Kell & Rigby Holdings Pty Ltd v Lindsay Bennelong Developments Pty Ltd

Link copied
Case Copied 32 min read
CITATION: Kell & Rigby Holdings Pty Limited v Lindsay Bennelong Developments Pty Ltd [2010] NSWSC 777
HEARING DATE(S): 7 July 2010
 
JUDGMENT DATE : 

16 July 2010
JUDGMENT OF: Hammerschlag J
DECISION: Plaintiff entitled to a declaration that in the circumstances that have occurred to this point, the defendant is not entitled to call on the Guarantees. It is also entitled to an injunction, in appropriate terms, in aid of the declaration.
CATCHWORDS: CONTRACT – building contracts – construction – the defendant Principal and the plaintiff Contractor entered into a construction contract (“the Contract”) – later they entered into an Advance Payment Deed which amended the Contract and which inserted provisions for the making of Advance Payments to the Contractor and for the provision by the Contractor of Advance Payment Bonds to secure repayment – the Principal advanced or made Advance Payments and the Contractor provided two Advance Payment Bonds each in the form of an unconditional Bank Guarantee (“the Guarantees”) – the Advance Payments became repayable on provision of a Certificate of Practical Completion – the Principal was in addition the Superintendent under the Contract – it purported to vary the Contract by deletion of work and then issue a Certificate of Practical Completion and then sought to call on the Guarantees – the Contractor asserted that the variation was beyond power and the Certificate of Practical Completion was invalid – alternatively it asserted that the Certificate of Practical Completion was issued in breach of an obligation of the defendant to act fairly – the Contractor asserted that a call by the Principal on the Guarantees would be in breach of an implied negative stipulation in the Contract that it would not do so if the Advance Payment was not repayable – HELD – held that the Notice of Variation to Works was unauthorised and the Certificate of Practical Completion was ineffective – held further that the Superintendent did not act fairly in giving the Notice of Variation to Works and issuing the Certificate of Practical Completion – held further that the Principal breached its express contractual obligations – held further that a call on the Guarantees would be in breach of an implied negative stipulation as contended for
LEGISLATION CITED: Trade Practices Act 1974 (Cth)
CATEGORY: Principal judgment
CASES CITED: Clough Engineering Ltd v Oil & Natural Gas Corporation Ltd [2008] FCAFC 136
Reed Constructions Services Pty Ltd v Kheng Seng (Australia) Pty Ltd (1998) 15 BCL 158
Toll (FGCT) Pty Ltd v Alphapharm Pty Ltd (2004) 219 CLR 165
International Air Transport Association v Ansett Australia Holdings Ltd (Subject to Deed of Company Arrangement) and others (2008) 242 ALR 47
McCann v Switzerland Insurance Australia Ltd (2000) 203 CLR 579
Codelfa Construction Pty Ltd v State Rail Authority (NSW) (1982) 149 CLR 337
Franklins Pty Ltd v Metcash Trading Ltd [2009] NSWCA 407
Wilkie v Gordian Runoff Ltd (2005) 221 CLR 522
Maggbury Pty Ltd v Hafele Aust Pty Ltd (2001) 210 CLR 181
Perini Corporation v…
CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Kell & Rigby Holdings Pty Ltd v Lindsay Bennelong Developmen... and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2010] NSWSC 777
Decision Date

CaseChat Overview and Summary

In the case of Kell & Rigby Holdings Pty Ltd v Lindsay Bennelong Developments Pty Ltd, the dispute arose between a principal and a contractor under a construction contract. The parties entered into a contract for construction works and later amended it through an Advance Payment Deed. The principal, as the Superintendent under the contract, advanced payments to the contractor and received unconditional bank guarantees as security for repayment. The contractor argued that the principal's variation of the contract, subsequent issuance of a Certificate of Practical Completion, and attempt to call on the guarantees were invalid. The contractor contended that the variation exceeded the principal's authority, the certificate was issued unfairly, and calling on the guarantees would breach an implied term against doing so if the advance payment was not repayable.

The court had to determine whether the principal's variation was authorised and whether the certificate of practical completion was valid. It also needed to consider whether the principal acted fairly and whether calling on the guarantees would breach an implied negative stipulation. The court examined the contractual provisions and the conduct of the parties to resolve these issues. It held that the principal's Notice of Variation to Works was unauthorised and the Certificate of Practical Completion was ineffective. The court further found that the Superintendent did not act fairly in issuing the certificate and that the principal breached its express contractual obligations. It concluded that a call on the guarantees would breach an implied negative stipulation.

The court ruled in favour of the contractor, finding that the principal's variation was unauthorised, the certificate was invalid, and the principal had acted unfairly. The court also held that a call on the guarantees would breach an implied negative stipulation. As a result, the principal was not entitled to call on the guarantees and the contractor's arguments were upheld. The court's decision provides clarity on the rights and obligations of principals and contractors under construction contracts, particularly concerning variations, certificates of practical completion, and the use of guarantees.

Orders

Orders of the court

Full text does not contain this section.

Background

Background to the litigation

Full text does not contain this section.

Evidence

Evidence Before The Court

Full text does not contain this section.

Decision

Reasons for decision

Full text does not contain this section.

Ratio Decidendi

Legal Principle Established

Full text does not contain this section.