SUPREME COURT OF QUEENSLAND
CITATION:
Monarch Building Systems P/L v Quinn Villages P/L [2005] QSC 321
PARTIES:
MONARCH BUILDING SYSTEMS PTY LTD ACN 000 776 189
(plaintiff)
v
QUINN VILLAGES PTY LTD ACN 000 776 189
(defendant)FILE NO/S:
BS 2436 of 2001
DIVISION:
Trial Division
PROCEEDING:
Claim
ORIGINATING COURT:
Supreme Court, Brisbane
DELIVERED ON:
4 November 2005
DELIVERED AT:
Brisbane
HEARING DATE:
26 October 2005
JUDGE:
de Jersey CJ
ORDERS:
1. Declaration that there was not a concluded contract between the parties as alleged by the defendant
2. Further hearing of the proceeding adjourned to a date to be fixed
3. Costs reserved with liberty to apply
CATCHWORDS:
CONTRACTS – GENERAL CONTRACTUAL PRINCIPLES – OFFER AND ACCEPTANCE – CONTRACT IMPLIED FROM CONDUCT OF PARTIES – where there was no contractual document executed by both parties – where ultimate sticking point between the parties concerned the provision for liquidated damages in respect of delay – where plaintiff contended the parties’ intention was not to make a concluded bargain at all, unless and until they executed a formal contract – where defendant contended the parties’ conduct was consistent with being bound to a contract which did not include any effective provision for liquidated damages – whether the parties intended to be bound to the extent they had reached agreement
Sale of Goods Act 1896 (Qld)
African Minerals Ltd v Pan Palladium Ltd [2003] NSWSC 268
Alford & Ors v Ebbage & Ors [2004] QCA 283
Brambles Holdings Ltd v Bathurst City Council (2001) 53 NSWLR 153
Eastgate Properties P/L v J Hutchinson P/L [2005] QSC 196
Integrated Computer Services Pty Ltd v Digital Equipment Corp(Aust) Pty Ltd (1988) 5 BPR 11, 110
Masters v Cameron (1954) 91 CLR 353
Meates v Attorney-General [1983] NZLR 308
Pagnan SpA v Feed Products Ltd [1987] 2 Lloyd’s Rep 601COUNSEL:
B Laurie for the plaintiff
S Couper QC for the defendantSOLICITORS:
Simmonds Crowley & Galvin for the plaintiff
Plastiras Meredith Mohr Lawyers for the defendant
Introduction
The plaintiff (“Monarch”) manufactures and supplies steel products for the building industry. In the year 2000, Monarch supplied such products for incorporation into a home unit development at Mount Coolum. The defendant (“Quinn”) was the developer. Quinn’s project manager was Global Construction Management Pty Ltd (“Global”).
Monarch sues Quinn, on the basis of a quantum meruit, for the unpaid value of goods supplied. Monarch’s pleaded position is that between February and June 2000, it had unsuccessfully sought to negotiate with Quinn an agreement to cover the supply. On the other hand, Quinn pleads that a contract was in fact concluded in about March 2000, for the design, fabrication, supply and delivery of the goods, a contract “partly written, partly oral and partly implied”.
Determination of preliminary issue
The pleadings raise a host of factual issues alleging non-compliance by Monarch with its obligations, and consequential losses to Quinn. On 28 January 2005 the court ordered that “there be a separate determination of the issues raised by…
Keep reading for free
Create a free CaseChat account to read Monarch Building Systems P/L v Quinn Villages P/L and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2005] QSC 321
- Decision Date
CaseChat Overview and Summary
The primary legal issue before the court was whether the parties intended to be bound to the extent they had reached agreement, despite the absence of a formal executed contract. The court had to determine whether the parties' conduct and correspondence amounted to an implied contract. The plaintiff argued that there was no concluded bargain until a formal contract was executed, while the defendant contended that the parties' conduct indicated an intention to be contractually bound without the need for a formal document.
The court found that there was no concluded contract between the parties as alleged by the defendant. The reasoning was based on the lack of a formal executed contract and the absence of an intention to be bound by a contract until such a document was executed. The court held that the parties had not reached an agreement on all material terms, including the provision for liquidated damages, which was a significant sticking point in the negotiations. Consequently, the court granted the plaintiff's application for a declaration that there was no concluded contract between the parties as alleged by the defendant. The proceedings were further adjourned, and costs were reserved with liberty to apply.
Orders
Orders of the court
1. Declaration that there was not a concluded contract between the parties as alleged by the defendant
2. Further hearing of the proceeding adjourned to a date to be fixed
3. Costs reserved with liberty to apply
Background
Background to the litigation
Evidence
Evidence Before The Court
Decision
Reasons for decision
Ratio Decidendi