| IN THE SUPREME COURT OF VICTORIA | Not Restricted |
AT MELBOURNE
COMMERCIAL AND EQUITY DIVISION
BUILDING CASES LIST
No. 6527 of 2000
| FLUOR AUSTRALIA PTY LTD | Plaintiff |
| v | |
| SHERRITT INTERNATIONAL CORPORATION AND ANOTHER | Defendants |
---
JUDGE: | HARPER J | |
WHERE HELD: | MELBOURNE | |
DATE OF HEARING: | 27 SEPTEMBER 2002 | |
DATE OF JUDGMENT: | 30 SEPTEMBER 2002 | |
CASE MAY BE CITED AS: | FLUOR AUSTRALIA PTY LTD v SHERRITT INTERNATIONAL CORP & ANOR | |
MEDIUM NEUTRAL CITATION: | [2002] VSC 420 | |
---
practice and procedure – Application to strike out statement of claim – Liability contingent on outcome of arbitration – Arbitrator's award in relation to part of claims only – Incomplete cause of action – Portions of statement of claim unsustainable.
---
APPEARANCES: | Counsel | Solicitors |
| For the Plaintiff | Ms A.M. Ryan | Allens Arthur Robinson |
| For the Defendants | Mr J. Santamaria QC with Mr R. Peters | Arnold Bloch Liebler |
HIS HONOUR:
This is the return of a summons issued by the defendants on 25 September 2002. By it, those parties seek an order that the plaintiff’s amended statement of claim, which is dated 1 February 2002, be struck out. Consequential orders are also sought.
It is necessary to sketch the background to the dispute. On 21 August 1997, the plaintiff entered into two agreements with Anaconda Operations Pty Ltd ("Anaconda"). They concern the construction of a cobalt and nickel treatment plant at Murrin Murrin in Western Australia. The plaintiff’s role, among other things, was to "complete the design and construction of the plant" and to provide assistance to Anaconda in the "commissioning, production and ramp up and other operational support following [the plant’s] mechanical completion."[1]
[1]Amended statement of claim, paragraph 29.
Rightly or wrongly, Anaconda was not happy with the plaintiff’s performance, or at least some aspects of it. It accordingly invoked those provisions in the contracts which provided for the resolution of disputes by arbitration. Arbitral proceedings subsequently commenced. On 7 September 2002, the arbitrators handed down the first of what may be expected to be a series of awards; certainly, the interim award of 7 September does not purport to resolve all the issues submitted to arbitration. It is concerned only with what is known as "Area 3200" of the Murrin Murrin plant, one of numerous ares into which the plant is divided. Of the other areas, disputes in relation to those known as Areas 3300 to 3700 are still before the arbitrators.
The decision to go to arbitration was a step which, in the plaintiff’s eyes, left it more exposed than it deserves to be. For while the plaintiff (as I understand it) denies most if not all of Anaconda’s allegations, it contends that, if they are made out, then it is entitled to be indemnified by the defendants.
This is the classic "third party" claim. Unfortunately, however, it is "a very great shortcoming of arbitration as a dispute resolution process … that it does not easily admit" such a claim: see the judgment of Byrne J delivered on 29 May 2002, in an earlier…
Keep reading for free
Create a free CaseChat account to read Fluor Australia Pty Ltd v Sherritt International Corporation and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
Find similar cases
Other decisions on the same topics. Each opens in a new tab.
Details
- Case
- [2002] VSC 420
- Decision Date
CaseChat Overview and Summary
The central legal issue revolved around the enforceability of claims that were contingent upon the outcome of an arbitration process. The court had to assess whether the incomplete nature of the arbitration award, which addressed only part of the applicant’s claims, affected the validity of the remaining claims in the statement of claim. Additionally, the court considered whether the doctrine of severability applied, allowing the sustainable portions of the claim to proceed independently from the unsustainable parts.
The court ruled that the claims which were contingent on the outcome of the arbitration could not proceed in the absence of a final arbitration award. It found that the incomplete arbitration process rendered these claims unsustainable. However, the court also determined that the doctrine of severability applied, allowing the parts of the statement of claim not contingent on the arbitration to proceed. The court found that these claims were sufficiently independent and could be severed from the contingent claims, thereby permitting the remaining parts of the statement of claim to continue.
In conclusion, the Federal Court of Australia allowed the application to strike out the portions of the statement of claim that were contingent on the outcome of the arbitration. However, it permitted the remaining, independent claims to proceed, effectively severing them from the contingent claims. The court's decision provided clarity on the enforceability of contingent claims in the context of incomplete arbitration awards and the application of the doctrine of severability in such scenarios.
Background
Background to the litigation
Decision
Reasons for decision
Ratio Decidendi