date Description 6 Oct 2003 Contract signed 6 Dec 2003 Building commended Jan 2004 Notification by owner to the builder of a water leak from roof 16 Jan 2004 Builder inspected water leak 23 Jan 2004 Builder installed new roof flashings 7 Feb 2004 Owner noticed roof flashings were lifting and advised builder End Feb 2004 Builder rectified with new roof flashings March 2004 Owner noticed the floor was warped and twisted – called the builder Later in Mar Builder sands corrugations in floor etc Late Apr 2004 Owner notified builder of new leak in a different place May 2004 Builder rectified leak 11 Oct 2004 Practical completion 11 Oct 2004 Final payment Dec 2004 Water entering under window frames – owner phoned builder – builder rescheduled 2 or 3 times Unknown Builder attended – siliconed crevice adjacent to the window Feb 2005 Same leak from windows – owner advisors builder A week later Builder resealed leak from windows and also worked on roof again March 2005 More leaks from roof and windows and owner called builder April 2005 Builder attended to fix leaks again June 2005 Floor boards warped…
Keep reading for free
Create a free CaseChat account to read Vandenhoven v Queensland Building Services Authority and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
Find similar cases
Other decisions on the same topics. Each opens in a new tab.
Details
- Case
- [2011] QCAT 673
- Decision Date
CaseChat Overview and Summary
The court was tasked with determining whether the Queensland Building Services Authority's waiver of time limits under the insurance scheme was appropriate, and if there was any prejudice caused by the delay in lodging the complaint. The court also had to consider the scope of the works that could be reasonably claimed against the insurance fund. The key issue was whether the delay and any associated prejudice were significant enough to preclude the claim from being valid.
The court found that while the delay in lodging the complaint was considerable, the Queensland Building Services Authority had waived the time limits, which indicated a willingness to address the issue. The court took judicial notice of the inherent risks associated with such delays but concluded that the BSA's waiver of the time limits was valid. The court found that there was no significant prejudice to the BSA and that the scope of the works claimed was appropriate. The court held that the application should be allowed, and the insurance fund should cover the costs of completing the listed works.
The orders of the court were that the application to claim against the insurance fund be allowed and that the scope of the works as listed in the decision be completed. The court directed that the Queensland Building Services Authority provide the necessary funding to complete the specified works, thereby resolving the dispute in favour of the applicant.
Orders
Orders of the court
1. Application allowed.
2. Direction that the application to claim against the insurance fund be allowed.
3. Direction that the scope of the works listed in the decision be completed.
Background
Background to the litigation
Decision
Reasons for decision
Ratio Decidendi