| IN THE SUPREME COURT OF VICTORIA | Not Restricted |
AT MELBOURNE
COMMON LAW DIVISION
JUDICIAL REVIEW AND APPEALS LIST
S ECI 2024 06511
BETWEEN:
| NESET ICBUDAK and HULYA ICBUDAK | Applicants |
| v | |
| ALSA CONSTRUCTIONS & ORS (according to the attached Schedule) | Respondents |
---
JUDGE: | Ierodiaconou AsJ |
WHERE HELD: | Melbourne |
DATE OF HEARING: | 1 May 2025 |
DATE OF RULING: | 27 June 2025 |
CASE MAY BE CITED AS: | Icbudak v Alsa Constructions |
MEDIUM NEUTRAL CITATION: | [2025] VSC 377 |
---
APPEAL – Application for an extension of time to appeal cost orders made by the Victorian Civil and Administrative Tribunal – Icbudak v Symmetric Homes Pty Ltd (Building and Property) (Costs) [2024] VCAT 595 – Applicants sought costs of rectifying alleged defects to their house – Icbudak v Symmetric Homes Pty Ltd (Building and Property) [2021] VCAT 1074 – Huang v Frankston City Council [2024] VSCA 38 – Explanation for delay – Whether any prejudice has been caused by the delay – Merits of the proposed appeal – Discretionary nature of cost decisions – Francis v Wilson [2023] VSC 410 – Real prospect of success – Extension of time to appeal granted.
---
APPEARANCES: | Counsel | Solicitors |
| The Applicants in person | ||
| For the Respondents | Mr J Twigg KC with Mr L Hogan | Ward & Co. Legal Consultants |
TABLE OF CONTENTS
Material
Background
Applicable Principles
Extension of Time
Cost rulings are discretionary
Error of Law
Notice of Appeal
Analysis
Length of delay
Explanation for the delay
Applicants’ submissions
Respondents’ submissions
Analysis - explanation of delay
Whether delay has occasioned respondents to suffer prejudice
Merits of the proposed appeal
Applicants’ submissions
Respondents’ submissions
Analysis – merits of appeal
Conclusion
HER HONOUR:
Neset Icbudak and Hulya Icbudak filed a notice seeking to appeal cost orders made by the Victorian Civil and Administrative Tribunal (‘Tribunal’). Their notice of appeal was filed more than three months late. The applicants seek an extension of time. The respondents oppose the application.
Material
The applicants are self-represented. They rely on two affidavits of the first applicant, Mr Icbudak, respectively sworn on 12 December 2024 and 25 February 2025, and their outline of submissions filed on 27 March 2025.
The respondents rely on the affidavit of their solicitor, Marvin Lyle Ward, sworn on 6 March 2025, and their outline of submissions filed on 24 April 2025.
Background
The applicants issued a Tribunal proceeding seeking the costs of rectifying alleged defects to their house from the respondents (‘Tribunal proceeding’).
The respondents to the Tribunal proceeding were:
(a)the first respondent, Symmetric Homes Pty Ltd (‘Symmetric’), a building company – its director, Mr Yorenc, was also a registered builder;
(b)the second respondent, Alsa Constructions, a building company controlled by Mr Alinc;
(c)the third respondent, Mr Alinc, was a registered builder; and
(d)the fourth respondent, Mrs Alinc, Mr Yorenc’s sister.
The applicants alleged that the respondents had breached implied warranties. The applicants asserted their rights as subsequent owners per ss 8 and 9 of the Domestic Building Contracts Act 1995 (Vic).[1]
Continue reading Icbudak v Alsa Constructions
Sign in free to access the full text
- AGLC
- Icbudak v Alsa Constructions [2025] VSC 377
- Case
- [2025] VSC 377
- Decision Date
CaseChat Overview and Summary
The primary legal issues the court had to determine were whether there was a satisfactory explanation for the delay in lodging the appeal, whether any prejudice had been caused by the delay, and whether the proposed appeal had a real prospect of success. The court also considered the discretionary nature of cost decisions and the appropriate criteria to apply in granting an extension of time. The applicant's arguments were supported by references to previous cases such as Huang v Frankston City Council and Francis v Wilson, which provided guidance on the principles to be applied in such circumstances.
The court found that the applicant had provided a satisfactory explanation for the delay, and that no prejudice had been caused to the respondent as a result. The applicant's explanation was deemed reasonable, and the court accepted that the delay was not due to any fault or neglect on their part. In terms of the merits of the proposed appeal, the court was satisfied that there was a real prospect of success, based on the arguments presented and the applicable legal principles. The court emphasised the discretionary nature of cost decisions and noted that the matter was suitable for appeal. Accordingly, the court granted the application for an extension of time to appeal the costs orders.
The final orders of the court were that the applicant be granted an extension of time to appeal the costs orders made by VCAT, and that the applicant's application for an extension of time be otherwise dismissed without costs. This decision provides useful guidance for parties in similar situations, highlighting the importance of providing a satisfactory explanation for any delay in lodging an appeal and demonstrating that the proposed appeal has a real prospect of success.
Orders
Orders of the court
Full text does not contain this section.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.