Civil and Administrative Tribunal
New South Wales
Medium Neutral Citation: Farthing v Wagg and Hackett; Wagg and Hackett v Farthing [2015] NSWCATCD 12 Hearing dates: 13, 14 and 15 May 2013, 2 July 2013 and 1 September 2014 Decision date: 22 January 2015 Jurisdiction: Consumer and Commercial Division Before: N Correy, Senior Member Decision: 1. In matter HB11/43514 that the homeowners pay to the builder the sum of $41,148.01 in damages for breach of contract.
2. In matter HB 11/62299 that the builder pay to the homeowners the sum of $1,125.00 in respect to the costs of rectification of defective work.
3. That the homeowners pay to the builder the difference in the amounts payable in paragraphs 1 and 2 above being an amount of $40,023.01 within 28 days of the date of this order.
4. That the builders submissions in relation to costs be filed and served on the homeowners within 21 days of the date of this order.
5. That the homeowners response to the builder’s costs submissions be filed and served on the builder within 21 days of the date of service upon them of the builders submission .
6. Any reply submissions by the builder if required, limited to two pages be filed within 7 days of receipt of the homeowners’ submissions.Legislation Cited: Home Building Act 1989 (HBA)
Civil and Administrative Tribunal Act 2013 (CAT)Cases Cited: Koompahtoo Local Aboriginal Land Council v Sanpine Pty Ltd (2007) CLR 115
McCann v Switzerland Insurance Australia (2000) 203 CLR 589
Floriut Holdings Pty Ltd v Sebastian Builders and Developers Pty Ltd (2009)NSWCA 303
Carr v JA Berriman Pty Ltd (1953) 27 ALR 273
North Sydney Leagues Ltd v Synergy Protection Agency Pty Ltd [2012] NSWCA 168
Robinson v Harman (1848) 1 Ex 850
Chappel v Hart (1998) 195 CLR 232
Nowlan v Marson Transport Pty ltd [2001] NSWCA 346
White v Overland [2002] FCA 1333Category: Principal judgment Parties: Dean Farthing (applicant/cross respondent)
Andrew Wagg and Marie Hackett (respondents/cross applicants)Representation: Counsel: BCA Bradley for Farthing
T Catanzariti for Wagg and Hackett
Solicitors: HWL Ebsworth Lawyers for D Farthing
Maccallum Lawyers for Andrew Wagg and Marie Hackett
File Number(s): HB 11/43514 and HB 11/62299 Publication restriction: Nil
reasons for decision
APPLICATIONS
-
There are two applications before me which proceeded together with such evidence heard forming the basis for my determination in both matters.
-
The builder’s application HB 11/ 43514 dated 25 August 2011 seeks damages for breach of contract following an alleged wrongful termination by the homeowners of the contract between the parties.
-
The homeowners’ application HB11 /62299 dated 22 November 2011 alleges a number of breaches of the contract by the builder including a failure to provide complete substantiation of invoices as required by the contract, underestimating the cost of the job, building the house in a location on the site not in accordance with the homeowners request resulting in higher costs, overcharging in respect to labour hire employees and the cost of a number…
Keep reading for free
Create a free CaseChat account to read Farthing v Wagg and Hackett; Wagg and Hackett v Farthing and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2015] NSWCATCD 12
- Decision Date
CaseChat Overview and Summary
The primary legal issues before the court were whether the builder had breached the contract by failing to complete the works to the agreed standard and whether the homeowners were liable for any payment defaults. The court also had to decide on the costs associated with rectifying the defective work and the appropriate allocation of costs between the parties. The court needed to interpret the terms of the contract and assess whether either party had breached the agreement or acted in a manner inconsistent with the terms.
The court found that the builder had indeed breached the contract by failing to complete the works to the agreed standard and by not rectifying the identified defects. The court determined that the homeowners were also liable for a portion of the payment default, but less than the builder claimed. The court ordered the homeowners to pay the builder the difference in the amounts owed, and also directed the builder to pay the homeowners for the costs of rectifying the defective work. The court provided detailed instructions for the submission and response of costs between the parties, outlining the timeline and limitations for each step.
The court's orders were precise and directed both parties to take specific actions within defined timeframes. The homeowners were ordered to pay the builder a net amount of $40,023.01, reflecting the balance of the owed amounts after accounting for the costs of rectification. The builder was required to submit and serve its cost submissions within 21 days of the order, with the homeowners responding within a further 21 days. Any reply submissions by the builder were limited to two pages and had to be filed within 7 days of receipt of the homeowners' submissions. This detailed and structured approach ensured clarity and compliance in the execution of the court's directives.
Orders
Orders of the court
1. In matter HB11/43514 that the homeowners pay to the builder the sum of $41,148.01 in damages for breach of contract.
2. In matter HB 11/62299 that the builder pay to the homeowners the sum of $1,125.00 in respect to the costs of rectification of defective work.
3. That the homeowners pay to the builder the difference in the amounts payable in paragraphs 1 and 2 above being an amount of $40,023.01 within 28 days of the date of this order.
4. That the builders submissions in relation to costs be filed and served on the homeowners within 21 days of the date of this order.
5. That the homeowners response to the builder’s costs submissions be filed and served on the builder within 21 days of the date of service upon them of the builders submission .
6. Any reply submissions by the builder if required, limited to two pages be filed within 7 days of receipt of the homeowners’ submissions.
Background
Background to the litigation
Evidence
Evidence Before The Court
Decision
Reasons for decision
Ratio Decidendi