FEDERAL COURT OF AUSTRALIA
Management 3 Group Pty Ltd (In Liq) v Lenny’s Commercial Kitchens Pty Ltd [2011] FCAFC 162
Citation: Management 3 Group Pty Ltd (In Liq) v Lenny’s Commercial Kitchens Pty Ltd [2011] FCAFC 162 Appeal from: Management 3 Group Pty Ltd (in liq) v Lenny’s Commercial Kitchens Pty Ltd (No 2) [2011] FCA 663 Parties: MANAGEMENT 3 GROUP PTY LTD (IN LIQUIDATION) ACN 100 863 036 and ANDREW REGINALD YEO AND GESS MICHAEL RAMBALDI (AS LIQUIDATORS OF MANAGEMENT 3 GROUP PTY LTD (IN LIQUIDATION) ACN 100 863 036 v LENNY’S COMMERCIAL KITCHENS PTY LTD ACN 009 044 295 and SINO IRON PTY LTD ACN 058 429 708 File number: VID 735 of 2011 Judges: LANDER, GILMOUR & GORDON JJ Date of judgment: 12 December 2011 Catchwords: CONTRACTS – interpretation – construction contract – clause relating to purchase of unaffixed items – full payment not made by Principal – whether Principal acquired ownership of items pursuant to clause
TORTS – conversion – ownership of unaffixed items – whether items converted – measure of damages
Legislation: Corporations Act 2001 (Cth), s 440C Cases cited: Associated Midland Corporation Ltd v Bank of New South Wales [1983] 1 NSWLR 533 cited
Australian Broadcasting Commission v Australasian Performing Right Association Ltd (1973) 129 CLR 99 cited
Egan v State Transport Authority (1982) 31 SASR 481 cited
MLW Technology Pty Ltd v May [2005] VSCA 29 cited
Pacific Carriers Ltd v BNP Paribas (2004) 218 CLR 451 cited
R J Grills Pty Ltd v Dellios [1988] VR 136 cited
Toll (FGCT) Pty Ltd v Alphapharm Pty Ltd (2004) 219 CLR 165 citedDate of hearing: 16 November 2011 Place: Melbourne Division: GENERAL DIVISION Category: Catchwords Number of paragraphs: 80 Counsel for the Appellants: Mr L Glick SC with Ms C Pierce Solicitor for the Appellants: Russell Kennedy Counsel for the Respondents: Mr J Digby QC Solicitor for the Respondents: Johnson Winter & Slattery
IN THE FEDERAL COURT OF AUSTRALIA
VICTORIA DISTRICT REGISTRY
GENERAL DIVISION
VID 735 of 2011
ON APPEAL FROM THE FEDERAL COURT OF AUSTRALIA
BETWEEN: MANAGEMENT 3 GROUP PTY LTD (IN LIQUIDATION) ACN 100 863 036
First AppellantANDREW REGINALD YEO AND GESS MICHAEL RAMBALDI (AS LIQUIDATORS OF MANAGEMENT 3 GROUP PTY LTD (IN LIQUIDATION) ACN 100 863 036
Second and Third AppellantsAND: LENNY’S COMMERCIAL KITCHENS PTY LTD
ACN 009 044 295
First RespondentSINO IRON PTY LTD ACN 058 429 708
Second Respondent
JUDGES:
LANDER, GILMOUR & GORDON JJ
DATE OF ORDER:
12 DECEMBER 2011
WHERE MADE:
MELBOURNE
THE COURT ORDERS THAT:
1.The appeal be allowed.
2.The appellants bring forward short minutes of order.
Note:Entry of orders is dealt with in Rule 39.32 of the Federal Court Rules 2011.
IN THE FEDERAL COURT OF AUSTRALIA
VICTORIA DISTRICT REGISTRY
GENERAL DIVISION
VID 735 of 2011
ON APPEAL FROM THE FEDERAL COURT OF AUSTRALIA
BETWEEN: MANAGEMENT 3 GROUP PTY LTD (IN LIQUIDATION) ACN 100 863 036
First AppellantANDREW REGINALD YEO AND GESS MICHAEL RAMBALDI (AS LIQUIDATORS OF MANAGEMENT 3…
Keep reading for free
Create a free CaseChat account to read Management 3 Group Pty Ltd (In Liq) v Lenny's Commercial Kit... and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
Details
- Case
- [2011] FCAFC 162
- Decision Date
CaseChat Overview and Summary
The primary legal issue was the interpretation of clause 42.2 of the Contract between M3G and Sino, which related to the purchase of unaffixed items. The court had to determine whether full payment for these items had been made by Sino, and consequently, whether Sino or M3G owned the unaffixed goods at the time of M3G's administration. If Sino owned the goods, there was no conversion; if M3G owned them, Sino's actions constituted conversion. Additionally, the court considered the measure of damages in a conversion claim, which is assessed by reference to the value of the property at the date of conversion.
The court held that the primary judge's interpretation of clause 42.2 was incorrect. It found that the clause should be construed in the context of the entire Contract and that the ordinary meaning of the words should not lead to a capricious or unreasonable result. The court concluded that M3G owned the unaffixed goods at the time of administration, and Sino's installation of those goods constituted conversion. Therefore, Sino was liable to M3G for the total value of those goods at the date of conversion, which was $236,000. The court also noted that damages should be assessed by reference to the value of the goods at the date of conversion, in the place they were located, and in the state they were in at that time.
The final orders of the court were to allow the appeal and for the appellant to bring forward short minutes of order. The specific entry of orders is governed by Rule 39.32 of the Federal Court Rules 2011.
Orders
Orders of the court
1. The appeal be allowed.
2. The appellants bring forward short minutes of order.
Note: Entry of orders is dealt with in Rule 39.32 of the Federal Court Rules 2011.
Background
Background to the litigation
Evidence
Evidence before the court
Decision
Reasons for decision
Ratio Decidendi
Legal principle established
There was an additional complication in this proceeding, and that relates to the question of damages, the quantum of which was a live issue before the primary judge and on appeal. In a claim for conversion the plaintiff’s damages are to be assessed as at the date of the conversion by reference to the value of the property at that date: Associated Midland Corporation Ltd v Bank of New South Wales [1983] 1 NSWLR 533 at 550 per Mahoney JA. The only evidence led by the appellants as to the value of the Additional Goods in the place they were located and the state they were in on 7 April 2009 was the invoices that had issued when M3G had purchased the goods.Consideration of Appeal Clause 42.2 has to be construed in the context of the Contract as a whole because the other provisions may reveal the proper meaning of the clause under consideration. If the words are plain and unambiguous they must be given their plain meaning, even if that leads to a capricious or unreasonable result. However, if the ordinary meaning of the words is inconsistent with other clauses of the Contract, that may be a reason to depart from the plain meaning. If the words are ambiguous then the words should be given a meaning that is not “capricious, unreasonable, inconvenient or unjust”: Australian Broadcasting Commission v Australasian Performing Right Association Ltd (1973) 129 CLR 99 at 109 per Gibbs J. A commercial contract should be construed in accordance with business commonsense: MLW Technology Pty Ltd v May [2005] VSCA 29. The Contract required M3G to execute the works identified in the Contract in accordance with the terms of the Contract. The Contract contained as Schedule 1 the “Australian Standard General Conditions of Contract for Design and Construct” (Standard). The Standard covers the following type of project procurement methods:(a) Design and Construct Contract.(b) Design Development and Construct Contract.(c) Design, Novate and Construct Contract. Clause 3.1 of the Contract provides that the Contractor (M3G) shall execute and complete the work under the Contract in accordance with the requirements of the Contract. The work under the Contract is defined to mean “the work which the Contractor is or may be required to execute under the Contract and includes the Contractor’s Design Obligations, variations, remedial work, Constructional Plant and Temporary Works”. The “works” is defined to mean “the whole of the work to be executed in accordance with the Contract, including variations provided for by the Contract, which by the Contract is to be handed over to the Principal”. Clause 5.1 provides for the Contractor to give security for the purpose of ensuring the due and proper performance of the Contract. Clause 5 states that the security required to be provided is identified in Annexure Part A. Clause 5.9 addresses the release of security if security is being given by the Contractor. It provides:If the Contractor has provided security then the Principal shall release it when required by Clause 42.6. If the Contractor has provided additional security for any item of unfixed plant and materials pursuant to Clause 42.2, the Principal shall release that additional security within 14 days of the incorporation into the Works of the unfixed plant or materials.