In the Matter of Torrens Constructions Pty Ltd (No 3)

Link copied
Case Copied 10 min read

SUPREME COURT OF SOUTH AUSTRALIA

(Civil: Application)

IN THE MATTER OF TORRENS CONSTRUCTIONS PTY LTD (No 3)

[2025] SASC 53

Reasons for Decision of the Honourable Justice Kimber  

PROCEDURE - CIVIL PROCEEDINGS IN STATE AND TERRITORY COURTS - SECURITY FOR COSTS - PROCEDURE

PROCEDURE - CIVIL PROCEEDINGS IN STATE AND TERRITORY COURTS - SECURITY FOR COSTS - PROCEDURE - MORE THAN ONE ORDER

PROCEDURE - CIVIL PROCEEDINGS IN STATE AND TERRITORY COURTS - SECURITY FOR COSTS

This is an application by the first, second, and third respondents (the respondents) for a further order for security for costs in the trial of this matter.  The application is made in the context of the trial having not concluded in the 12 days the subject of the existing security for costs order.  It is not disputed that a further three days is required to complete the trial.

The respondents are seeking that the applicant pay further security for costs equivalent to six days at the daily rate of $7,300.  The respondents submit that this is the appropriate order given the preparation of written submissions prior to closing addresses.  The applicant opposes this application, submitting that no order should be made.  The applicant submits that time was ‘lost’ during the trial due to the conduct of the respondents.  In particular, that time was ‘lost’ due to its application to amend the pleadings during the trial as a result of the late disclosure of documents by the respondents and the manner of cross-examination of the only civilian witness of substance called by the applicant.

Held, granting the application for a further order for security of costs:

1.The applicant is to pay security for costs for an additional three days in the amount of $21,900; and

2.      The above amount is to be paid by 20 June 2025.

Uniform Civil Rules 2020 (SA) r 115.1(1), referred to.

Camping Warehouse Australia Pty Ltd v Downer EDI Ltd [2016] VSC 29; Anchung Pty Ltd v Northern Territory of Australia (No 2) [2016] NTSC 34, applied.

Re Torrens Constructions Pty Ltd [2024] SASC 136; Re Torrens Constructions Pty Ltd [2023] SASC 25, discussed.

IN THE MATTER OF TORRENS CONSTRUCTIONS PTY LTD (No 3)
[2025] SASC 53

Civil: Application

KIMBER J:

  1. This is an application by the first, second, and third respondents (the respondents) for a further order for security for costs in the trial of this matter. 

  2. Two previous orders have been made in favour of the respondents.  The first order was made by Judge Bochner, as her Honour then was, in the amount of $56,000 for costs up to, and including, the first day of the trial.[1]  The second order was made by me, as the trial Judge, in the amount of $85,580 for a period of 11 days from the second day of the trial.[2] 

    [1]    Re Torrens Constructions Pty Ltd (Supreme Court of South Australia, Judge Bochner, 24 February 2023).

    [2]    Re Torrens Constructions Pty Ltd [2024] SASC…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read In the Matter of Torrens Constructions Pty Ltd (No 3) and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2025] SASC 53
Decision Date

CaseChat Overview and Summary

Torrens Constructions Pty Ltd (No 3) involved a dispute between the applicant and the respondents regarding the provision of security for costs in civil proceedings. The matter was heard in the South Australian Supreme Court. The primary issue before the court was whether the applicant, Torrens Constructions Pty Ltd, should be ordered to provide additional security for costs due to the trial's extended duration.

The respondents argued that, given the trial's longer-than-expected duration, an order for security for costs was warranted. They contended that the applicant was a trustee company without property in its own right, divested of its only substantial asset in September 2022, and had no one standing behind it to offer security. Furthermore, the respondents submitted that there was no suggestion that an order for security would stultify the action and that there was unchallenged evidence that the applicant was unlikely to meet any costs order made against it. They proposed an order for six days of security for costs, considering the preparation of written submissions between 24 June 2025 and 22 July 2025. The applicant, however, opposed any order for additional security for costs, arguing that time was 'lost' during the trial due to arguments about amendments to the statement of claim and lengthy cross-examination of a key witness. The applicant contended that, if not for these issues, the trial would have been completed within the 12 days covered by existing security for costs orders.

The court considered Rule 115.1(1) of the Uniform Civil Rules 2020 (SA), which allows the court to order security for costs under certain circumstances, including when the applicant is bringing the claim for someone else's benefit. The court concluded that the submissions made by the respondents, which remained unchallenged, weighed in favor of granting the application. Although the court was not satisfied that any time was appropriate for the preparation of closing submissions, it found that the three days set aside to complete the trial were material, given the trial's extended duration. Consequently, the court ordered the applicant to pay further security for costs for three days in the amount of $21,900. The court also ordered that this amount be paid by 20 June 2025 and invited the parties to discuss any further orders that might be necessary.

Orders

Orders of the court

Background

Background to the litigation

For the reasons that follow, I order that the applicant pay, by the close of business on 20 June 2025, security for costs for three days in the amount of $21,900. Background The background in the proceedings, at least before the trial commenced, is set out in Re Torrens Constructions Pty Ltd [2024] SASC 136. I will not repeat that summary. An overview of the submissions of the parties The respondents submit that, due to the trial having occupied longer than anticipated, the order sought is appropriate. The respondents submit that there is no challenge to the following submissions made before Judge Bochner as her Honour then was, namely that:[3] ·The applicant is a trustee company and so is bringing this action for the benefit of another;·As a trustee company, the applicant owns no property in its own right, and in fact, divested itself of its only substantial asset in September 2022;·No one standing behind the applicant has come forward to offer security;·There has been no suggestion that an order for security would stultify this action;·There is unchallenged evidence that the applicant is unlikely to be able to meet any costs order made against it.[3] Re Torrens Constructions Pty Ltd [2023] SASC 25, [18]. The respondents submit that, given the above, if the order sought is not made, there is a substantial risk that the applicant may have no ability to meet an adverse costs order. Although only three more sitting days should be needed to complete the trial, the respondents submit that an order for six days is appropriate given the preparation of written submissions between 24 June 2025 and 22 July 2025. The applicant opposes any order being made. The applicant submits that I should find the following: ·that time was ‘lost’ during the first 12 days of the trial; ·that the fault for that ‘lost’ time lies with the respondents; and·had that time not been ‘lost’, the trial would have been completed within the 12 days the subject of existing orders for security for costs. Broadly, the applicant submits that, during the trial to date, approximately a day or so was ‘lost’ due to arguments about amendments to the statement of claim which were ultimately granted. The applicant further submits that the cross‑examination of the only substantial civilian witness called by the applicant was unduly lengthy. Taking what might be described as a ‘broad brush’ approach, the applicant submits that if those things had not occurred, the trial would have been completed within 12 days. In the alternative, the applicant submits that even if the above submissions are rejected, the amount of any further order should be significantly less than that sought. The applicant submits that is, on its own, a reason to decline to make any order. The rules and some principles Rule 115.1(1) of the Uniform Civil Rules 2020 (SA) provides: [4] [4] Uniform Civil Rules 2020 (SA) r 115.1(1).115.1—Security for costs(1)The Court may order that an applicant in an action provide security for costs if—(a) the applicant is bringing the claim or application for someone else’s benefit;(b) the applicant is ordinarily resident outside Australia;(c) there are reasonable grounds to suspect that the action has been brought for an ulterior purpose; (d) the order is authorised by statute; or(e) the order is necessary in the interests of justice.

Evidence

Evidence Before The Court

Decision

Reasons for decision

I turn to the application of the respondents for further security of costs to be ordered for the three days to prepare closing submissions. I am not satisfied that any time is appropriate for that preparation. Had the trial been able to continue uninterrupted, that is work which would have been necessary within the earlier order made with respect to security for costs from the second day of the trial. Conclusion As earlier outlined, in this application, the submissions set out at [7] above remain unchallenged. Those matters weigh in favour of the application being granted. In my view, they are matters of substantial weight to whether an order should be made. Having concluded that the period of three days for preparation of closing submissions should not be the subject of any order, what remains is the three days set aside to complete the trial. That is a relatively short period but, in the context of a trial that has taken 12 days to date, it is a period which is material. There is no dispute that the appropriate amount per day is $7,300. In the circumstances, I find that the applicant should pay further security for costs for three days in the amount of $21,900. Orders 1.The applicant pay security for costs for an additional three days in the amount of $21,900. 2.The above amount is to be paid by 20 June 2025.3.I will hear the parties as to any further orders which may be necessary.

Ratio Decidendi

Legal Principle Established