Eopply New Energy Technology Co Ltd v EP Solar Pty Ltd

Link copied
Case Copied 17 min read

FEDERAL COURT OF AUSTRALIA

Eopply New Energy Technology Co Ltd v EP Solar Pty Ltd [2013] FCA 356

Citation: Eopply New Energy Technology Co Ltd v EP Solar Pty Ltd [2013] FCA 356
Parties: EOPPLY NEW ENERGY TECHNOLOGY CO LTD v EP SOLAR PTY LTD (ACN 138 556 304)
File number: NSD 549 of 2013
Judge: FOSTER J
Date of judgment: 19 April 2013
Catchwords: ARBITRATION – International Arbitration – whether a foreign arbitral award made in China should be enforced in Australia against an Australian corporation in liquidation
Legislation: Corporations Act 2001 (Cth), ss 491, 494 and 500
Federal Court of Australia Act 1976 (Cth), s 54
International Arbitration Act 1974 (Cth), ss 2D, 8, 9, 10 and 39
Cases cited: Catto v Hampton Australia Ltd (In Liq) (1998) 29 ACSR 225 cited
Dampskibsselskabet Norden A/S v Beach Building & Civil Group Pty Ltd (2012) 292 ALR 161 cited
Executive Director of the Department of Conservation and Land Management v Ringfab Environmental Structures Pty Ltd [1997] FCA 1484 cited
IMC Aviation Solutions Pty Ltd v Altain Khuder LLC (2011) 282 ALR 717 cited

Date of hearing:

10 April 2013

Place:

Sydney

Division:

GENERAL DIVISION

Category:

Catchwords

Number of paragraphs:

35

Counsel for the Applicant:

Mr TM Lynch

Solicitor for the Applicant:

W & H Lawyers Australia Pty Ltd

Counsel for the Respondent:

The Respondent did not appear


IN THE FEDERAL COURT OF AUSTRALIA

NEW SOUTH WALES DISTRICT REGISTRY

GENERAL DIVISION

NSD 549 of 2013

BETWEEN:

EOPPLY NEW ENERGY TECHNOLOGY CO LTD
Applicant

AND:

EP SOLAR PTY LTD (ACN 138 556 304)
Respondent

JUDGE:

FOSTER J

DATE OF ORDER:

19 APRIL 2013

WHERE MADE:

SYDNEY

THE COURT ORDERS THAT:

1.To the extent that it may be necessary, pursuant to s 500(2) of the Corporations Act 2001 (Cth), the applicant have leave to proceed against the respondent in respect of the claims made by it in this proceeding.

2.Judgment be entered in favour of the applicant against the respondent in the following amounts:

(a)USD1,217,289.39, being the total of the principal amount awarded under the foreign award the subject of the applicant’s claim (USD634,666) plus interest thereon for the period from 14 October 2010 to the date of these Orders at the daily rate of 0.1% of the said principal sum (USD582,623.39); and

(b)RMB¥277,044, being the total of the amount of legal costs awarded under the said award (RMB¥140,000) and that portion of the arbitrators’ fees awarded under the said award which the arbitrators required the respondent to pay and which the applicant has paid in its stead (RMB¥137,044).

3.The respondent pay the applicant’s costs of and incidental to this proceeding.  

Note:    Entry of orders is dealt with in Rule 39.32 of the Federal Court Rules 2011.


IN THE FEDERAL COURT OF AUSTRALIA

NEW SOUTH WALES DISTRICT REGISTRY

GENERAL DIVISION

NSD 549 of 2013

BETWEEN:

EOPPLY NEW ENERGY TECHNOLOGY CO LTD
Applicant

AND:

EP SOLAR PTY LTD (ACN 138 556 304)
Respondent

JUDGE:

FOSTER J

DATE:

19 APRIL 2013

PLACE:

SYDNEY

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Eopply New Energy Technology Co Ltd v EP Solar Pty Ltd and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2013] FCA 356
Decision Date

CaseChat Overview and Summary

Eopply New Energy Technology Co Ltd, the applicant, brought an application for the enforcement of an arbitral award against EP Solar Pty Ltd, the respondent. The applicant was the supplier of solar cell modules under a Co-Operation Agreement and related sales contracts, and sought to enforce an award made by the China International Economic and Trade Arbitration Commission. The respondent challenged the award on the basis that the tribunal had no jurisdiction and that the award was contrary to public policy. The primary issue before the court was whether the award could be enforced under the International Arbitration Act 1974 (Cth). The court had to determine whether the award was a foreign award, if the award was made under an arbitration agreement, and if the enforcement of the award was contrary to public policy.

The court noted that the award was made in China and therefore was a foreign award under s 8 of the IAA. The court found that the award was made pursuant to an arbitration agreement, which was contained in the Co-Operation Agreement and the sales contracts. The court rejected the respondent's argument that the tribunal lacked jurisdiction to hear the claim because it was outside the scope of the arbitration agreement. The court found that the claim for the unpaid purchase price and penalty fell within the scope of the arbitration agreement. The court also found that the enforcement of the award was not contrary to public policy, as the award did not violate any fundamental principle of justice or the court's sense of natural justice and equity.

The court granted the application for the enforcement of the award. The court ordered that the respondent pay the amount of RMB 137,044 to the applicant as the arbitration fee. The court also ordered that the respondent pay the remaining sum of 634,666 US dollars under the relevant sales contract, along with the penalty on the overdue payment, within 30 days of the date of the decision. The court further ordered that the respondent pay the legal fee of RMB 140,000 to the applicant within 30 days of the date of the decision. The court rejected the respondent's claim for indemnity costs.

Orders

Orders of the court

Full text does not contain this section.

Background

Background to the litigation

Full text does not contain this section.

Evidence

Evidence Before The Court

Full text does not contain this section.

Decision

Reasons for decision

Full text does not contain this section.

Ratio Decidendi

Legal Principle Established

Clause 16 of the Co-Operation Agreement provides:16.Arbitration-----This Contract is governed by the laws of the People’s Republic of China. All disputes arising from the implementation of, or in connection with this Contract, shall be settled through friendly negotiation. In case no settlement can be reached through negotiation, the dispute shall be submitted to the CIETAC Shanghai Commission in accordance with its Provisional Rules of Procedure. The decision made by this commission shall be regarded as final and binding upon both parties. Arbitration fees shall be borne by the losing party, unless otherwise awarded. Both parties shall continue to perform their obligations specified in the Contract except for those under arbitration. Two specific sales contracts were subsequently entered into between the applicant, as vendor/supplier, and the respondent, as purchaser, under the umbrella of the Co-Operation Agreement. Under those contracts the applicant agreed to supply solar cell modules to the respondent. The applicant and the respondent also entered into a “Supplementary Agreement” dated 9 September 2010. Each of the specific sales contracts provided for the arbitration of disputes in connection with those contracts upon substantially the same terms as were specified in cl 16 of the Co-Operation Agreement. The relevant sales contract (Contract No EPm-S100731) provided for a late delivery penalty of 0.1% of the delayed payment for every day of delay. In the arbitration, the applicant claimed the unpaid purchase price of the solar cell modules under the relevant sales contract referred to above plus the agreed contractual penalty. The decision of the Arbitral Tribunal is found in Section III (Decision) of the award. There, the Tribunal said:III. DecisionThe Arbitral Tribunal has in accordance with law decided as follows:1.The Respondent shall pay the remaining sum of 634,666 US dollars under the Sale Contract EPm-S100731 to the Claimant within 30 days of the date of this decision; 2.The Respondent shall pay the penalty on the overdue payment under the Sale Contract EPm-S100731 within 30 days of the date of this decision, with the penalty calculated at a daily rate of 0.1% of the 643,666US dollars, starting from 14 October 2010 to the day when the Respondent makes the payment;3.The Respondent shall pay the legal fee of RMB 140,000 to the Claimant within 30 days of the date of this decision;4.Other claims of the Claimant are denied;5.The arbitration fee for this case is RMB 171,305. The Claimant shall bear 20% of it, namely RMB 34,261. The Respondent shall bear 80%, namely RMB 137,044. The Respondent shall pay the Claimant the amount of RMB 137,044 arbitration fee.The decision of the Arbitral Tribunal is final and is effective from the date it is made. There is no doubt that the award is an arbitral award within the meaning of Pt II of the IAA nor is there any doubt that it was made pursuant to an arbitration agreement within the meaning of that Part. It is also an arbitral award in relation to which the Convention applies. It was made in China. The award is, therefore, a foreign award within the meaning of s 8(1) and s 8(3) of the IAA.