Morris v Leaney

Case [2022] NSWCA 95


Court of Appeal


Supreme Court


New South Wales

Medium Neutral Citation: Morris v Leaney [2022] NSWCA 95
Hearing dates: 18 March 2022
Date of orders: 17 June 2022
Decision date: 17 June 2022
Before: Payne JA at [1]
White JA at [2]
Beech-Jones JA at [3]
Decision:

(1)   Appeal dismissed.

(2)   The Appellants pay the Respondent’s costs of the Appeal.

Catchwords:

PROFESSIONAL NEGLIGENCE – architect – respondent was engaged as architect for appellant’s home renovations – appellants indicated initial budget of $300,000 which was later revised to $600,000 – respondent provided “opinion on probable cost” of $590,000 excluding GST and other items in April 2015 for preliminary design – further additions to design thereafter – appellants engaged builder who commenced work on cost plus basis in December 2015 – falling out between parties and appellants continued with builder – by June 2016 substantial increase in costs and some aspects of design not pursued – renovations cost $780,000 but only increased value of house by $330,000 – appellants sued for false and misleading representation about cost of renovations and breach of contractual and tortious duty to advise about cost – appellants claimed damages on a no transaction basis namely that  if known that cost would have exceeded $600,000 would not have undertaken renovations – trial judge rejected appellants evidence of express representations about cost of renovations – trial judge upheld contract and tort claim but only awarded nominal damages – whether trial judge’s approach to damages was erroneous – whether trial judge’s findings warranted finding that respondent obliged to advise appellants that renovations could not be undertaken for $600,000 – whether appellants would not have undertaken renovations if they had been so advised – held – trial judge’s approach to damages erroneous – however not able to conclude that had respondent not breached his contractual and tortious duties then appellants would not have undertaken renovations – appeal dismissed

Legislation Cited:

Competition and Consumer Act 2010 (Cth), Sch 2 – Australian Consumer Law

Civil Liability Act 2002 (NSW)

Supreme Court Act 1970 (NSW)

Cases Cited:

Cappello v Hammond & Simonds NSW Pty Ltd [2021] NSWCA 57

Doepel & Associates Architects Pty Ltd v Hodgkinson [2008] WASCA 262

Gates v City Mutual Life Assurance Society Ltd (1986) 160 CLR 1; [1986] HCA 3

Hilton v Legal Profession Admission Board [2017] NSWCA 232

Leeda Projects Pty Ltd v Zeng (2020) 61 VR 384; [2020] VSCA 192

Martinez as trustee for Martinez HWL Practice Trust as representative of the partners trading as HWL Ebsworth Lawyers v Griffiths as trustee for the Griffiths HWL Practice Trust [2019] NSWCA 310

McBratney v Boston [1994] ATPR 41-355

Morris v Leaney [2021] NSWDC 224

Robinson v Kenny [2014] FCA 988

Voli v Inglewood Shire Council (1963) 110 CLR 74; [1963] HCA 15

Wyzenbeek v Australasian Marine Imports Pty Ltd (in liq) (2019) 272 FCR 373; [2019] FCAFC 167

Texts Cited:

Walmsley, Abadee, Zipser and Sirtes, Professional Liability in Australia (3rd ed, 2016, Law Book Company) 

Continue reading Morris v Leaney

Sign in free to access the full text

Details
AGLC
Morris v Leaney [2022] NSWCA 95
Case
[2022] NSWCA 95
Decision Date

CaseChat Overview and Summary

In *Morris v Leaney*, the appellants, who engaged the respondent architect for home renovations, sued the respondent for professional negligence. The dispute arose from the significant cost overruns of the renovations, which ultimately cost $780,000, far exceeding the appellants' revised budget of $600,000. The appellants alleged that the respondent made false and misleading representations about the cost of the renovations and breached contractual and tortious duties to advise them accurately on the likely expenditure.

The primary legal issues before the Court of Appeal were whether the trial judge erred in their approach to assessing damages, and whether the trial judge's findings supported a conclusion that the respondent was obliged to advise the appellants that the renovations could not be completed within their $600,000 budget. A further question was whether the appellants would have forgone the renovations had they received such advice.

The Court of Appeal held that the trial judge's approach to damages was erroneous. However, despite finding a breach of the respondent's contractual and tortious duties, the Court was unable to conclude that the appellants would not have undertaken the renovations had they been properly advised. Consequently, the appeal was dismissed.

Orders

Orders of the court

(1) Appeal dismissed.

(2) The Appellants pay the Respondent’s costs of the Appeal.

Background

Background to the litigation

Full text does not contain this section.

Evidence

Evidence Before The Court

Full text does not contain this section.

Decision

Reasons for decision

Full text does not contain this section.

Ratio Decidendi

Legal Principle Established

Full text does not contain this section.