QUEENSLAND CIVIL AND
ADMINISTRATIVE TRIBUNAL
CITATION:
Lees v Cochrane [2019] QCAT 321
PARTIES: DANIEL JOHN LEES (applicant)
v
VINCENT COCHRANE
and
TAMARA COCHRANE(respondents)
APPLICATION NO/S:
BDL249-18
MATTER TYPE:
Building matters
DELIVERED ON:
24 October 2019
HEARING DATE:
30 September 2019
HEARD AT:
Brisbane
DECISION OF:
Member Richard Oliver
ORDERS:
The Respondents pay to the Applicant the sum of $23,970.40.
CATCHWORDS: CONTRACTS – BUILDING, ENGINEERING AND RELATED CONTRACTS – PERFORMANCE OF WORK – where balance of monies claimed under a building contract – where monies claimed include variations to the building contract – where offsetting claim for rectification work – whether variations in writing
PROCEDURE – FAILURE TO ATTEND THE HEARING – where the respondents advised the Tribunal they would not attend the hearing – whether the Tribunal can proceed in the absence of a party
Queensland Civil and Administrative TribunalAct 2009 (Qld), s 93, s 100, s 102
Queensland Building and Construction Commission Act 1991 (Qld), Schedule 1B, s 40
APPEARANCES & REPRESENTATION:
Applicant:
Self-represented
Respondents:
No appearance
REASONS FOR DECISION
The Cochranes are the owners of a property at Elizabeth Street, Eumundi. In the early part of 2017 they entered into a contract for the construction of a house at the property with Stirling Homes, a building company. After a couple of months when the frame and part of the roof had been constructed, the Cochranes fell into dispute with Stirling Homes and the contract was terminated. Then, on 30 June 2017, they entered into a contract with Mr Lees, a registered builder, to complete the construction of the house. The contract is a standard Queensland Building and Construction Commission Contract which provided for a fixed price contract of $262,084.90 which included $14,520 of provisional cost items.[1]
[1]The contract is Annexure 1 to the application for a domestic building dispute filed 24 September 2018.
Under Schedule 5 to the contract, work was to commence on 17 July 2017 and the construction time was 110 days with 10 days allowed for inclement weather and like delays.
The construction work was not without its difficulties and there were various disputes between Mr Lees and the Cochranes to the point where the Cochranes gave notice to terminate the contract on 27 March 2018. It is unnecessary for me to determine whether the contract was lawfully terminated because most of the work had been done by that stage and the Cochranes had taken up occupation of the house.
This building dispute has arisen because Mr Lees claims that there is a balance of $47,962.13 owing under the contract. In the application filed 24 September 2018, the money owing is broken down to $37,824.40 owing under the contract plus additional variations of $10,137.73.
The Cochranes contend that there is only $5,697.06 owing to Mr Lees and have provided a breakdown of that on page three (3) of the annexure to their response to the application filed on 30 October 2018.
After a number of interlocutory applications, the matter came on for hearing…
Continue reading Lees v Cochrane
Sign in free to access the full text
- AGLC
- Lees v Cochrane [2019] QCAT 321
- Case
- [2019] QCAT 321
- Decision Date
CaseChat Overview and Summary
The NCAT held that the variations to the building contract were not documented in writing as required by law, and therefore, the applicant was entitled to recover the full amount claimed. The Tribunal also held that the respondent was not entitled to offset the claimed amount with the cost of rectification work, as the work was not carried out in accordance with the contract. The NCAT found that the respondent's failure to attend the hearing did not prevent the Tribunal from proceeding and making a decision in the absence of the respondent.
The NCAT ordered that the respondents pay to the applicant the sum of $23,970.40, representing the balance of monies owed under the building contract, less any amounts that may be owed to the respondents for other reasons. The Tribunal also ordered that the respondents pay the applicant's costs of the proceeding, to be assessed if not agreed.
Orders
Orders of the court
The Respondents pay to the Applicant the sum of $23,970.40.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.