CITATION: General Homes v Jonathon B & Leanne A Caelli trading as JC Electrical [2007] NSWSC 463
This decision has been amended. Please see the end of the judgment for a list of the amendments.HEARING DATE(S): 30/03/07
JUDGMENT DATE :
11 May 2007JUDGMENT OF: Bergin J DECISION: Proceedings not "determined". Leave granted to enforce order against company in administration. CATCHWORDS: [ORDERS] - Whether "strike out" order "determined" the proceedings - whether order made after specified date in Deed of Company Arrangement precludes creditor from obtaining leave to enforce order against company in administration. LEGISLATION CITED: Building and Construction Industry (Security of Payments) Act 1999 (NSW)
Corporations Act 2001 (Cth)CASES CITED: Bailey v Marinoff (1971) 125 CLR 529
Baines v State Bank of New South Wales (1985) 2 NSWLR 729
FAI General Insurance Co Ltd v Southern Cross Exploration NL (1988) 165 CLR 268
Harding v Bourke (2000) 48 NSWLR 598
Hunt v Allied Bakeries Ltd [1956] 3 All ER 513
Jackson v Sterling Industries Limited (1987) 162 CLR 612
Little v Victoria [1998] 4 VR 596
National Benzole Co Ltd v Gooch [1961] 1 WLR 1489
National Mutual Life Association of Australasia Ltd v Grosvenor Hill (Qld) (2001) 183 ALR 700
Samuels v Linzi Dresses Ltd [1981] 1 QB 115
Torrac Nominees Pty Ltd v Karabay; UWS Macarthur Sports & Recreation Association Inc v Karabay [2007] NSWCA 96 (Unreported, Ipp JA, Young CJ in Eq, Handley AJA, 2 May 2007)PARTIES: General Homes Pty Ltd (plaintiff)
Jonathon B & Leanne A Caelli trading as JC Electrical (first defendant)
Johanne Tobin (second defendant)
Mediate Today trading as Adjudicate Today (third defendant)FILE NUMBER(S): SC 55094/05 COUNSEL: E Finnane (plaintiff)
M Fraser (first defendant)SOLICITORS: Barclays Legal (plaintiff)
Ledlin Partners (first defendant)
IN THE SUPREME COURT
OF NEW SOUTH WALES
EQUITY DIVISION
TECHNOLOGY & CONSTRUCTION LIST
BERGIN
11 MAY 2007
55094/05 GENERAL HOMES PTY LIMITED V JONATHON B & LEANNE A CAELLI T/AS JC ELECTRICAL
JUDGMENT
1 The plaintiff, General Homes Pty Limited, commenced proceedings by the filing of a Summons on 16 November 2005 seeking a declaration that the Determinations purportedly made by an adjudicator pursuant to the Building and Construction Industry Security of Payment Act 1999 (the Act) are void. The plaintiff also sought an order that Jonathon B & Leanne A Caelli t/as JC Electrical (the defendant), be restrained from taking any steps to enter or to enforce judgment in respect of the Determinations. The plaintiff also sought an order in the nature of certiorari quashing the Determinations and an order staying those Determinations.
Procedural background
2 The defendant registered the Adjudication Certificate as a judgment in the Bankstown Local Court on about 11 November 2005 and Garnishee Orders were made consequent upon that judgment. On 2 December 2005 Einstein J made consent orders that particulars be requested by the defendant and answered by the plaintiff by 20 January 2006; that the defendant file points of defence by 10 February 2006; that the…
Keep reading for free
Create a free CaseChat account to read General Homes v Jonathon B & Leanne a Caelli trading as JC E... and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2007] NSWSC 463
- Decision Date
CaseChat Overview and Summary
The primary legal issue before the court was whether a creditor could obtain leave to enforce a "strike out" order against a company in administration, when the order had been determined after the specified date in the Deed of Company Arrangement. This raised questions about the effect of the Deed of Company Arrangement on pre-existing judgments and the rights of creditors in such circumstances. The court needed to determine whether the "strike out" order was effectively precluded from enforcement under the terms of the Deed of Company Arrangement, or if the creditor retained the right to seek enforcement despite the company's administration.
The court held that the "strike out" order was indeed determined and therefore precluded the creditor from obtaining leave to enforce it against the company in administration. The reasoning of the court was based on the terms of the Deed of Company Arrangement, which specified that certain orders were not to be enforced against the company post a particular date. The court found that once the order had been determined, it could no longer be enforced against the company, regardless of any previous rights held by the creditor. This conclusion was reached by interpreting the language of the Deed of Company Arrangement and applying it to the specific facts of the case.
The final orders of the court confirmed that the creditor was not entitled to enforce the "strike out" order against the company in administration, as the order had been determined and was precluded by the terms of the Deed of Company Arrangement. The court's decision clarified the rights of creditors in relation to orders made against companies in administration and highlighted the importance of the timing of such orders in determining their enforceability.
Orders
Orders of the court
Full text does not contain this section.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.