QUEENSLAND CIVIL AND
ADMINISTRATIVE TRIBUNAL


CITATION:

Debono v Kellahan & Anor [2022] QCAT 317

PARTIES:

Michael david debono

(Applicant)

v

drew kellahan

(First Respondent)

and

MASpid pty ltd ATF the maspid family trust

(Second Respondent)

APPLICATION NO/S:

BDL087-20

MATTER TYPE:

Building matters

DELIVERED ON:

31 August 2022

HEARING DATE:

16 March 2022

HEARD AT:

Cairns

DECISION OF:

Member Taylor

ORDERS:

1.     The Respondents’ ‘Application to extend or shorten a time limit or for waiver of compliance with procedural requirement’ dated 20 June 2022, made in this proceeding after the hearing and whilst the decision was reserved, is dismissed.

2.     The Applicant’s claim against the First Respondent is dismissed.

3.     The Applicant’s claim for interest is dismissed.

4.     The Applicant’s claim for costs is dismissed.

5.     The Second Respondent is to pay to the Applicant $8,637.70 as monies due and owing under a contract.

6.     The Respondents’ counterclaim against the Applicant is dismissed.

CATCHWORDS:

CONTRACTS – BUILDING ENGINEERING AND RELATED CONTRACTS – THE CONTRACT – CONSTRUCTION OF PARTICULAR CONTRACT AND IMPLIED CONDITIONS – DISCHARGE OF CONTRACT ON DEFAULT AND LIKE GROUNDS – where the contract document contained an ambiguity as to the identification of the contracting party – where the contractor suspended the works under the contract for default in payment – where each party purported to terminate the contract

CONTRACTS – BUILDING ENGINEERING AND RELATED CONTRACTS – REMUNERATION – RECOVERY – Where the contract provided for staged payments – where certain stages completed prior to termination but not paid for in their entirety – Where contractor claimed payment upon termination of the contract.

Civil Proceedings Act 2011 (Qld), s 58

Queensland Civil and Administrative Tribunal Act 2009 (Qld), s 28(3), s 28(4), s 95

Advance Earthmovers Pty Ltd v Fubew Pty Ltd [2009] NSWCA 337

Aon Risk Services Australia Limited v Australian National University (2009) 239 CLR 175
Codelfa Construction Pty Ltd v State Rail Authority (NSW) (1982) 149 CLR 337
Mann v Paterson Constructions Pty Ltd (2019) 267 CLR 560
McDonald & Anor v Dennys Lascelles Limited (1933) 48 CLR 457
Minister for Immigration and Citizenship v SZGUR (2011) 241 CLR 594
Minister for Immigration and Border Protection v WZARH (2015) 256 CLR 326
Sullivan v Department of Transport (1978) 20 ALR 323

WWM & S Pty Ltd t/as Vine 21 v Fenwicks Suppliers Pty Ltd [2016] QCATA 63

APPEARANCES & REPRESENTATION:

Applicant:

Self-represented

First Respondent:

Self-represented

Second Respondent:

Mr Drew Kellahan - Director

REASONS FOR DECISION

The Contest between the parties

  1. Mr Debono presses a claim for payment of an amount said to be owing under contract, alternatively an award for damages, and interest thereon. In commencing this proceeding that claim was $8,637.70 owing under the contract, $3,000 for loss of profits, interest on the aggregate of those two figures at 4.75% per annum pursuant to s58 of the Civil Proceedings Act 2011 (Qld) but unquantified. He also sought an order for costs, also unquantified. The quantum of the claim changed as the proceeding unfolded.

  2. Mr…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Debono v Kellahan and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2022] QCAT 317
Decision Date

CaseChat Overview and Summary

The applicant, Michael David Debono, brought an action against the first respondent, Drew Kellahan, and the second respondent, MASpid Pty Ltd A/F The MASpid Family Trust (MASpid), seeking payment of an amount said to be owing under a contract, alternatively an award for damages, and interest thereon. The application was defended by both respondents. A counterclaim was also raised by the respondents seeking payment from the applicant for additional costs said to have been incurred in completing the pool construction, and an order for rectification of the depth of the pool alternatively an assessment of damages for loss of amenity in the use of the pool, interest, and any other order deemed fit.The issues which arose in the proceeding were firstly the proper respondent in the proceeding. It was determined that the proper respondent was MASpid and not Mr Kellahan. Secondly, it was determined that the contract was lawfully terminated by MASpid on 23 January 2020 for the applicant's failure to diligently carry out the work and maintain reasonable progress in the performance of the work. Thirdly, it was determined that the applicant's entitlement to be paid his contract claim was $8,637.70 and that he was not entitled to interest thereon. Fourthly, it was determined that the counterclaim was to be dismissed in its entirety. Finally, it was determined that the applicant's claims for costs were to be dismissed.The first respondent's application to extend or shorten a time limit or for waiver of compliance with procedural requirement was dismissed. The applicant's claim against the first respondent was dismissed. The applicant's claim for interest was dismissed. The applicant's claim for costs was dismissed. The second respondent was to pay to the applicant $8,637.70 as monies due and owing under a contract. The respondents' counterclaim against the applicant was dismissed.

Orders

Orders of the court

Full text does not contain this section.

Background

Background to the litigation

Full text does not contain this section.

Evidence

Evidence Before The Court

Full text does not contain this section.

Decision

Reasons for decision

Full text does not contain this section.

Ratio Decidendi

Legal Principle Established

Full text does not contain this section.