Lyons v Queensland Building and Construction Commission & Dreamstarter Pty Ltd (in liquidation)

Link copied
Case Copied 83 min read
CITATION: Lyons v Queensland Building and Construction Commission & Dreamstarter Pty Ltd (in liquidation) [2016] QCAT 218
PARTIES: Andrew Lyons
(Applicant)
v
Queensland Building and Construction Commission
(First Respondent)
and
Dreamstarter Pty Ltd (in liquidation)
(Second Respondent)
APPLICATION NUMBER: GAR 150-10; BDL 222-10
MATTER TYPE:

General administrative review matters

HEARING DATE: 19 October, 2015 and 2 November, 2015
HEARD AT: Brisbane
DECISION OF: Member Ann Fitzpatrick
DELIVERED ON: 9 June 2016
DELIVERED AT: Brisbane
ORDERS MADE:

It is ordered that:

[1]   The decision of the Queensland Building and Construction Commission, made on 19 April, 2010 be substituted with the following decision:-

“Mr Lyons’ claim for assistance under the Statutory Home Warranty Insurance Scheme be accepted on the basis that Mr Lyons:

(a)  has properly terminated the contract with Dreamstarter Pty Ltd dated 20 June, 2009, as varied;

(b)  has properly terminated the agreement constituted or evidenced by Variation 1 dated 14 October, 2009 validly on 3 December, 2009 for Dreamstarter Pty Ltd’s default;

(c)  liability to Dreamstarter Pty Ltd under the Contract at the date of termination of the Contract was nil; and

(d)  reasonable cost of completing the Contract following termination exceeds $435,000.00.”

[2]   It is declared that the Queensland Building and Construction Commission paid Mr Lyons the sum of $200,000.00 pursuant to the terms of the “BSA Home Warranty Insurance Policy” on 8 April, 2013.

[3]   The Queensland Building and Construction Commission pay to Mr Lyons the following costs:

a)    In addition to his costs fixed at $1,000.00 in APL299-10, all his costs of and incidental to  GAR150-10, including:

(1)    this application;

(2)   all of his costs of BDL222-10 from 25 November, 2011 to the date of this order;

(3)   his costs of registering two judgments in the Magistrates Court, being M7040/12 and M7041/12; assessed on the Magistrates Court scale on a standard basis;

(4)   his costs of winding up Dreamstarter Pty Ltd in Federal Court of Australia proceedings QUD 322 of 2012; assessed on the Federal Court scale on a party and party basis;

(5)   his costs of obtaining leave to proceed against Dreamstarter Pty Ltd (in liquidation), in Supreme Court Proceedings S8077/2012 assessed on the Supreme Court Scale on a standard basis;

(6)   the costs of the liquidation of Dreamstarter Pty Ltd, in an amount of $17,500.00;

(7)   the costs of obtaining the order made 14 September, 2012 in APL086-12, fixed at $30,660.60.

[4]   Unless otherwise ordered, the costs to be assessed on the District Court Scale on a standard basis.

[5]    Unless otherwise fixed, the costs be fixed in accordance with a costs report prepared by Mr Stephen Hartwell, costs assessor, or such other costs assessor as may be nominated by Mr Lyons.

CATCHWORDS:

Costs – costs of related proceedings – non-party order for costs – discretion – interest on costs.

Acts Interpretation Act 1954 (Qld), ss20, 27B
Civil Proceedings Act 2011 (Qld), s58;
Queensland Building and Construction Commission Act 1991 (Qld), s77;
Queensland Civil and Administrative Tribunal Act 2009 (Qld), ss3, 442,48, 102, 106,…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Lyons v Queensland Building and Construction Commission & Dr... and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2016] QCAT 218
Decision Date

CaseChat Overview and Summary

In this matter, the plaintiff, Mr Lyons, was involved in a contractual dispute with Dreamstarter Pty Ltd. The Queensland Building and Construction Commission (QBCC) was also a party to the proceedings. The dispute centred around the validity of contract terminations and the application of the Statutory Home Warranty Insurance Scheme. The case was heard in the Supreme Court of Queensland.

The court was tasked with determining whether Mr Lyons had properly terminated the contract with Dreamstarter Pty Ltd and whether the QBCC should pay him under the terms of the statutory warranty scheme. The court also had to decide on the costs to be awarded to Mr Lyons, including those related to various proceedings and actions taken against Dreamstarter Pty Ltd.

The court found that Mr Lyons had properly terminated the contract with Dreamstarter Pty Ltd and was entitled to compensation under the statutory warranty scheme. In relation to the costs, the court exercised its discretion under the relevant legislation to order that the QBCC pay Mr Lyons' costs. These costs included those related to the current application, previous proceedings, obtaining leave in another court, and the liquidation of Dreamstarter Pty Ltd. The court determined that these costs should be assessed on the District Court Scale, with specific instructions for the assessment of certain costs by a nominated costs assessor.

The court ordered that the decision of the QBCC be substituted with a new decision accepting Mr Lyons' claim for assistance. It also declared that the QBCC had already paid Mr Lyons $200,000.00 under the warranty policy and ordered the payment of further costs as outlined in the judgment.

Orders

Orders of the court

It is ordered that:

[1] The decision of the Queensland Building and Construction Commission, made on 19 April, 2010 be substituted with the following decision:-

“Mr Lyons’ claim for assistance under the Statutory Home Warranty Insurance Scheme be accepted on the basis that Mr Lyons:

(a) has properly terminated the contract with Dreamstarter Pty Ltd dated 20 June, 2009, as varied;

(b) has properly terminated the agreement constituted or evidenced by Variation 1 dated 14 October, 2009 validly on 3 December, 2009 for Dreamstarter Pty Ltd’s default;

(c) liability to Dreamstarter Pty Ltd under the Contract at the date of termination of the Contract was nil; and

(d) reasonable cost of completing the Contract following termination exceeds $435,000.00.”

[2] It is declared that the Queensland Building and Construction Commission paid Mr Lyons the sum of $200,000.00 pursuant to the terms of the “BSA Home Warranty Insurance Policy” on 8 April, 2013.

[3] The Queensland Building and Construction Commission pay to Mr Lyons the following costs:

a) In addition to his costs fixed at $1,000.00 in APL299-10, all his costs of and incidental to GAR150-10, including:

(1) this application;

(2) all of his costs of BDL222-10 from 25 November, 2011 to the date of this order;

(3) his costs of registering two judgments in the Magistrates Court, being M7040/12 and M7041/12; assessed on the Magistrates Court scale on a standard basis;

(4) his costs of winding up Dreamstarter Pty Ltd in Federal Court of Australia proceedings QUD 322 of 2012; assessed on the Federal Court scale on a party and party basis;

(5) his costs of obtaining leave to proceed against Dreamstarter Pty Ltd (in liquidation), in Supreme Court Proceedings S8077/2012 assessed on the Supreme Court Scale on a standard basis;

(6) the costs of the liquidation of Dreamstarter Pty Ltd, in an amount of $17,500.00;

(7) the costs of obtaining the order made 14 September, 2012 in APL086-12, fixed at $30,660.60.

[4] Unless otherwise ordered, the costs to be assessed on the District Court Scale on a standard basis.

[5] Unless otherwise fixed, the costs be fixed in accordance with a costs report prepared by Mr Stephen Hartwell, costs assessor, or such other costs assessor as may be nominated by Mr Lyons.

Background

Background to the litigation

Evidence

Evidence Before The Court

Decision

Reasons for decision

Ratio Decidendi

Legal Principle Established