Supreme Court
New South Wales
Medium Neutral Citation: Futurepower Developments Pty Ltd v TJ & RF Fordham Pty Ltd [2017] NSWSC 232 Hearing dates: 6 March 2017 Decision date: 14 March 2017 Jurisdiction: Equity - Technology and Construction List Before: Ball J Decision: The claim for relief in paragraphs 1, 2, 3, 7 and 8 of the summons dismissed with costs.
Catchwords: ADMINISTRATIVE LAW – judicial review – jurisdictional error – whether adjudicator failed to afford natural justice or procedural fairness – whether adjudicator gave sufficient reasons for his decision
BUILDING AND CONSTRUCTION – Building and Construction Industry Security of Payment Act 1999 (NSW) – adjudication determination – whether adjudicator erred in making a finding in relation to the “Superintendent’s Representative” – whether adjudicator adequately dealt with contract variationsLegislation Cited: Building and Construction Industry Security of Payment Act 1999 (NSW); s22(5) Cases Cited: Brookhollow Pty Limited v R&R Consultants Pty Limited and Anor [2006] NSWSC 1
Clyde Bergemann Senior Thermal Pty Ltd v Varley Power Services Pty Ltd [2011] NSWSC 1039
Collector of Customs v Pozzolanic Enterprises Pty Ltd (1993) 43 FCR 280; [1993] FCA 456
Minister for Immigration and Ethnic Affairs v Wu Shan Liang (1996) 185 CLR 259; [1996] HCA 6
PPK Willoughby v Eighty Eight Construction Pty Ltd [2014] NSWSC 760
Watpac Constructions (NSW) Pty Ltd v Austin Corp [2010] NSWSC 168Category: Principal judgment Parties: Futurepower Developments Pty Ltd (Plaintiff)
TJ & RF Fordham Pty Ltd (First Defendant)
Doron Rivlin (Second Defendant)
Adjudicate Today Pty Ltd (Third Defendant)Representation: Counsel:
Solicitors:
P Bambagiotti (Plaintiff)
FP Hicks (First Defendant)
Submitting Appearance (Second & Third Defendants)
Barclays Law Group (Plaintiff)
Moray & Agnew (First Defendant)
File Number(s): 2016/195001 Publication restriction: None
Judgment
Introduction
-
By a summons filed on 27 June 2016, the plaintiff, Futurepower, seeks to quash a determination of the second defendant (the Adjudicator) made on 15 June 2016 under the Building and Construction Industry Security of Payment Act 1999 (NSW) (the Act) in favour of the first defendant, TRN, in the sum of $684,054.89.
-
Futurepower also seeks relief in respect of the underlying construction contract. However, that relief is not the subject of this judgment.
Background
-
On or about 12 June 2015, TRN, as contractor, and Futurepower, as developer or principal, entered into a construction contract by which TRN agreed to undertake the construction of roads and drainage works for a residential subdivision at Jardine Drive, Edmondson Park, New South Wales (the Contract). The Contract was in writing and was for a lump sum of $899,043.04, excluding GST. North Western Surveys Pty Ltd (NWS), together with one of its employees, Mr John Attard, was named as the Superintendent under the Contract.
-
On 29 April 2016, TRN submitted a payment claim for an amount of $691,984.71, including GST. The payment claim included an amount of $422,733.10 plus GST which was claimed in respect of 12 variations to the Contract for the costs of removing asbestos which was…
Keep reading for free
Create a free CaseChat account to read Futurepower Developments Pty Ltd v TJ and RF Fordham Pty Ltd and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
Find similar cases
Other decisions on the same topics. Each opens in a new tab.
Details
- Case
- [2017] NSWSC 232
- Decision Date
CaseChat Overview and Summary
The legal issues the court had to resolve included whether the adjudicator failed to afford natural justice or procedural fairness and whether the adjudicator provided sufficient reasons for his decision. Additionally, the court examined whether the adjudicator erred in making a finding in relation to the "Superintendent’s Representative" and if he adequately dealt with contract variations.
The court found that the adjudicator had indeed failed to afford natural justice or procedural fairness, as he did not allow Futurepower an adequate opportunity to respond to a significant allegation. Furthermore, the court held that the adjudicator's reasons were insufficient because they did not address the key issue of the "Superintendent’s Representative". The adjudicator's decision regarding contract variations was also found to be inadequate as he did not properly consider the terms of the contract in relation to these variations.
The Supreme Court of New South Wales quashed the adjudicator's determination and remitted the matter for reconsideration by a different adjudicator. This decision underscored the importance of ensuring procedural fairness and providing adequate reasons in adjudication proceedings.