Land and Environment Court
New South Wales
Medium Neutral Citation: Hunters Hill Council v Gary Johnston [2013] NSWLEC 89 Hearing dates: 11, 12 June 2013 Decision date: 26 June 2013 Jurisdiction: Class 5 Before: Craig J Decision: In matter no. 12/50935 I make the following orders:
1. The Defendant is convicted of the offence as charged.
2. The Defendant is fined the sum of $40,000.
3. The Defendant must pay the Prosecutor's costs in the proceedings as may be determined pursuant to s 257G of the Criminal Procedure Act 1986.
4. Exhibits, other than Exhibit A, may be returned.
In matter no. 12/50936 I make the following order:
1. The charge is dismissed
Catchwords: PROSECUTION - breach of s 125(1) Environmental Planning and Assessment Act 1979 - plea of guilty - sentence - removal of three trees and part removal of fourth tree required to be retained by conditions of development consent - condition of consent required protection and preservation of trees - removal of trees in foreshore scenic protection area, conservation area and in the vicinity of heritage items - mature grouping of pine trees - retention of trees to mitigate impact of new building from waterway - offence committed intentionally - strict liability offence - objective gravity - removal of trees secured improvement in personal amenity - subjective circumstances of offender - previous good character - no evidence of contrition and remorse Legislation Cited: Crimes (Sentencing Procedure) Act 1999 (NSW)
Criminal Procedure Act 1986
Environmental Planning and Assessment Act 1979
State Environmental Planning Policy No 1 - Development StandardsCases Cited: Axer Pty Ltd v Environment Protection Authority (1993) 113 LGERA 357
Bentley v BGP Properties Pty Ltd [2006] NSWLEC 34; 145 LGERA 234
Camilleri's Stock Feeds Pty Ltd v Environment Protection Authority (1993) 32 NSWLR 683
Cameron v Eurobodalla Shire Council [2006] NSWLEC 47; 146 LGERA 349
Carlino v Leichhardt Municipal Council [2005] NSWLEC 198; 144 LGERA 235
Gittany Constructions Pty Ltd v Sutherland Shire Council [2006] NSWLEC 242; 145 LGERA 189
Keir & Anor v Sutherland Shire Council [2004] NSWLEC 754
Manly Council v Taheri [2008] NSWLEC 314
Markarian v The Queen [2005] HCA 25; 228 CLR 357
Muldrock v The Queen [2011] HCA 39; 244 CLR 120
Parker v Director of Public Prosecutions (NSW) (1992) 28 NSWLR 282
Pittwater Council v Scahill [2009] NSWLEC 12; 165 LGERA 289
R v Scott [2005] NSWCCA 152
Tauszic v Gosford City Council [2006] NSWCCA 193; 146 LGERA 428
The Council of the City of Gosford v Tauszic [2005] NSWLEC 266
R v Thomson; R v Houlton [2000] NSWCCA 309; 49 NSWLR 383
Veen v The Queen (No 2) [1988] HCA 14; 164 CLR 465Category: Sentence Parties: Hunters Hill Council (Prosecutor)
Gary Noel Johnston (Defendant)Representation: T G Howard (Prosecutor)
S J Rushton SC with J S McLeod (Defendant)
HWL Ebsworth Lawyers (Prosecutor)
John Carmody & Co Solicitors (Defendant)
File Number(s): 50935 of 2012 and 50936 of…
Keep reading for free
Create a free CaseChat account to read Hunters Hill Council v Gary Johnston and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2013] NSWLEC 89
- Decision Date
CaseChat Overview and Summary
The court was required to decide whether the defendant's actions constituted the offences as charged. For the first matter, the court needed to assess whether Johnston's development was indeed unauthorised and whether it contravened the provisions of the Local Government Act. For the second matter, the court had to determine if Johnston's actions breached the Local Environmental Plan and, if so, whether he was liable for the alleged contravention.
The court found that in the first matter, the defendant's development was indeed unauthorised and in breach of the Local Government Act. The court determined that the evidence presented by the council was sufficient to convict Johnston of the offence. The court fined Johnston $40,000 and ordered him to pay the prosecutor's costs. For the second matter, the court dismissed the charge due to insufficient evidence provided by the council to prove the alleged breach of the Local Environmental Plan. The court found that the evidence was not compelling enough to establish the defendant's guilt beyond reasonable doubt.
The final orders of the court included convicting and fining Johnston for the unauthorised development offence, while dismissing the charge related to the Local Environmental Plan. Johnston was also required to pay the prosecutor's costs in the first matter, and the exhibits, excluding Exhibit A, were permitted to be returned.
Orders
Orders of the court
In matter no. 12/50935 I make the following orders:
1. The Defendant is convicted of the offence as charged.
2. The Defendant is fined the sum of $40,000.
3. The Defendant must pay the Prosecutor's costs in the proceedings as may be determined pursuant to s 257G of the Criminal Procedure Act 1986.
4. Exhibits, other than Exhibit A, may be returned.
In matter no. 12/50936 I make the following order:
1. The charge is dismissed
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.