Imperial Homes (Qld) Pty Ltd v Boys

Link copied
Case Copied 83 min read

QUEENSLAND CIVIL AND
ADMINISTRATIVE TRIBUNAL


CITATION:

Imperial Homes (Qld) Pty Ltd v Boys [2020] QCAT 299

PARTIES: IMPERIAL HOMES (QLD) PTY LTD

(applicant)

v

DANIEL JAY BOYS

(respondent)

APPLICATION NO/S:

BDL252-18

MATTER TYPE:

Building matters

DELIVERED ON:

5 August 2020

HEARING DATES:

10 October 2019
11 October 2019

HEARD AT:

Brisbane

DECISION OF:

Member Poteri

ORDERS:

1.   The Respondent pay the Applicant the sum of $24,260.25 within 30 days of the date of this order;

2.   The Respondent pay default interest on any monies owing to the Applicant under Order (1) at the default interest rate of 18% per annum calculated from 11 August 2018;

3.   The Applicant must deliver all keys, remote control devices, all certificates and warranty/operational documents relating to the House to the Respondent within 30 days of the date of this order;

4. The parties are at liberty to make submissions to the Tribunal in respect of any application for the award of costs pursuant to s 77 of the Queensland Building and Construction Commission Act 1991 (Qld) or clause 34 of the Building Contract within 21 days of the date of this order. Such submissions should also comment on the orders of Senior Member Brown made on 8 August 2019 and Member Oliver made on 11 September 2019.

CATCHWORDS:

CONTRACTS – BUILDING CONTRACT – PERFORMANCE OF WORK – TIME – NOTICES TO REMEDY SUBSTANTIAL BREACH, PRACTICAL COMPLETION AND TERMINATION – CLAIMS FOR DAMAGES AND DEFAULT INTEREST – where the parties entered into a home building contract – where the builder claimed practical completion – where the owner rejected the builder’s claim – where the owner issued a notice to remedy substantial breach which was rejected by the builder – where the owner issued a notice of termination of the building contract and entered into possession of the home – where the owner has claimed that the builder is in substantial breach of the building contract - where the owner has claimed damages and solatium – where the builder has accepted the owner’s repudiation of the building contract – where the builder has claimed default interest

Bellgrove v Eldridge (1954) 90 CLR 613
Williams v Stone Homes P/L and Anor [2014] QDC 64
Avilake Pty Ltd v Tucker and Anor [2012] QCATA 211
Prosser v Kimama Holdings Pty Ltd T/A Visual Diversity Homes [2015] QCAT 77
Miller & Anor v Lida Build Pty Ltd [2013] QCA 332
Thompson Residential Pty Ltd v Hart & Anor [2014] QDC 132
Queensland Civil and Administrative Tribunal Act 2009 (Qld), s 28
Queensland Building and Construction Commission Act 1991 (Qld), s 77; Schedule 1B s 40, s 41, s 42, s 43, s 44
Acts Interpretation Act 1954 (Qld), s 38

Corporations Act 2001 (Cth), s 109X

APPEARANCES & REPRESENTATION:

Applicant:

L Watt of Becker Watt Lawyers

Respondent:

D B Ferraro of Counsel instructed by Taylor David, Lawyers

REASONS FOR DECISION

Background

  1. For the purposes of drafting the decision I will refer to the Applicant, Imperial Homes Pty Ltd, as…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Imperial Homes (Qld) Pty Ltd v Boys and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details

Case
[2020] QCAT 299
Decision Date

CaseChat Overview and Summary

Imperial Homes (Qld) Pty Ltd sought relief against Boys, who had been contracted to construct a home, following disagreements over the completion and quality of the work. The dispute reached the Queensland Civil and Administrative Tribunal, where the primary concern was whether Boys had fulfilled his contractual obligations, particularly regarding practical completion and subsequent termination of the contract. The Tribunal had to determine if Imperial Homes was justified in rejecting Boys' claim of practical completion and issuing a notice to remedy substantial breach.

The legal issues revolved around the interpretation of the building contract, the builder's entitlement to claim practical completion, and the owner's right to reject this claim and terminate the contract. The Tribunal also needed to consider whether the builder's actions constituted a substantial breach and if the owner was entitled to damages, solatium, and default interest. Additionally, the Tribunal had to address the validity of the termination and the builder's acceptance of the owner's repudiation.

The Tribunal found that Boys had not achieved practical completion as per the contract, leading to Imperial Homes' justified rejection and subsequent termination. The Tribunal held that Boys' actions constituted a substantial breach, warranting damages and solatium. Regarding the builder's claim for default interest, the Tribunal ruled that such interest was payable under the contract terms. The Tribunal ordered Boys to pay the specified sum within 30 days, along with default interest calculated from a particular date. It also mandated the delivery of all property keys and documents to Imperial Homes and allowed submissions on costs within a set timeframe.

The final orders required Boys to pay Imperial Homes $24,260.25 with default interest, deliver all property-related items, and consider further submissions on costs. The Tribunal's decision confirmed Imperial Homes' claims and addressed the builder's counterclaims, providing a clear resolution to the contractual disputes.

Orders

Orders of the court

1. The Respondent pay the Applicant the sum of $24,260.25 within 30 days of the date of this order;

2. The Respondent pay default interest on any monies owing to the Applicant under Order (1) at the default interest rate of 18% per annum calculated from 11 August 2018;

3. The Applicant must deliver all keys, remote control devices, all certificates and warranty/operational documents relating to the House to the Respondent within 30 days of the date of this order;

4. The parties are at liberty to make submissions to the Tribunal in respect of any application for the award of costs pursuant to s 77 of the Queensland Building and Construction Commission Act 1991 (Qld) or clause 34 of the Building Contract within 21 days of the date of this order. Such submissions should also comment on the orders of Senior Member Brown made on 8 August 2019 and Member Oliver made on 11 September 2019.

Background

Background to the litigation

Decision

Reasons for decision

Ratio Decidendi

Legal principle established