District Court
New South Wales
- Amendment notes
Medium Neutral Citation: Kore v Intelligent Building Pty Ltd [2025] NSWDC 297 Hearing dates: 10 March 2025 – 12 March 2025, 21 May 2025 Date of orders: 08 August 2025 Decision date: 08 August 2025 Jurisdiction: Civil Before: Weber SC DCJ Decision: See [90] below
Catchwords: BUILDING AND CONSTRUCTION – Breach of residential building contract – Delay – Where building was to be completed within a specified time period – Defective works – Where both parties claim to have validly terminated building contract – Whether monies awarded under an Adjudicator’s Determination and registered as a judgment debt can be recovered pursuant to s 32 of the Building and Construction Industry Security of Payment Act 1999 (NSW) – Consequential loss incurred from renting alternative accommodation – Correct measure of damages for breach of building contract – Whether sole director of building company is necessarily liable under the Design and Building Practitioners Act 2020 (NSW)
Legislation Cited: Building and Construction Industry Security of Payment Act 1999 (NSW) s 32
Civil Procedure Act 2005 (NSW) s 100
Design and Building Practitioners Act 2020 (NSW) ss 36, 37
Home Building Act 1989 (NSW) ss 92, 94, 96
Cases Cited: Barber v Oracle (NSW) Pty Ltd [2019] NSWSC 1370
Ceerose Pty Ltd v Building Products Australia Pty Ltd [2015] NSWSC 1886
Mangano v Amescorp Pty Ltd [2024] NSWDC 195
Sargent v ASL Developments Ltd (1974) 131 CLR 634
The Owners – Strata Plan No 84674 v Pafburn Pty Ltd [2022] NSWSC 659
Category: Principal judgment Parties: Nishant Kore (First Plaintiff)
Divya Kore (Second Plaintiff)
Intelligent Building Pty Ltd (First Defendant)
Andrew Hanna (Second Defendant)
John Hanna (Third Defendant)
Eman Shonoda (Fourth Defendant)Representation: Solicitors:
In Person:
Adelstein Solicitors (Plaintiffs)
J Hanna (First and Third Defendants)
A Hanna (Second Defendant)
E Shonoda (Fourth Defendant)
File Number(s): 2023/00321282 Publication restriction: None
Judgment
Introduction
-
These proceedings concern a dispute arising out of a home building contract. The subject of the contract was a two-storey home at Schofields (the ‘Contract’).
-
The Contract was in a standard form NSW Residential Building Contract for New Dwellings as published by the Housing Industry Association ('HIA'). It contained no special conditions, and as such it prescribed a 26-week period for completion (subject to valid extensions of time).
-
The parties to the Contract were the plaintiffs, who are husband and wife, and the first defendant (‘IB’). Also joined in the proceedings were the second, third and fourth defendants. The third defendant (‘JH’) is an experienced engineer who, on any view of it, was supervising the construction work undertaken pursuant to the Contract by IB. The fourth defendant (‘ES’) is the wife of JH and is the sole director of IB. She played no part in the actual construction work, including any supervision thereof. The second defendant (‘AH’) is the son of JH and ES. He was a 20% shareholder in IB but held no executive or other…
Continue reading Kore v Intelligent Building Pty Ltd
Sign in free to access the full text
- AGLC
- Kore v Intelligent Building Pty Ltd [2025] NSWDC 297
- Case
- [2025] NSWDC 297
- Decision Date
CaseChat Overview and Summary
The court first considered the nature of the delay and the defective works. It found that Intelligent Building had indeed delayed the completion and failed to meet the contractual standards. Regarding the termination of the contract, the court held that Intelligent Building had not validly terminated the contract, as required by the terms of the agreement. The court then addressed the issue of recovering monies awarded under the Security of Payment Act. It determined that such monies could be recovered, as they were not subject to the statutory payment provisions. The court also found that the correct measure of damages for the breach included the cost of renting alternative accommodation due to the delay. Finally, the court concluded that the sole director of Intelligent Building was not necessarily liable under the Design and Building Practitioners Act 2020 (NSW), as the statutory provisions did not automatically impose liability on individual directors.
The court ordered that Kore recover the monies awarded in the Adjudicator’s Determination and registered as a judgment debt. It also awarded Kore damages for the cost of alternative accommodation. The court further held that the sole director of Intelligent Building was not liable under the Design and Building Practitioners Act 2020 (NSW). These orders aimed to provide Kore with appropriate compensation for the breach of contract and the associated costs incurred.
Orders
Orders of the court
See [90] below
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.