CITATION: | Jespersen v Queensland Building and Construction Commission [2017] QCAT 459 |
PARTIES: | Jan Jespersen |
| v | |
| Queensland Building and Construction Commission (Respondent) | |
APPLICATION NUMBER: | GAR284-16 |
HEARD AT: | Brisbane |
DECISION OF: | Member Howe |
DELIVERED ON: | 19 December 2017 |
DELIVERED AT: | Brisbane |
ORDERS MADE: | 1. The decision of the Queensland Building and Construction Commission not to issue a direction to rectify defective building work to the contractor is confirmed. 2. The application is dismissed. |
CATCHWORDS: | PROFESSIONS AND TRADES – BUILDERS – STATUTORY POWER TO REQUIRE RECTIFICATION OF DEFECTIVE OR INCOMPLETE BUILDING WORK – where owner claims defective building work – where Queensland Building and Construction Commission makes decision not to issue direction to rectify to contractor – guidelines under AS3727 – where finding of structural and non-structural defective building work – whether claim by owner to replace entire works unreasonable Queensland Building and Construction Commission Act 1991 (Qld), s 72(5) |
APPEARANCES: | |
APPLICANT: | Self-represented |
RESPONDENT: | Ms E Ward, Inhouse Counsel |
REASONS FOR DECISION
Mr Jespersen lives in Shailer Park in the Logan City Council catchment area. In October 2015, he engaged Mr Kennedy, a concreter, to lay a concrete driveway.
Mr Kennedy did the work on 14 December 2015 and Mr Jespersen paid him for the job. Over the period from 30 January 2016 to 15 February 2016, Mr Jespersen wrote to the contractor complaining about cracks in the concrete. Mr Kennedy attempted to rectify some of the problems but not to Mr Jespersen’s satisfaction.
On 20 February 2016, Mr Jespersen complained to the Queensland Building and Construction Commission (the Commission). There were initially four matters of complaint, which increased to nine on
23 February 2016. The complaints generally concerned cracks in the concrete, spalling, concrete thickness, general finish and a poorly formed post construction control joint.
On 14 March 2016, Mr Nicolson, a building inspector in the employ of the Commission, carried out a site inspection. Though he observed that there were cracks between 1mm and 2mm wide, there was some spalling and the depth of the concrete was in places less then the requisite 100mm, he determined it was not reasonable that a direction to rectify defective building work be issued to the contractor.
On 23 May 2016, Mr Jespersen sought internal review of that decision.
On 15 September 2016, Mr Matthews, another building inspector in the employ of the Commission, carried out another inspection of the property for the purpose of the internal review. Both Mr Jespersen and Mr Kennedy were in attendance.
Mr Matthews found one crack at the bottom right corner of the driveway near the kerb measured between 1.25mm and 2mm. He noted under Australian Standard AS3727 Guide to Residential Pavements that was outside the permitted tolerance of 1.5mm. He also found the slab, in the area of the crack, was under the recommended thickness of 100mm for light traffic in AS3727. He also found there was…
Keep reading for free
Create a free CaseChat account to read Jespersen v Queensland Building and Construction Commission and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2017] QCAT 459
- Decision Date
CaseChat Overview and Summary
The central legal issues before the court were whether the Queensland Building and Construction Commission was correct in its decision not to issue a direction to the contractor for rectifying the defective building work and whether the owner's claim to replace the entire works was unreasonable. The court had to consider the extent of the defects, the reasonableness of the owner's claim, and the guidelines provided under AS3727 in making its decision.
The court held that the Queensland Building and Construction Commission's decision not to issue a direction to the contractor was well-founded. The court found that while there were defects in the building work, they were not of such a nature or extent that warranted a complete replacement of the works. The owner's claim was considered unreasonable given the findings of the Commission. The court concluded that the Commission had exercised its discretion appropriately in line with the statutory guidelines and that the decision not to issue a direction to rectify the defects was justified.
The court's final orders confirmed the decision of the Queensland Building and Construction Commission and dismissed the application brought by the owner. This outcome underscores the importance of adhering to statutory guidelines and exercising reasonable discretion when addressing claims of defective building work.
Orders
Orders of the court
1. The decision of the Queensland Building and Construction Commission not to issue a direction to rectify defective building work to the contractor is confirmed.
2. The application is dismissed.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.