District Court
New South Wales
Medium Neutral Citation: Fordham v Dewsash Pty Ltd t/as S.P. & W. Hobson [2012] NSWDC 109 Hearing dates: 25/05/2012 and 28/05/2012 Decision date: 27 July 2012 Before: P Taylor SC DCJ Decision: 1. Allow the appeal.
2. Set aside the orders of the Tribunal.
3. Remit the matter to the Tribunal for a rehearing in accordance with these reasons, pursuant to ss 67(3)(b) and (4) of the CTTT Act.
4. Order that the plaintiff's costs of the appeal be costs of the proceedings in the Tribunal.
Catchwords: Appeal from Tribunal - question with respect to matter of law - no evidence - agreement - mitigation of loss - quantum of damages - estoppel - costs Legislation Cited: Consumer, Trader and Tenancy Tribunal Act 2001 Cases Cited: Kostas v HIA Insurance Services Pty Limited [2010] HCA 32
Mahlo & Ors v Westpac Banking Corporation Ltd [1999] NSWCA 358
Pavey & Matthews v Paul (1987) 162 CLR 221Category: Principal judgment Parties: James Arthur Fordham (plaintiff)
Dewsash Pty Limited t/as S.P. & W. Hobson (defendant)Representation: Mr J Young (plaintiff)
Mr S V Shepherd (defendant)
Blackwell Short Lawyers (plaintiff)
Creaghe Lisle Solicitors (defendant)
File Number(s): 2011/165234 Publication restriction: No Decision under appeal
- Date of Decision:
- 2011-03-17 00:00:00
- Before:
- Tribunal Member S Smith
- File Number(s):
- HB 09/25483; HB 10/21874
Judgment
A. Introduction
This is an appeal from a decision of the Consumer, Trader and Tenancy Tribunal ("the Tribunal") under s 67 of the Consumer, Trader and Tenancy Tribunal Act 2001 ("the CTTT Act"), in respect of a building dispute.
B. Background
The facts as found by the Tribunal were as follows.
Mr Fordham, the plaintiff, owned some rural land at Bendick Murrell in the central west of New South Wales. He had plans to build a cottage. He negotiated with Mr Hobson, the owner of the defendant's building company, and on 25 June 2002 the parties entered a standard HIA contract for the building of the house. The contract provided for a price of $187,000 with no deposit, and a schedule of progress payments commencing with $50,000 when the slab and underfloor plumbing were complete.
Site work commenced in November 2002, and after many inspections and rectifications the main part of the slab was poured on 13 May 2003.
In April 2003, shortly before the slab was poured, the defendant presented the plaintiff with invoices totalling $36,000. As the slab had not been poured, the plaintiff may have been within his rights to make no payment until all works referable to the first progress payment were substantially complete. In any event, on about 28 April 2003 the plaintiff paid the defendant $29,000.
After the slab was poured, a further dispute arose between the parties concerning the adequacy of the slab. Experts were retained. After some debate those experts, Mr Simpson for the defendant, and Mr Noonan for the plaintiff, agreed on a rectification procedure whereby a concrete topping would be put on the existing slab to…
Keep reading for free
Create a free CaseChat account to read Fordham v Dewsash Pty Ltd t/as S.P. and W. Hobson and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2012] NSWDC 109
- Decision Date
CaseChat Overview and Summary
The central legal issues before the court were whether the Tribunal erred in law by finding that there was no evidence of an agreement, the extent to which the plaintiff mitigated his losses, the appropriate quantum of damages, and whether an estoppel applied to prevent the defendant from relying on certain facts. Additionally, the court had to consider the allocation of costs between the parties.
The court found that the Tribunal had erred in concluding that there was no evidence of an agreement between the parties. The court held that there was sufficient evidence to establish the existence of a binding contract. Regarding mitigation of loss, the court found that the plaintiff had not adequately mitigated his losses, which impacted the quantum of damages awarded. The court also held that an estoppel applied, preventing the defendant from relying on certain facts. Finally, the court ordered that the plaintiff's costs of the appeal be costs of the proceedings in the Tribunal.
The court allowed the appeal, set aside the orders of the Tribunal, and remitted the matter to the Tribunal for a rehearing in accordance with the court's reasons. The court also ordered that the plaintiff's costs of the appeal be costs of the proceedings in the Tribunal.
Orders
Orders of the court
1. Allow the appeal.
2. Set aside the orders of the Tribunal.
3. Remit the matter to the Tribunal for a rehearing in accordance with these reasons, pursuant to ss 67(3)(b) and (4) of the CTTT Act.
4. Order that the plaintiff's costs of the appeal be costs of the proceedings in the Tribunal.
Background
Background to the litigation
Evidence
Evidence Before The Court
Decision
Reasons for decision
Ratio Decidendi