Case Title: Delta Electricity v Centennial Mandalong Pty Ltd Medium Neutral Citation: [2014] NSWCA 178 Hearing Date(s): 22 April 2014 Decision Date: 06 June 2014 Before: McColl JA at [1]; Barrett JA at [2]; Ward JA at [3] Decision: Appeal dismissed with costs
[Note: The Uniform Civil Procedure Rules 2005 provide (Rule 36.11) that unless the Court otherwise orders, a judgment or order is taken to be entered when it is recorded in the Court's computerised court record system. Setting aside and variation of judgments or orders is dealt with by Rules 36.15, 36.16, 36.17 and 36.18. Parties should in particular note the time limit of fourteen days in Rule 36.16.]
Catchwords: CONTRACTS - general contractual principles - construction and interpretation of contracts - whether government charges imposed under the national carbon pricing scheme on methane emissions were charges "attributable to" coal sold by the respondent and purchased by the appellant Legislation Cited: Clean Energy Act 2011 (Cth)
Clean Energy (Consequential Amendments Act) 2011 (Cth)
Clean Energy (Unit Shortfall Charge - General) Act 2011 (Cth)
Coal and Oil Shale Mine Workers (Superannuation) Act 1941(NSW)
Coal Industry Act 2001(NSW)
Fair Trading Act 1973 (UK)
Mine Subsidence Compensation Act 1961 (NSW)
Mining (General) Regulation 1997 (NSW)
National Greenhouse and Energy Reporting Act 2007 (Cth)
National Greenhouse and Energy Reporting (Measurement) Determination 2008 (Cth)Cases Cited: Central Asbestos Co Ltd v Dodd [1973] AC 518
Codelfa Construction Pty Ltd v State Rail Authority of New South Wales [1982] HCA 24; (1982) 149 CLR 337
Dryden Construction Co Ltd v New Zealand Insurance Co Ltd [1959] NZLR 1336
Electricity Generation Corporation v Woodside Energy Ltd [2014] HCA 7; (2014) 88 ALJR 447
R v Monopolies and Mergers Commission, Ex parte National House Building Council [1994] TLR 38
Re Golden Key Ltd [2009] EWCA Civ 636
Reardon Smith Line Ltd v Hansen-Tangen [1976] 1 WLR 989; [1976] 3 All ER 570
Repatriation Commission v Law (1980) 31 ALR 140
Roncevich v Repatriation Commission [2005] HCA 40; (2005) 222 CLR 115
Total Transport Corp v Arcadia Petroleum Ltd (The Eurus) [1998] 1 Lloyd's Rep 351
Zhu v Treasurer of New South Wales [2004] HCA 56 at [82]; (2004) 218 CLR 530Texts Cited: Sir Kim Lewison and David Hughes, The Interpretation of Contracts in Australia (2012, Thomson Reuters)
J W Carter, The Construction of Commercial Contracts, (2012, Hart Publishing)Category: Principal judgment Parties: Delta Electricity (Appellant)
Centennial Mandalong Pty Ltd (Respondent)Representation - Counsel: Counsel:
NC Hutley SC with JA Watson (Appellant)
AC Archibald QC with JR Williams (Respondent)- Solicitors: Solicitors:
Jones Day (Appellant)
Herbert Smith Freehills (Respondent)File Number(s): CA 2013/380234 Decision Under Appeal - Before: McDougall J - Citation: [2013] NSWSC 1505; [2013] NSWSC 1860 - Court File Number(s): 2012/384031 Publication Restriction: Nil
HEADNOTE
[This Headnote is not to be read as part of the judgment]
This judgment relates to an appeal by Delta Electricity, the owner and operator of the Vales…
Keep reading for free
Create a free CaseChat account to read Mahdi Jahandideh v R and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
Find similar cases
Other decisions on the same topics. Each opens in a new tab.
Details
- Case
- [2014] NSWCA 178
- Decision Date
CaseChat Overview and Summary
The Court of Appeal was required to determine the proper construction of the contractual term "attributable to" in the context of the specific sale of coal. This involved considering whether the methane emissions, and the associated government charges, were sufficiently connected to the coal itself to fall within the scope of the contractual provision. The court had to assess the intention of the parties as expressed in the contract and apply general principles of contractual interpretation to resolve this ambiguity.
The Court of Appeal reasoned that the phrase "attributable to" required a direct causal or consequential link between the methane emissions and the coal sold. Applying established principles of contractual construction, the court found that the carbon pricing scheme's charges on methane emissions were not directly attributable to the coal in the manner contemplated by the contract. The court concluded that the charges were a consequence of the broader environmental impact of the coal's extraction and use, rather than an inherent characteristic or direct cost of the coal itself as sold. Consequently, the appeal was dismissed.
Orders
Orders of the court
Appeal dismissed with costs
[Note: The Uniform Civil Procedure Rules 2005 provide (Rule 36.11) that unless the Court otherwise orders, a judgment or order is taken to be entered when it is recorded in the Court's computerised court record system. Setting aside and variation of judgments or orders is dealt with by Rules 36.15, 36.16, 36.17 and 36.18. Parties should in particular note the time limit of fourteen days in Rule 36.16.]
Background
Background to the litigation
Decision
Reasons for decision
Ratio Decidendi