| CITATION: | Prosser v Kimama Holdings Pty Ltd T/A Visual Diversity Homes [2015] QCAT 77 |
| PARTIES: | Michelle Prosser (Applicant) |
| v | |
| Kimama Holdings Pty Ltd T/A Visual Diversity Homes (Respondent) |
| APPLICATION NUMBER: | BDL052-14 |
| MATTER TYPE: | Building matters |
| HEARING DATE: | 13 October 2014 and 4 February 2015 |
| HEARD AT: | Brisbane |
| DECISION OF: | Member Howe |
| DELIVERED ON: | 12 March 2015 |
| DELIVERED AT: | Brisbane |
| ORDERS MADE: | The respondent pay to the applicant the sum of $11,995.15 within 30 days of the date of order. | |
| CATCHWORDS: | BUILDING MATTERS - regulated contract – variation – failure to make variation in writing – repudiation of contract – breach of contract – termination of contract by commencement of proceedings - determination of ambiguities between specifications and drawings - practical completion - certification – unsigned Form 21 – defects – assessment of damages – calculation of cost of rental premises as basis of assessment – owner excluded from occupation in breach of contract Allaro Homes Cairns Pty Ltd v O’Reilly & Anor [2012] QCA 286 | |
APPEARANCES and REPRESENTATION (if any):
| APPLICANT: | Michelle Prosser represented herself |
| RESPONDENT: | Anthony Smith and Daniel Smith for the respondent company |
REASONS FOR DECISION
BACKGROUND
On 11 May 2013 the parties signed a building contract. The price stated was $199,800. The contract changed the usual stages for progress payments on the basis there was extensive site works necessary before the slab stage and retaining walls.
The parties enjoyed a good relationship prior to contract and during most of the construction, but had fallen out by the time the builder claimed practical completion stage had been achieved on 19 February 2014. The owner, Ms Prosser, disputed that that stage had been reached. She refused to pay the final payment. The builder refused to let her into the home.
She commenced these proceedings in the Tribunal. She claimed a number of things including damages for breach of contract. At initial hearing the builder’s counterclaim was for the payment due at practical completion, $19,980, plus $10,000 for a variation to the contract. Ms Prosser was still excluded from the property as at the first day of hearing and the Tribunal ordered the final payment of $19,980 be made to the builder and the builder supply and install all appliances and hand over possession to her by 18 October 2014. The parties complied. That meant the claim of the builder was reduced to claiming for the $10,000 variation.
Ms Prosser disputed the $10,000 variation. She disputed practical completion had been achieved by the builder on 19 February 2014. She claimed for the cost of air-conditioning she said was due under the contract and not supplied. She also had complaints about the retaining walls. Finally, she claimed for defective building work.
The Contract Price
Throughout April 2013 the parties negotiated the price of the build. Attachment 1 to Ms Prosser’s statement of evidence[1] is a series of emails between the parties. On 16 April 2013 she told the builder…
Keep reading for free
Create a free CaseChat account to read Prosser v Kimama Holdings Pty Ltd T/A Visual Diversity Homes and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
Find similar cases
Other decisions on the same topics. Each opens in a new tab.
Details
- Case
- [2015] QCAT 77
- Decision Date
CaseChat Overview and Summary
The court examined the evidence and found that the builder had repudiated the contract by failing to make the variation in writing, which was a requirement under the contract. The court also found that the owner was entitled to terminate the contract and claim damages due to the builder's breach of contract. The court considered the cost of rental premises as an appropriate basis for assessing damages, as the owner was excluded from occupation of the property in breach of contract. The court determined that the builder was liable for the cost of the rental premises for the period of exclusion, which was calculated to be $11,995.15.
In summary, the court held that the builder had repudiated the contract and that the owner was entitled to terminate the contract and claim damages. The court ordered the builder to pay the owner the sum of $11,995.15 within 30 days of the date of the order. The court also determined that the calculation of damages based on the cost of rental premises was appropriate, given the circumstances of the case.
Orders
Orders of the court
The respondent pay to the applicant the sum of $11,995.15 within 30 days of the date of order.
Background
Background to the litigation
Decision
Reasons for decision
Ratio Decidendi