| IN THE SUPREME COURT OF VICTORIA | Not Restricted | |
AT MELBOURNE
COMMERCIAL AND EQUITY DIVISION
BUILDING CASES LIST
No. 6527 of 2000
| FLUOR AUSTRALIA PTY LTD (ACN 004 511 942) | Plaintiff |
| v | |
| SHERRITT INTERNATIONAL CORPORATION (NB-500937) | First Defendant |
| DYNATEC CORPORATION (ON-1261960) | Second Defendant |
---
JUDGE: | Byrne J | |
WHERE HELD: | Melbourne | |
DATE OF HEARING: | 3 May 2002 | |
DATE OF JUDGMENT: | 29 May 2002 | |
CASE MAY BE CITED AS: | Fluor Australia Pty Ltd v Sherritt International Corporation | |
MEDIUM NEUTRAL CITATION: | [2002] VSC 203 | |
---
Practice and Procedure – claims for damages for negligence and misleading and deceptive conduct – alleged loss comprises liability to third party the subject of incomplete arbitration – whether present loss – whether claims premature – stay or summary judgment – inconsistent allegations – abuse of process – pleadings – sufficiency of particulars
APPEARANCES: | Counsel | Solicitors |
| For the Plaintiff | Mr D.G. Collins SC, with Ms A.M. Ryan | Allens Arthur Robinson |
| For the Defendants | Mr J.G. Santamaria QC, with Mr R.M. Peters | Arnold Bloch Leibler |
HIS HONOUR:
This litigation commenced by writ filed on 18 August 2000 arises out of a project for the design, construction and commissioning of a nickel and cobalt treatment plant at Murrin Murrin in Western Australia. The project was undertaken by certain joint venturers who acted by their agent Anaconda Operations Pty Ltd (“Anaconda”). On 21 August 1997 the plaintiff, Fluor Australia Pty Ltd (“Fluor”), entered into two agreements with Anaconda whereby it agreed to complete the design and construction of the plant and to provide Anaconda with assistance in the “commissioning, production and ramp up and other operational support following mechanical completion of the Plant”.[1] These contracts contained provisions for the resolution of disputes by arbitration. Disputes have indeed arisen between Fluor and Anaconda and these have been referred to arbitration pursuant to the Commercial Arbitration Act 1984 (Vic). The arbitration is not complete.
[1]Statement of claim para. 29.
The defendants to this proceeding are two Canadian companies whose business it is to provide process and metallurgical technologies services with respect to mineral extraction. The secondnamed defendant, Dynatec Corporation (“Dynatec”), is a wholly owned subsidiary of the firstnamed defendant, Sherritt International Corporation (“Sherritt”), and is the company through which Sherritt provides its process and metallurgical technologies services. I shall refer to Sherritt and Dynatec as “the Sherritt parties” unless it be necessary to distinguish between them. Before the 1997 agreements between Anaconda and Fluor were entered into, Sherritt was retained in March 1995 by Anaconda Nickel Ltd, the ultimate holding company of one of the joint venturers, to grant to Anaconda Nickel a licence to use its technology in the project and to provide process design, engineering and technical services in relation to it.[2] For this latter purpose the Sherritt parties prepared a feasibility study, performed test work and preliminary design for the plant.
[2]Statement of claim para. 7.
Between June 1996 and August 1997 Fluor was introduced into the project and worked in conjunction with the Sherritt parties in…
Keep reading for free
Create a free CaseChat account to read Fluor Australia Pty Ltd v Sherritt International Corporation and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
Find similar cases
Other decisions on the same topics. Each opens in a new tab.
Details
- Case
- [2002] VSC 203
- Decision Date
CaseChat Overview and Summary
The court examined the nature of Fluor Australia's loss, focusing on whether it constituted a present loss or was contingent on the outcome of the incomplete arbitration. It was necessary to determine whether the claims for damages could proceed or if they should be stayed until the arbitration was finalised. The court also considered whether the inconsistent allegations in the pleadings rendered the claims ambiguous and whether there was an abuse of process in bringing the claims. Furthermore, the sufficiency of the particulars in the pleadings was assessed to ensure that the claims were adequately described.
In its decision, the court held that Fluor Australia's loss was not a present loss as it depended on the outcome of the incomplete arbitration. Consequently, the claims for damages were premature and should be stayed until the arbitration was finalised. The court also found that there was an abuse of process in bringing the claims due to the inconsistent allegations and insufficient particulars in the pleadings. The court ruled that the claims were inadequately described, and as such, the plaintiff's claims were dismissed. The court ordered that the proceedings be stayed pending the outcome of the arbitration and that the plaintiff pay the defendant's costs.
Background
Background to the litigation
Decision
Reasons for decision