G R Construction and Development Pty Ltd v Brisbane City Council

Link copied
Case Copied 66 min read

PLANNING AND ENVIRONMENT COURT

OF QUEENSLAND

CITATION:

G R Construction & Development Pty Ltd v Brisbane City Council [2022] QPEC 9

PARTIES:

G R CONSTRUCTION & DEVELOPMENT PTY LTD
(Appellant)

v

BRISBANE CITY COUNCIL

(Respondent)

FILE NO/S:

3900/2019

DIVISION:

Planning and Environment

PROCEEDING:

Appeal

ORIGINATING COURT:

Planning and Environment Court, Brisbane

DELIVERED ON:

23 March 2022

DELIVERED AT:

Brisbane

HEARING DATE:

13, 14, 16 September and 27 October 2021 and further written submissions received on 2 and 9 February 2022

JUDGE:

Kefford DCJ

ORDER:

I order:

1.        The appeal is allowed.

2.        The decision of Brisbane City Council notified by the decision notice dated 3 October 2019 is set aside.

3.        The development application is remitted to Brisbane City Council.

4.        Subject to further order of the Court, by 29 April 2022, Brisbane City Council is to give a decision notice approving the proposed development subject to lawful development conditions

CATCHWORDS:

PLANNING AND ENVIRONMENT – APPEAL –DEVELOPMENT APPLICATION – where the Appellant seeks a development in a Rural residential zone – where the Appellant seeks to reconfigure a lot for 12 residential lots, a new road and a balance lot – whether the development is an inappropriate land use – whether the development unacceptably impacts the character and visual amenity of the area – whether the development impacts existing and future industrial uses – whether the development will enjoy appropriate residential amenity despite acoustic impact by industrial development – whether approval is an inappropriate ad hoc approach to planning – whether an approval is an appropriate exercise of the planning discretion

LEGISLATION:

Planning Act 2016 (Qld), ss 45, 59, 60

Planning and Environment Court Act 2016 (Qld), ss 43, 45, 47

Planning Regulation 2017 (Qld), s 31, sch 24

CASES:

Abeleda & Anor v Brisbane City Council & Anor [2020] QCA 257, applied

Ashvan Investments Unit Trust v Brisbane City Council & Ors [2019] QPEC 16; [2019] QPELR 793, approved

Body Corporate for Lindor Community Title Scheme 29204 and Planit Consulting Pty Ltd v Gold Coast City Council & Anor [2018] QPEC 54; [2018 QPELR 265, approved

Brisbane City Council v YQ Property Pty Ltd [2020] QCA 253, applied

Dreamline Development Corporation Pty Ltd v Brisbane City Council & Ors [2021] QPEC 13, approved

Elan Capital Corporation Pty Ltd & Anor v Brisbane City Council [1990] QPLR 209, distinguished

Glenella Estates Pty Ltd v Mackay Regional Council & Ors [2010] QPEC 132; (2010) 180 LGERA 226, distinguished

Intrafield Pty Ltd v Redland Shire Council [2001] QCA 116; (2001) 116 LGERA 350, applied

Isgro v Gold Coast City Council & Anor [2003] QPEC 2; [2003] QPELR 414, approved

Kanesamoorthy & Anor v Brisbane City Council [2016] QPEC 42; [2016] QPELR 784, approved

Magree & Ors v Landsborough Shire Council & Anor [1987] QPLR 149, approved

McKay v Brisbane City Council & Anor; Panozzo v Brisbane City Council & Anor; Jensen v Brisbane City Council & Anor [2021] QPEC 42, approved

Murphy…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read G R Construction and Development Pty Ltd v Brisbane City Cou... and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2022] QPEC 9
Decision Date

CaseChat Overview and Summary

In G R Construction and Development Pty Ltd v Brisbane City Council, the appellant sought a development in a Rural residential zone. The appellant's development application aimed to reconfigure a lot into 12 residential lots, create a new road, and establish a balance lot. The Brisbane City Council refused to approve the development. The appellant then appealed to the Queensland Planning and Environment Court, which was required to determine whether the proposed development was an inappropriate land use, whether it unacceptably impacted the character and visual amenity of the area, whether it affected existing and future industrial uses, whether it would enjoy appropriate residential amenity despite acoustic impacts from industrial development, whether approval would be an inappropriate ad hoc approach to planning, and whether an approval would be an appropriate exercise of the planning discretion.

The court held that the statutory framework in the Planning and Environment Court Act 2016 (Qld) and the Planning Act 2016 (Qld) applied. The exercise of the discretion must be based on an assessment that must be carried out against the assessment benchmarks and having regard to, relevantly, any development approval for, and any lawful use of, the premises and adjacent premises and the common material, including properly made submissions about the development application. The Court of Appeal decisions in Brisbane City Council v YQ Property Pty Ltd, Abeleda & Anor v Brisbane City Council & Anor, Wilhelm v Logan City Council & Ors, and Trinity Park Investments Pty Ltd v Cairns Regional Council & Ors; Dexus Funds Management Limited v Fabcot Pty Ltd & Ors confirm the approach articulated in Ashvan Investments Unit Trust v Brisbane City Council & Ors and Murphy v Moreton Bay Regional Council & Anor; Australian National Homes Pty Ltd v Moreton Bay Regional Council & Anor. The starting point generally remains that the planning scheme is taken to be an embodiment of the public interest. Nevertheless, the Planning Act 2016 affords flexibility to an assessment manager, or the Court on appeal, in deciding an impact assessable development application, to permit approval of a development application in the face of non-compliance with a planning scheme.

The Court concluded that the appeal was allowed, and the decision of Brisbane City Council notified by the decision notice dated 3 October 2019 was set aside. The development application was remitted to Brisbane City Council. Subject to further order of the Court, by 29 April 2022, Brisbane City Council was to give a decision notice approving the proposed development subject to lawful development conditions.

Orders

Orders of the court

I order:

1. The appeal is allowed.

2. The decision of Brisbane City Council notified by the decision notice dated 3 October 2019 is set aside.

3. The development application is remitted to Brisbane City Council.

4. Subject to further order of the Court, by 29 April 2022, Brisbane City Council is to give a decision notice approving the proposed development subject to lawful development conditions

Background

Background to the litigation

Full text does not contain this section.

Evidence

Evidence Before The Court

Full text does not contain this section.

Decision

Reasons for decision

Each of the above questions are to be determined by reference to the applicable statutory assessment and decision-making framework. What is the relevant framework for the decision? The statutory framework in the Planning and Environment Court Act 2016 (Qld) and the Planning Act 2016 (Qld) applies. There is a broad discretion in determining these appeals.[12] As the development application required an impact assessment, the exercise of the discretion must be based on an assessment that:[13](a)must be carried out against the assessment benchmarks[14] and having regard to, relevantly, any development approval for, and any lawful use of, the premises and adjacent premises and the common material, including properly made submissions about the development application;[15] and(b)may be carried out against, or having regard to, any other relevant matter, other than a person’s personal circumstances (financial or otherwise).[12]Planning and Environment Court Act 2016 s 47; Planning Act 2016 s 60(3). [13]Planning Act 2016 ss 45(5) and 59.[14]City Plan version 15 applied at the time the development application was properly made. See Exhibit 5.1 p 2 [1].[15]Planning Regulation 2017 (Qld) s 31 and sch 24. In deciding the appeal, the Court must confirm the decision appealed against, or change the decision appealed against, or set it aside and either make a decision replacing it or return the matter to the Council with directions that the Court considers appropriate.[16][16]Planning and Environment Court Act 2016 s 47. The assessment and decision-making process is to be approached consistent with the Court of Appeal decisions of Brisbane City Council v YQ Property Pty Ltd,[17] Abeleda & Anor v Brisbane City Council & Anor,[18] Wilhelm v Logan City Council & Ors[19] and Trinity Park Investments Pty Ltd v Cairns Regional Council & Ors; Dexus Funds Management Limited v Fabcot Pty Ltd & Ors.[20] Collectively, those cases confirm the approach articulated in Ashvan Investments Unit Trust v Brisbane City Council & Ors[21] and Murphy v Moreton Bay Regional Council & Anor; Australian National Homes Pty Ltd v Moreton Bay Regional Council & Anor.[22][17][2020] QCA 253.[18][2020] QCA 257.[19][2020] QCA 273.[20][2021] QCA 95.[21][2019] QPEC 16; [2019] QPELR 793, 803-13 [35]-[86].[22][2019] QPEC 46; [2020] QPELR 328, 333-7 [12]‑[22]. As is apparent from the Court of Appeal decisions, the starting point generally remains that the planning scheme is taken to be an embodiment of the public interest.[23] In most instances, where a planning scheme is not affected by changed circumstances, the decision-maker would give significant weight to it.[24] Nevertheless, the Planning Act 2016 affords flexibility to an assessment manager, or the Court on appeal, in deciding an impact assessable development application, to permit approval of a development application in the face of non-compliance with a planning scheme.[25] Inherent in the exercise of the discretion to approve a development application in the face of non-compliance is a balancing exercise that is invariably complicated and multi-faceted. The exercise is to be based on the assessment carried out under s 45 of the Planning Act 2016. The way the balance is struck will turn on the facts and circumstances of each case, including the nature and extent of the non-compliances, if any, with an assessment benchmark.[26][23]Abeleda & Anor v Brisbane City Council & Anor [2020] QCA 257, [42], [54]; Wilhelm v Logan City Council & Ors [2020] QCA 273, [77].[24]Abeleda & Anor v Brisbane City Council & Anor [2020] QCA 257, [40].[25]Abeleda & Anor v Brisbane City Council & Anor [2020] QCA 257, [53]; Ashvan Investments Unit Trust v Brisbane City Council & Ors [2019] QPEC 16; [2019] QPELR 793, 804‑6 [40]-[51]; Murphy v Moreton Bay Regional Council & Anor; Australian National Homes Pty Ltd v Moreton Bay Regional Council & Anor [2019] QPEC 46; [2020] QPELR 328, 334 [13]‑[14].[26]Abeleda & Anor v Brisbane City Council & Anor [2020] QCA 257, [56]-[57].

Ratio Decidendi

Legal Principle Established

Full text does not contain this section.