| CITATION: | Burnett & Heath v Fergbilt Pty Ltd [2015] QCAT 328 |
| PARTIES: | Greg Burnett Jacqueline Heath (Applicant) |
| v | |
| Fergbilt Pty Ltd (Respondent) |
| APPLICATION NUMBER: | BDL275-14 |
| MATTER TYPE: | Building matters |
| HEARING DATE: | 27 July 2015 |
| HEARD AT: | Brisbane |
| DECISION OF: | Member Lumb |
| DELIVERED ON: | 21 August 2015 |
| DELIVERED AT: | Brisbane |
| ORDERS MADE: | 1. The Respondent is ordered to rectify, within 28 days of the date of these orders the following defective or incomplete work at the Applicants’ home at Alderley, Brisbane: a. all ‘Alabaster’ coloured areas of the painted exterior trim and features (including stairs and windows); b. the cracking along the cornices on the ground floor level and the paint surface discoloration of putty finishing on those cornices; c. the ceiling mounted light and IXL heater in the main upstairs bathroom. 2. The Respondent shall pay damages to the Applicants in the sum of $16,079.00 in respect of the defective concrete work in the driveway, forecourt and pedestrian pavement areas of the Applicants’ home at Alderley, Brisbane, with such sum to be paid within 28 days of the date of these orders. 3. The Applicants are awarded costs of the proceeding in the sum of $7,181.33, with such sum to be paid by the Respondent within 28 days of the date of these orders. |
| CATCHWORDS: | BUILDING DISPUTE – TRIBUNAL WORK – domestic building work – alleged defective or incomplete tribunal work – rectification – damages – expert evidence Domestic Building Contracts Act 2000 (Qld), s 8, s 41, s 44 Belgrove v Eldridge (1954) 90 CLR 613 |
APPEARANCES:
| APPLICANT: | Greg Burnett resprented himself and Jacqueline Heath |
| RESPONDENT: | Craig Ferguson, director, represented Fergbilt Pty Ltd |
REASONS FOR DECISION
By an application for domestic building disputes filed on 6 November 2014 (‘the Application’), the Applicants sought rectification or completion of alleged defective work (and costs) in relation to renovation work performed by the Respondent at the residential home owned by the Applicants situated at Alderley in Brisbane in the State of Queensland (‘the Property’).
The details of the alleged defective work were set out in the schedule to the Application. There were four items of work described as follows:
a) defective external concrete work at the front and side of the Property which has excessive cracking across 22 separate locations and, in several locations, concrete is breaking up with looser pieces of concrete coming away;
b) defective external painting work because the Respondent’s painter used the incorrect paint colour on windows, front stairs and features of the street facing front of the Property and the colour does not match the paint colour of the remainder of the trims and features across the Property;
c) defective cracking has occurred between the cornice and ceiling in several sections of the new ground floor…
Keep reading for free
Create a free CaseChat account to read Burnett & Heath v Fergbilt Pty Ltd and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2015] QCAT 328
- Decision Date
CaseChat Overview and Summary
The central legal issues in the case were whether the respondent had breached the terms of the contract by carrying out defective or incomplete work, and if so, what remedies were available to the applicants. The court had to consider expert evidence provided by both parties regarding the quality of the work and the extent of any defects. The court also needed to determine the appropriate damages for the defective concrete work and whether the applicants were entitled to costs.
The tribunal found that the respondent had indeed breached the contract by carrying out defective or incomplete work on the applicants' property. The tribunal accepted the expert evidence presented by the applicants and rejected the respondent's arguments. The tribunal ordered the respondent to rectify the defective or incomplete work within 28 days of the date of the orders. The tribunal also awarded damages to the applicants in the sum of $16,079.00 for the defective concrete work, as well as costs of the proceeding in the sum of $7,181.33, to be paid by the respondent within 28 days of the date of the orders.
Orders
Orders of the court
1. The Respondent is ordered to rectify, within 28 days of the date of these orders the following defective or incomplete work at the Applicants’ home at Alderley, Brisbane:
a. all ‘Alabaster’ coloured areas of the painted exterior trim and features (including stairs and windows);
b. the cracking along the cornices on the ground floor level and the paint surface discoloration of putty finishing on those cornices;
c. the ceiling mounted light and IXL heater in the main upstairs bathroom.
2. The Respondent shall pay damages to the Applicants in the sum of $16,079.00 in respect of the defective concrete work in the driveway, forecourt and pedestrian pavement areas of the Applicants’ home at Alderley, Brisbane, with such sum to be paid within 28 days of the date of these orders.
3. The Applicants are awarded costs of the proceeding in the sum of $7,181.33, with such sum to be paid by the Respondent within 28 days of the date of these orders.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.