Kyren Pty Ltd v Wunda Projects Australia Pty Ltd

Link copied
Case Copied 79 min read

SUPREME COURT OF SOUTH AUSTRALIA

(Full Court: Civil)

KYREN PTY LTD v WUNDA PROJECTS AUSTRALIA PTY LTD & ORS

[2012] SASCFC 23

Judgment of The Full Court

(The Honourable Justice Sulan, The Honourable Justice Anderson and The Honourable Justice David)

15 March 2012

CONTRACTS - BUILDING, ENGINEERING AND RELATED CONTRACTS - THE CONTRACT - CONSTRUCTION OF PARTICULAR CONTRACTS AND IMPLIED CONDITIONS - VARIATIONS

CONTRACTS - GENERAL CONTRACTUAL PRINCIPLES - DISCHARGE, BREACH AND DEFENCES TO ACTION FOR BREACH - REPUDIATION AND NON-PERFORMANCE

CONTRACTS - BUILDING, ENGINEERING AND RELATED CONTRACTS - REMUNERATION - RECOVERY ON QUANTUM MERUIT

Kyren Pty Ltd (“the appellant”) and Wunda Projects Australia Pty Ltd (“the respondent”) negotiated a contract related to the construction of an apartment building on North Terrace, Adelaide – the appellant, as principal, removed works from the respondent contractor – the respondent brought a claim against the appellant for unpaid works, variations and loss of profits – trial Judge found in favour of the respondent and dismissed the cross claim brought by the appellant.

The parties agreed to vary the contract substituting tax invoices for progress payment claims  – whether the effect of the contractual variations was to render the tax invoices conclusive – whether the appellant repudiated the contract – whether the respondent complied with the notice provisions of the contract – whether the directions given by the superintendent before repudiation was accepted by the respondent were effective in withdrawing work from the scope of the contract – whether the appellant was entitled to liquidated damages under the contract – whether the trial Judge erred in not granting an application to reopen the case to allow the appellant to plead two additional matters not raised at trial.

Held:  Appeal allowed in respect of two key issues raised on appeal – the Judge was in error in his conclusion that the tax invoices were conclusive – there was an express agreement between the parties that tax invoices would only be issued after the parties had inspected the works and agreed the percentage of the work that had been completed – Kyren was entitled to remove work from the respondent following its repudiation and breach of contract – until the respondent accepted the appellant’s repudiation, the contract remained on foot.

Building Work Contractors Act 1995 (SA) s 6, s 6(2), referred to.
Fox v Percy (2003) 214 CLR 118; Berry v Wong [2000] NSWSC 1002; Integrated Computer Services Pty Ltd v Digital Equipment Corp (Aust) Pty Ltd (1988) 5 BPR 11110; Laurinda Pty Ltd v Capalaba Park Shopping Centre Pty Ltd (1989) 166 CLR 623; Peninsula Balmain Pty Ltd v Abigroup Contractors Pty Ltd (2002) 18 BCL 322; [2002] NSWCA 211; Koompahtoo Local Aboriginal Land Council v Sanpine Pty Ltd (2007) 233 CLR 115; Shevill v The Builders Licensing Board (1982) 149 CLR 620; Kennedy v Collings Construction Company Pty Ltd (1989) 7 BCL 25; Jennings Construction Ltd v Q H & M Birt Pty Ltd (1986) 8 NSWLR…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Kyren Pty Ltd v Wunda Projects Australia Pty Ltd and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2012] SASCFC 23
Decision Date

CaseChat Overview and Summary

Kyren Pty Ltd (the appellant) and Wunda Projects Australia Pty Ltd (the respondent) entered into a contract for the construction of an apartment building. Disputes arose when the appellant removed certain works from the respondent's scope. The respondent subsequently claimed payment for unpaid works, variations, and loss of profits, while the appellant cross-claimed. The trial judge found in favour of the respondent.

The appeal concerned several legal issues, including whether contractual variations meant that tax invoices were conclusive, whether the appellant had repudiated the contract, the effectiveness of the respondent's compliance with notice provisions, the validity of directions to withdraw work before repudiation was accepted, the appellant's entitlement to liquidated damages, and whether the trial judge erred in refusing to allow the appellant to reopen its case to plead additional matters.

The Full Court of the Supreme Court of South Australia allowed the appeal on two key issues. It held that the trial judge erred in concluding that the tax invoices were conclusive, finding instead that there was an express agreement that tax invoices would only be issued after inspection and agreement on the percentage of work completed. The Court also found that the appellant was entitled to remove work from the respondent following the respondent's repudiation and breach of contract, and that the contract remained on foot until the repudiation was accepted. The Court dismissed the appeal on all other grounds and allowed the notice of alternative contention, confirming the respondent's right to elect for payment on a quantum meruit basis for work completed. The parties were directed to meet and attempt to agree on a final judgment figure within 21 days, based on detailed schedules prepared by the appellant's solicitors.

Orders

Orders of the court

Full text does not contain this section.

Background

Background to the litigation

THE COURTBackground This is an appeal from a decision of a Judge of the District Court by Kyren Pty Ltd (“Kyren”), allowing a claim by the respondent, Wunda Projects Australia Pty Ltd (“Wunda”) in the sum of $629,934.40. Anna Maria Marveggio is joined as the second respondent to the action as Trustee for the WPA Trust and WPA Nominees Pty Ltd is joined as the third respondent as Trustee for the Wunda Projects Trust. The second and third respondents were joined in the action after trial following the appellant becoming aware that Wunda operated for and on behalf of the Wunda Projects Australia Partnership of which the second and third respondents are members. When we refer to the respondent, this is to be taken to mean Wunda. The project The litigation relates to the building of a multistorey apartment building on North Terrace, Adelaide. On 2 June 2006, Wunda contracted with Kyren to carry out the internal finishing works on the building. The project was known as the “Palais project”. The primary purpose of the project was to provide accommodation for university students. Kyren’s plan was to complete the building for occupation by students in the 2007 academic year. Ultimately, the contract divided the work into three areas:·The installation of plasterboard petitioning, corridor and internal walling and ceilings (“CW works”), valued at $2.56 million; ·The completion of carpentry works, valued at approximately $163,000; and ·Painting works valued at approximately $165,000. Wunda directly undertook the carpentry works, but subcontracted the CW and painting works to E & M Linings Pty Ltd (“E & M”) and Asset Painting & Maintenance Services Pty Ltd (“Asset Painting”) respectively. Work commenced on 24 July 2006. The works did not progress as scheduled. After disputes arose in relation to the performance of the works, Kyren took the remaining CW and painting works out of Wunda’s hands on 18 January 2007 and, later, the remaining carpentry works on 1 February 2007. Kyren then paid other contractors to complete the works. Practical completion was achieved on 20 March 2007, approximately a month a half after the contracted practical completion date of 31 January 2007. Negotiation history In order to understand the various disputes that are the subject of the litigation and the issues argued in this appeal, it is necessary to trace the history of the negotiations and to describe the role of various persons involved in the negotiations and the subsequent administration of the contract. In March 2006, Mr Kon Corolis (“Corolis”) was employed by Kyren to manage the development. Mr Theo Samaras (“Samaras”), a director of Kyren, authorised Corolis to engage Wunda to undertake the three packages of works. The trial Judge described the circumstances in which the parties came together for the Palais project. He observed that Corolis, who had formally been employed by the Adelaide City Council, had had previous dealings with Wunda and, in particular, Mr Tony Basile (“Basile”), who was Wunda’s principal project manager.

Evidence

Evidence Before The Court

Full text does not contain this section.

Decision

Reasons for decision

The two aspects upon which Kyren seeks to reopen its case are related. It is our view that it is simply too late to do this. The application to reopen followed a 46 day trial, a very detailed judgment and then an argument and subsequent order on costs.Conclusion We would allow the appeal in respect of key issues 1 and 4. We would dismiss the appeal on all other grounds. We would allow the notice of alternative contention. Wunda has a right to elect for payment by quantum meruit in order to recover for the work that had been completed at the time that the contract was terminated. Prior to the hearing in this Court, detailed schedules were prepared by the solicitors for Kyren showing various scenarios and calculating the amounts owing depending on the findings of this Court. These were based on estimates from a quantity surveyor. We consider that the parties should now easily be able to come to a final figure. We require the parties to meet and discuss those schedules and to attempt to agree the appropriate figure. Too much time and money has been spent on this litigation. It is time it was finalised. We will allow the parties 21 days to finalise a judgment figure based on our findings.

Ratio Decidendi

Legal Principle Established

Full text does not contain this section.