Grandview Ausbuilder Pty Ltd v Budget Demolitions Pty Ltd (No 2)

Link copied
Case Copied 13 min read

Court of Appeal


Supreme Court


New South Wales

Medium Neutral Citation: Grandview Ausbuilder Pty Ltd v Budget Demolitions Pty Ltd (No 2) [2018] NSWCA 341
Hearing dates: On the papers
Decision date: 24 December 2018
Before: Beazley P
Decision:

(1)   Set aside orders (1) and (4) made on 19 December 2018.

 

(2)   Extend the time for compliance with the statutory demand served on 31 January 2018 until 7 days after judgment is delivered on the summons seeking leave to appeal and, if leave be granted, the appeal, on the condition that Grandview Ausbuilder Pty Ltd pay into Court the sum of $340,000 on or before Thursday 10 January 2019.

 

(3)   The monies paid into Court pursuant to order (2) to be paid out as the Court may direct upon determination of the summons seeking leave to appeal and, if leave be granted, the appeal.

 (4)   Direct the parties to provide a timetable by email to the Registrar by 12 noon on Monday 24 December 2018.
Catchwords:

CIVIL PROCEDURE – Court of Appeal – application to extend time for compliance with statutory demand for payment

  JUDGMENTS AND ORDERS – amending, varying and setting aside – Court of Appeal
Legislation Cited: Corporations Act 2001 (Cth), s 459M
Uniform Civil Procedure Rules 2005 (NSW), r 36.16
Cases Cited: Australian Beverage Distributors Pty Ltd v Cranswick Premium Wines Pty Ltd (2004) 50 ACSR 544; [2004] NSWSC 877
Jem Developments Pty Ltd v Hansen Yuncken Pty Ltd (2006) 60 ACSR 393; [2006] NSWSC 1378
Category:Procedural and other rulings
Parties: Grandview Ausbuilder Pty Ltd (Applicant)
Budget Demolitions Pty Ltd (Respondent)
Representation:

Counsel:
V Culkoff (Applicant)
N Allan (Respondent)

  Solicitors:
Julie A Orsini (Applicant)
Ziman & Ziman (Respondent)
File Number(s): 2018/346856
 Decision under appeal 
Court or tribunal:
Supreme Court of New South Wales
Jurisdiction:
Equity
Citation:
Grandview Ausbuilder Pty Ltd v Budget Demolitions Pty Ltd (No 2) [2018] NSWSC 1713
Date of Decision:
7 November 2018
Before:
Parker J
File Number(s):
2018/56438

Judgment

  1. HER HONOUR: On 19 December 2018, I ordered that the time for compliance with a statutory demand served on the applicant, Grandview Ausbuilder Pty Ltd (Grandview), by the respondent, Budget Demolitions Pty Ltd (Budget), on 31 January 2018 be extended until seven days after judgment is delivered on Grandview’s summons seeking leave to appeal from the judgment of Parker J, in which his Honour dismissed Grandview’s application to set aside the statutory demand: Grandview Ausbuilder Pty Ltd v Budget Demolitions Pty Ltd [2018] NSWCA 336.

  2. Following delivery of judgment, counsel for Budget, in an email to the Court, drew the Court’s attention to what appeared to be a misapprehension in my reasons, at [39], as to the existence of certain court proceedings. Budget sought, therefore, that the Court’s judgment be reviewed pursuant to the Uniform Civil Procedure Rules 2005 (NSW), r 36.16(3A).

  3. In that judgment, I stated:

“[38]   I am of the opinion that there is at least a sufficient argument for Grandview to advance in support of its…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Grandview Ausbuilder Pty Ltd v Budget Demolitions Pty Ltd (N... and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Find similar cases

Other decisions on the same topics. Each opens in a new tab.

Details

Case
[2018] NSWCA 341
Decision Date

CaseChat Overview and Summary

Grandview Ausbuilder Pty Ltd sought an extension of time to comply with a statutory demand for payment served by Budget Demolitions Pty Ltd. The matter came before the Court of Appeal.

The primary legal issue before the Court of Appeal was whether to grant an extension of time for Grandview Ausbuilder Pty Ltd to comply with the statutory demand. This involved considering the circumstances surrounding the delay in compliance and the potential prejudice to both parties.

The Court of Appeal, in its decision, set aside previous orders made on 19 December 2018. It then extended the time for compliance with the statutory demand until seven days after the judgment on the summons seeking leave to appeal and, if leave were granted, the appeal itself. This extension was conditional upon Grandview Ausbuilder Pty Ltd paying $340,000 into Court by 10 January 2019. The Court further ordered that these monies be paid out as directed upon the determination of the leave to appeal summons and the appeal. Finally, the parties were directed to provide a timetable to the Registrar by 12 noon on 24 December 2018.

Orders

Orders of the court

(1) Set aside orders (1) and (4) made on 19 December 2018.

(2) Extend the time for compliance with the statutory demand served on 31 January 2018 until 7 days after judgment is delivered on the summons seeking leave to appeal and, if leave be granted, the appeal, on the condition that Grandview Ausbuilder Pty Ltd pay into Court the sum of $340,000 on or before Thursday 10 January 2019.

(3) The monies paid into Court pursuant to order (2) to be paid out as the Court may direct upon determination of the summons seeking leave to appeal and, if leave be granted, the appeal.

(4) Direct the parties to provide a timetable by email to the Registrar by 12 noon on Monday 24 December 2018.