Gold Coast City Council v Sunland Group Limited

Link copied
Case Copied 27 min read

SUPREME COURT OF QUEENSLAND

CITATION:

Gold Coast City Council v Sunland Group Limited & Anor [2020] QCA 89

PARTIES:

GOLD COAST CITY COUNCIL
(applicant)
v
SUNLAND GROUP LIMITED
ACN 063 429 532
SUNLAND DEVELOPMENTS NO 22 PTY LTD
ACN 164 903 011
(respondents)

FILE NO/S:

Appeal No 5420 of 2019
P & E Appeal No 1497 of 2017

DIVISION:

Court of Appeal

PROCEEDING:

Application for Leave Planning and Environment Court Act

ORIGINATING COURT:

Planning and Environment Court at Brisbane – [2019] QPEC 14 (Everson DCJ)

DELIVERED ON:

1 May 2020

DELIVERED AT:

Brisbane

HEARING DATE:

12 November 2019

JUDGES:

Sofronoff P and Philippides and McMurdo JJA

ORDERS:

1.   Grant leave to appeal.

2.   Allow the appeal.

3.   Set aside the orders made by the Planning and Environment Court on 4 April 2019.

4.    Dismiss the Originating Application filed in the Planning and Environment Court.

5.   Order the respondents to pay the appellant’s costs of the appeal and of the proceeding in the Planning and Environment Court.

CATCHWORDS:

APPEAL AND NEW TRIAL – APPEAL - GENERAL PRINCIPLES – RIGHT OF APPEAL – WHEN APPEAL LIES – OTHER CASES –– where one of the respondents purchased land at Mermaid Beach – where the land was then subject to a preliminary approval which had been granted by the Planning and Environment Court under the now repealed Integrated Planning Act 1997 (Qld) (“the IPA”) in 2007 – where the preliminary approval made provision for the development of the land by a multi-stage residential development – where the preliminary approval made provision for contributions to the cost of relevant infrastructure to be paid by developers to the applicant – where those contributions were to be made under planning scheme policies which had been made by the applicant under a regime set out in the IPA – where those planning scheme policies were expressed to be temporary measures – where under the statute which now governs the development of this land, namely the Planning Act 2016 (Qld) (“the Planning Act”), there is no provision for a local government to make any further planning scheme policy for infrastructure – where the respondents say that the only infrastructure charges which can be levied and become payable on the occasion of any development permit issued for this land, are charges calculated by reference to the planning scheme policies – where the applicant says that infrastructure charges must be levied and paid, not according to the policies, but pursuant to the regime for the giving of an infrastructure charges notice under s 119 of the Planning Act – where the Planning and Environment Court made declarations in the respondents’ favour – whether the primary judge erred in finding in favour of the respondent

STATUTES – ACTS OF PARLIAMENT – INTERPRETATION – INTERPRETATION ACTS AND PROVISIONS – where the primary judge found that the preliminary approval imposed a present obligation to pay contributions at a later date – where, in 2011, amendments to the Sustainable Planning Act 2009 (“the

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Gold Coast City Council v Sunland Group Limited and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2020] QCA 89
Decision Date

CaseChat Overview and Summary

The case of Gold Coast City Council v Sunland Group Limited involved a dispute between the Gold Coast City Council (the Council) and Sunland Group Limited (Sunland), regarding the recovery of infrastructure contributions for a land development project at Mermaid Beach. The preliminary approval for the development, granted in 2007 under the repealed Integrated Planning Act 1997 (Qld), included provisions for infrastructure contributions to be made under temporary planning scheme policies. However, under the current Planning Act 2016 (Qld), there is no provision for local governments to make further planning scheme policies for infrastructure. Sunland argued that infrastructure charges should be levied according to the planning scheme policies, while the Council maintained that the charges must be levied under the regime for infrastructure charges notices under section 119 of the Planning Act. The Planning and Environment Court made declarations in favour of Sunland, leading the Council to appeal the decision.

The primary legal issue in the appeal was whether the primary judge erred in finding in favour of Sunland. Specifically, the court needed to determine if the preliminary approval imposed a present obligation to pay contributions at a later date and if section 880 of the Sustainable Planning Act 2009 (SPA) prevented the Council from collecting the contributions under the preliminary approval. The Council argued that section 880 of the SPA, which stated that a local government must not levy certain infrastructure charges or impose a condition under a planning scheme policy, had the effect of preventing the Council from collecting the contributions under the preliminary approval. Sunland, on the other hand, contended that section 880 preserved the lawful effect of the infrastructure conditions.

The court found that the primary judge did not err in his interpretation of the preliminary approval and section 880 of the SPA. The judge held that the infrastructure conditions were in mandatory terms, obligating each contribution to be paid at a specific point in time and calculated according to identified planning scheme policies. The court noted that the Council continued to publish up-to-date rates for the infrastructure conditions, which meant that these conditions remained in effect. Furthermore, the court held that section 880(3) of the SPA expressly preserved the infrastructure conditions and the rights and obligations pertaining to them. Consequently, the Council was obliged to recover infrastructure contributions in accordance with the infrastructure conditions.

The Court of Appeal allowed the appeal, set aside the orders made by the Planning and Environment Court, dismissed the originating application, and ordered Sunland to pay the Council's costs of the appeal and the proceeding in the Planning and Environment Court.

Orders

Orders of the court

1. Grant leave to appeal.

2. Allow the appeal.

3. Set aside the orders made by the Planning and Environment Court on 4 April 2019.

4. Dismiss the Originating Application filed in the Planning and Environment Court.

5. Order the respondents to pay the appellant’s costs of the appeal and of the proceeding in the Planning and Environment Court.

Background

Background to the litigation

Evidence

Evidence Before The Court

Decision

Reasons for decision

Sections 119, 120 and 122 are within chapter 4, part 2.The Judgment The primary judge noted that the parties agreed on the relevant facts. The currency period of the Preliminary Approval, having twice been extended, had effect until 2023. His Honour also noted that the Council had continued to publish up-to-date rates for the planning scheme policies referred to in clauses 13 to 16, which he described as “the infrastructure conditions”.[30][30]Judgment [4]. The primary judge referred to events in 2015 and 2016, in which Sunland lodged a series of development applications, in response to which the Council granted development permits for the development of parts of the subject land. His Honour noted that the Council had then issued what purported to be infrastructure charges notices to Sunland in respect of each of those applications. The charges were not in accordance with the infrastructure conditions.[31][31]Judgment [5]. His Honour said that the first issue for determination was whether the Council was required to recover contributions (and recognise identified credits) in accordance with the infrastructure conditions.[32] But his Honour did not specifically consider whether those charges were validly levied.[33][32]Ibid.[33]Apparently because they were the subject of another challenge by Sunland, in a different case: see [58] below. He summarised the submissions made by Sunland, which had referred to s 286 of the Planning Act and s 801 and s 808 of the SPA. His Honour then summarised the Council’s arguments, which had relied upon s 880 of the SPA. His Honour’s resolution of these arguments was explained within these paragraphs of the judgment:“[11] The difficulty with the Council’s submission is that s 880(3) appears to preserve the lawful effect of the infrastructure conditions. To overcome this difficulty the Council submits that the preliminary approval did not levy infrastructure charges, rather it was worded such that this was left to the development permit stage. I reject this argument. The infrastructure conditions were in mandatory terms. Each contribution was obliged to be paid at a clear point in time (at the time application is made for a development permit). Each contribution is to be calculated in accordance with identified Planning Scheme Policies at the rates current at the due date of payment. The fact that these Planning Scheme Policies have now apparently been repealed is of no consequence in circumstances where, it is uncontentious that the Council continues to publish up-to-date rates for them.[12]There is a further difficulty with the Council’s contention that while the preliminary approval has continuing effect under SPA, the infrastructure conditions do not. There is no provision of SPA which expressly purports to preserve some parts of a preliminary approval and not others. Given the general effect of s 801, and more specifically, the effect of s 808 of SPA in preserving preliminary approvals, clear words would be required to bring about the outcome contended for by the Council. On the contrary s 880(3)(b) and (d) expressly preserved the infrastructure conditions and the rights and obligations pertaining to them. Upon the commencement of the PA they were in turn preserved pursuant to s 286 thereof.[13]It follows that the Council can and is obliged to recover infrastructure contributions (and recognise identified credits) in accordance with the infrastructure conditions.”The effect of s 880 of the SPA

Ratio Decidendi

Legal Principle Established