Fallon Street Properties Pty Ltd v Steel & Stuff Pty Ltd

Link copied
Case Copied 39 min read

NEW SOUTH WALES COURT OF APPEAL

CITATION:      FALLON STREET PROPERTIES PTY LTD v STEEL & STUFF PTY LTD [2006]  NSWCA 296

FILE NUMBER(S):
40946/05

HEARING DATE(S):               19 September 2006

DECISION DATE:     02/11/2006

PARTIES:
Fallon Street Properties Pty Ltd - Appellant
Steel & Stuff Pty Ltd - Respondent

JUDGMENT OF:       Santow JA Basten JA Hunt AJA   

LOWER COURT JURISDICTION: Supreme Court

LOWER COURT FILE NUMBER(S):          SC 4998/04

LOWER COURT JUDICIAL OFFICER:     Palmer J

COUNSEL:
S. Gagler SC/B. J. Sharpe - Appellant
H.J.A. Neal - Respondent

SOLICITORS:
JL & Sons, Sydney - Appellant
Dick & Williams, Albury - Respondent

CATCHWORDS:
LEASE – Land leased with partly completed development – reduced rent payable – whether lease subject to implied term that landlord should complete the building in accordance with the interim occupation certificate under the Environmental Planning and Assessment Act 1979 (NSW) within a reasonable time
DAMAGES – relocation to new premises – whether cost of relocation so far in excess of costs for completing building that it was not reasonable compensation – whether period for costs of additional rent should not extend beyond the date of termination of existing lease

LEGISLATION CITED:
Environmental Planning and Assessment Act 1979 (NSW), ss 109M, 121B

DECISION:
(1)  Allow the appeal in part and set aside order 5 made in the Equity Division on 11 November 2005 and entered on 6 December 2005
(2)  In lieu thereof, give judgment for the Respondent (the plaintiff below) in the sum of $342,824
(3)  Otherwise dismiss the appeal
(4)  Order the Appellant to pay the Respondent's costs of the appeal
(5)  Grant the Respondent a certificate under the Suitors’ Fund Act 1951 (NSW) in respect of that part of the appeal on which it was unsuccessful, if not disqualified pursuant to s 6(7).

JUDGMENT:

IN THE SUPREME COURT
OF NEW SOUTH WALES
COURT OF APPEAL

CA 40946/05
SC 4998/04

SANTOW JA
BASTEN JA
HUNT AJA

2 November 2006

FALLON STREET PROPERTIES PTY LTD v STEEL & STUFF PTY LTD

In May 2003, the Respondent leased premises from the Appellant for the manufacture, storage and sale of steel products.  The building on the land was uncompleted, but the consent authority under the Environmental Planning and Assessment Act 1979 (NSW) had issued an “interim occupation certificate”. At the time the lease was negotiated the building, being incomplete, was unsuitable for use as a sale room. Accordingly, pursuant to an oral agreement, the Respondent occupied the premises on the understanding that only half the monthly rental would be payable until the building and its curtilage were completed. The Appellant did not complete the building and the Respondent suffered losses. After further disputes, the Respondent secured alternative premises.

In September 2004 the Appellant demanded possession of the premises on the basis that the Respondent had, without justification, set off moneys owing to it in respect of the premises against the rent and was in breach of the lease.  The Respondent cross-claimed to prevent the Appellant disturbing its right of quiet possession of the…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Fallon Street Properties Pty Ltd v Steel & Stuff Pty Ltd and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2006] NSWCA 296
Decision Date

CaseChat Overview and Summary

Fallon Street Properties Pty Ltd (the appellant) and Steel & Stuff Pty Ltd (the respondent) were parties to a lease agreement concerning land with a partly completed development, under which a reduced rent was payable. The dispute centred on whether the lease contained an implied term that the landlord was obliged to complete the building in accordance with the interim occupation certificate issued under the *Environmental Planning and Assessment Act 1979* (NSW) within a reasonable time. The respondent also sought damages for relocation costs to new premises, raising questions about the reasonableness of these costs in relation to the costs of completing the building and whether the period for additional rent should extend beyond the termination date of the existing lease. The matter was heard in the Court of Appeal of New South Wales.

The primary legal issues before the court were: first, whether an implied term existed in the lease obliging the landlord to complete the building in accordance with the interim occupation certificate within a reasonable time; and second, concerning the assessment of damages, whether the cost of relocation was so far in excess of the costs for completing the building as to be unreasonable compensation, and whether the period for claiming additional rent should be limited to the date of termination of the existing lease.

The court considered the principles of implied terms in contracts, particularly in the context of leases for partly completed developments. It reasoned that the nature of the agreement and the circumstances surrounding its formation supported the implication of a term requiring the landlord to complete the building to a stage where it could be occupied in accordance with the interim occupation certificate within a reasonable time. Regarding damages, the court assessed the reasonableness of the relocation costs, balancing them against the landlord's breach and the respondent's losses. The court also determined the appropriate period for which additional rent could be claimed, aligning it with the period of the respondent's loss.

The Court of Appeal allowed the appeal in part, setting aside an earlier order and entering judgment for the respondent in the sum of $342,824. The appeal was otherwise dismissed, and the appellant was ordered to pay the respondent's costs of the appeal. The respondent was also granted a certificate under the *Suitors' Fund Act 1951* (NSW) in respect of the unsuccessful part of the appeal, subject to eligibility.

Orders

Orders of the court

(1) Allow the appeal in part and set aside order 5 made in the Equity Division on 11 November 2005 and entered on 6 December 2005; (2) In lieu thereof, give judgment for the Respondent (the plaintiff below) in the sum of $342,824; (3) Otherwise dismiss the appeal; (4) Order the Appellant to pay the Respondent's costs of the appeal; (5) Grant the Respondent a certificate under the Suitors' Fund Act 1951 (NSW) in respect of that part of the appeal on which it was unsuccessful, if not disqualified pursuant to s 6(7).

Background

Background to the litigation

Full text does not contain this section.

Evidence

Evidence Before The Court

Full text does not contain this section.

Decision

Reasons for decision

Full text does not contain this section.

Ratio Decidendi

Legal Principle Established

Full text does not contain this section.