CITATION:

Group Five Pty Ltd v Body Corporate for Cairns Golden Sands [2018] QCAT 372

PARTIES:

GROUP FIVE PTY LTD
(applicant)

v

BODY CORPORATE FOR CAIRNS GOLDEN SANDS CTS 17890

(respondent)

APPLICATION NO:

OCL053-16

MATTER TYPE:

Other civil dispute matters

DELIVERED ON:

5 November 2018

HEARING DATE:

On the papers

HEARD AT:

Brisbane

DECISION OF:

Senior Member Brown

ORDERS:

There is no order as to costs.

CATCHWORDS:

PROCEDURE – CIVIL PROCEEDINGS IN STATE AND TERRITORY COURTS – COSTS – GENERAL MATTERS – GENERALLY – where enabling Act does not empower QCAT to award costs – whether interests of justice require order for costs – consideration of factors under s 102(3) of Queensland Civil and Administrative Tribunal Act 2009 (Qld) – whether party acted in a way that unnecessarily disadvantaged another party – consideration of nature and complexity of the dispute – consideration of the relative strengths of the claims made by the parties – consideration of the financial circumstances of the parties – consideration of ‘anything else the tribunal considers relevant’ – where no order for costs

Ascot v Nursing & Midwifery Board of Australia [2010] QCAT 364
Queensland Racing Integrity Commission v Vale [2017] QCATA 110
Ralacom Pty Ltd v Body Corporate for Paradise Island Apartments (No 2) [2010] QCAT 412
Samimi v Queensland Building Services Authority [2012] QCAT 133
State of Queensland & Anor v Bell [2016] QCATA 176
Tamawood Ltd & Anor v Paans [2005] 2 Qd R 101
Turner v Macrossan & Amiet Pty Ltd (No 2) [2016] QCAT 255

Body Corporate and Community Management (Accommodation Module) Regulation 2008, s 129
Body Corporate and Community Management Act 1997 (Qld), s 126, Schedule 2
Queensland Civil and Administrative Tribunal Act 2009 (Qld), s 74, s 74(1), s 74(2)(a), s 100, s 102(1), s 102(3), s 102(3)(a), s 102(3)(f)

REPRESENTATION:

Applicant:

Mahoneys

Respondent:

Devenish Law

APPEARANCES:

This matter was heard and determined on the papers pursuant to s 32 of the Queensland Civil and Administrative Tribunal Act 2009 (Qld).

REASONS FOR DECISION

  1. This proceeding involves a dispute between Group Five as caretaking services contractor for Cairns Golden Sands, a scheme comprising 32 lots, and the body corporate for the scheme. The parties had entered into a Management and Letting Agreement (‘the Agreement’). The body corporate issued to Group Five a Remedial Action Notice (‘the RAN’) pursuant to s 129 of the Body Corporate and Community Management (Accommodation Module) Regulation 2008 (the Module) outlining what the body corporate said were breaches by Group Five of the Agreement. Group Five filed an Application to resolve a complex dispute (‘the Application’).  By consent the tribunal granted an injunction restraining the body corporate from terminating or attempting to terminate the Agreement based upon the RAN.[1] On 13 December 2017 the tribunal, by consent, set aside the RAN, ordered the Application be dismissed and directed the parties to file submissions on costs.

    [1]Decision made 27 September 2016.

  2. The costs of the proceeding now fall for determination.

    The background

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Group Five Pty Ltd v Body Corporate for Cairns Golden Sands and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2018] QCAT 372
Decision Date

CaseChat Overview and Summary

The case of Group Five Pty Ltd v Body Corporate for Cairns Golden Sands involves the determination of costs arising from a dispute between the parties, which was heard and determined by the Queensland Civil and Administrative Tribunal (QCAT). The primary dispute centred on the alleged breaches of an agreement by Group Five, leading to the body corporate's assertion of its right to terminate the agreement. The case involved multiple applications, extensions, and a compulsory conference, culminating in a consent order setting aside a resolution and dismissing the application.

The legal issues before the court were primarily concerned with whether QCAT had the authority to award costs and, if not, whether the interests of justice required an order for costs. The court considered the relevant factors outlined in section 102(3) of the Queensland Civil and Administrative Tribunal Act 2009 (Qld), including whether any party acted in a way that unnecessarily disadvantaged another party, the nature and complexity of the dispute, the relative strengths of the claims made by the parties, and the financial circumstances of the parties. The court also considered other relevant factors as stipulated in the Act.

In its reasoning, the tribunal found that the enabling Act, the Body Corporate and Community Management Act 1997 (Qld), did not confer upon QCAT a specific power to award costs. Therefore, costs fell for determination under the provisions of the Queensland Civil and Administrative Tribunal Act 2009 (Qld). The tribunal examined the factors outlined in section 102(3) and noted that many of the extensions of time sought by the parties were jointly requested. The tribunal found that the body corporate's claim that Group Five unnecessarily protracted the proceedings lacked sufficient detail and evidence to warrant a costs order against Group Five. Consequently, the tribunal concluded that no order for costs was warranted.

In summary, the tribunal did not make an order for costs, as it found that the interests of justice did not require such an order given the circumstances of the case.

Orders

Orders of the court

There is no order as to costs.

Background

Background to the litigation

The costs of the proceeding now fall for determination. The background The parties entered into the Agreement in June 2014. On 11 July 2016, the body corporate delivered to Group Five the RAN. The RAN asserted:(a)Breaches by Group Five of the Agreement relating to cleaning and maintenance of various parts of the common property including the bin area, the basement, the lift, the reception area, the grounds, the pool area, access ways and footpaths and toilets;(b)The failure by Group Five to report various by-law breaches;(c)The failure by Group Five to obtain quotes for required maintenance works;(d)The failure by Group Five to carry out directions issued by the body corporate;(e)The failure by Group Five to report to the body corporate committee various hazardous or dangerous matters;(f)The failure by Group Five to adequately staff and maintain the reception area;(g)The dumping of green waste by Group Five in contravention of council local laws;(h)The failure by Group Five to operate a restaurant from the manager’s unit;(i)The failure by Group Five to confer with the body corporate’s representative;(j)Various breaches of the code of conduct for body corporate managers and caretaking service contractors,[2] relying upon the previously identified breaches, and in not acting in the best interests of the body corporate. [2]BCCM Act, schedule 2. On 24 August 2016 the solicitors for the body corporate gave notice to Group Five’s financier pursuant to s 126 of the Body Corporate and Community Management Act 1997 (Qld). The notice asserted the body corporate’s right to terminate the Agreement based upon Group Five’s failure to comply with the RAN. On 7 September 2016 the body corporate gave notice to lot owners of an EGM scheduled for 4 October 2016. The only item on the EGM agenda was the termination of the Agreement. On 23 September 2016 Group Five filed the Application. Group Five also filed an application for interim injunctive relief to restrain the body corporate from terminating or attempting to terminate the Agreement. On 27 September 2016 orders by consent were made granting the interim injunctive relief sought by Group Five. The tribunal made directions for the filing of statements of evidence by the parties and for a compulsory conference to be held. The compulsory conference was held on 23 January 2017. Directions were thereafter made for the parties to file statements of evidence upon which they sought to rely. By consent, the time for compliance with the directions was varied from time to time. Ultimately on 13 December 2017, at a directions hearing, orders were made by consent setting aside the RAN and dismissing the Application. What do the parties say? Group Five says that the proceedings were complex with each party being legally represented. Group Five says that unless it had commenced the proceedings, the Agreement would have been terminated and it would have suffered significant financial losses. Ultimately, says Group Five, it was wholly successful in obtaining the relief it had sought. Group Five seeks its costs of the proceeding to be assessed on the District Court scale.

Evidence

Evidence Before The Court

Decision

Reasons for decision

Ratio Decidendi

Legal Principle Established

The provisions of s 102(3) are not grounds for awarding costs, merely factors the tribunal may take into consideration.[7][7]Ascot v Nursing & Midwifery Board of Australia [2010] QCAT 364.Consideration The relevant enabling Act in this proceeding is the BCCM Act. The BCCM Act does not confer upon the tribunal a specific power to award costs. Accordingly, costs fall for determination under the costs provisions found in Chapter 2, Part 6, Division 6 of the QCAT Act. I will address the matters for consideration set out in s 102(3) of the QCAT Act. Section 102(3)(a) - whether a party to a proceeding is acting in a way that unnecessarily disadvantages another party to the proceeding, including as mentioned in section 48(1)(a) to (g) The body corporate asserts that Group Five caused the proceedings to be protracted by making several requests for extensions of time. The relevant history is that the applicant and respondent were initially directed to file their respective statements of evidence by, respectively, 11 November 2016 and 2 December 2016.[8] By consent the dates for the filing of evidence were extended.[9] By consent the dates were further extended.[10] No directions were made following the compulsory conference held in January 2017 with the next step in the proceeding being the filing of an Application for miscellaneous matters by Group Five on 8 May 2017 seeking orders for the payment by the body corporate of the remuneration payable under the Agreement. By orders made 23 May 2017, the costs of that application were reserved. A further application for miscellaneous matters was filed by Group Five on 6 June 2017 seeking to enforce the payment by the body corporate of an agreed remuneration amount. At a directions hearing on 6 June 2017 the application was dismissed with no order as to costs. The parties were again directed to file their statements of evidence. The parties did not do so. At a directions hearing on 15 August 2017 the parties informed the Tribunal that a general meeting of the body corporate was to be called to address a motion to have a settlement deed executed to resolve the matters in dispute. The matter was listed for a further directions hearing on 12 September 2017. Following two further directions hearings, at a directions hearing on 13 December 2017 the orders were made setting aside the RAN and dismissing the Application. [8]Directions made 27 September 2016.[9]Application for decision/order by consent filed 21 October 2016; Directions made 24 October 2016.[10]Application for decision/order by consent filed 23 November 2016; Directions made 23 November 2016. Many of the extensions of time to comply with directions and which were granted by the tribunal were sought jointly by the parties. As I have observed, at no time (apart from the statement by Mr Ali accompanying the Application and statements by Mr Ali and Group Five’s solicitor relating to the remuneration application) has either party filed statements of evidence. The body corporate’s submission that Group Five protracted the proceeding through requests for extensions of time is not further elaborated upon. If what the body corporate is referring to are the various applications by the parties for orders by consent then, in the absence of more detailed submissions or evidence from the body corporate, it is difficult to see why Group Five should be visited with a costs order on the basis of any asserted delay.